Assess and price a variation
When a change is instructed, capture it, price the added or omitted work from your rates, check the programme and cost impact, and issue the variation for agreement so it is recovered rather than absorbed.
How it works, step by step
5 steps across the platform - what you do at each one, and why it matters.
Capture the instructed change
Change ordersLog the change the moment it is instructed: what was asked, who asked, the date, and the drawing or instruction reference, so the variation has a clear origin before any work is done to it.
Why: A change that is worked on site but never written down is the one that gets argued about later. Logging it at the instruction is what makes the claim provable instead of a memory.
Price the added and omitted work
BOQMeasure the work added and the work omitted, and price both from your BOQ rates so the variation shows a net figure built on the same rates the contract was won on.
Why: Pricing a change from the agreed rates, and pricing the omissions as honestly as the additions, is what keeps the variation defensible and gets it agreed without a fight over made-up numbers.
Check the cost and programme impact
ValueAdd the priced change into the value picture to see its effect on the forecast, and note any time it adds to the programme so any extension of time is claimed alongside the money.
Why: A change costs more than its own line when it delays other trades. Pricing the money and flagging the time together is what stops a paid variation quietly causing an unpaid delay.
Issue the variation for agreement
ContractsSend the priced variation to the client or contract administrator under the contract terms, with the measure and rates as backup, and track it through to a signed agreement.
Why: A variation that is priced but never formally issued is work you have done for free. Getting it agreed in writing is what turns a change into recovered cost instead of absorbed loss.
Report the variation position
ReportsRoll the variation into the change position report so the running total of instructed, priced and agreed changes is visible against the contract sum at any time.
Why: One variation is easy to follow, thirty are not. A live report of where every change stands is what stops agreed value slipping out of sight and never getting into an application.