Cazuri / Comercial și contracte
Comercial și contracte

Evaluarea unui compensation event și a unei contract instruction JBCC

Stabilește pe ce contract ești, dă notificarea pe care o cere acel contract în zilele pe care ți le dă, evaluează modificarea după regulile acelui contract, și rezolvă și timpul și banii, în loc să le duci în decontul final.

7 pași13 minAntreprenor generalConsultanță costuri / QSBirou de management de proiect / construcție

Cum funcționează, pas cu pas

7 pași în cadrul platformei - ce faceți la fiecare și de ce contează.

1

Read the change machinery off the contract

Contracte

Establish which form the job runs on and write down the periods that go with it. On NEC that is eight weeks to notify a compensation event under clause 61.3 and three weeks to submit a quotation under clause 62.3. Under the JBCC principal building agreement it is twenty working days to give notice of a claim for revision of the date for practical completion under clause 23.4.2, twenty working days to give notice of expense and loss under clause 26.5, and forty working days to submit the substantiated claim in either case.

Captură de ecran, pasul 1: Read the change machinery off the contract (Contracte, Evaluarea unui compensation event și a unei contract instruction JBCC)
Contracte: Read the change machinery off the contract

De ce: Both forms make a late notice fatal rather than untidy. NEC clause 61.3 removes the entitlement to a change in the Prices and the Completion Date where the Contractor did not notify in time, and clause 23.4.2 of the JBCC agreement forfeits the claim. The periods are the first thing to know on a job and the last thing anyone looks up once the argument has started.

IntrareSigned contractContract dataRezultatContract regimeNotice periods
2

Put the event on the early warning register

Registrul riscurilor

Log the matter the moment somebody sees it coming: what it is, what it could cost in money and in time, and who has to do something about it. On NEC this is the early warning register and it feeds the early warning meeting, where both sides look for ways to avoid or reduce the effect before anyone prices anything.

Captură de ecran, pasul 2: Put the event on the early warning register (Registrul riscurilor, Evaluarea unui compensation event și a unei contract instruction JBCC)
Registrul riscurilor: Put the event on the early warning register

De ce: The early warning register is the one part of NEC that is cheaper for both parties than the alternative, because the assessment of a compensation event can take into account what would have happened had the warning been given. There is no equivalent clause in the JBCC agreement, but there is no reason to run a JBCC job without the register either: a change seen four weeks out is a change somebody can still design around.

IntrareSite eventCurrent programmeRezultatEarly warning entryMeeting actions
3

Give the notice, and give it in writing

Corespondență

Issue the notice the contract asks for, naming the clause relied on, the cause, and the date you became aware. Under the JBCC agreement a claim for revision of the date for practical completion must go on to state the effect on the critical path and the extension asked for in working days, per clause 23.6, and that comes with the substantiated claim inside forty working days.

Captură de ecran, pasul 3: Give the notice, and give it in writing (Corespondență, Evaluarea unui compensation event și a unei contract instruction JBCC)
Corespondență: Give the notice, and give it in writing

De ce: Clause 17.5 of the JBCC principal building agreement gives an oral contract instruction no force or effect, so a change agreed on site and never written down is a change you did for free. The notice is also the only thing that stops the clock, and on both forms a notice that names no clause and no date is treated as correspondence rather than as a notice.

IntrareInstruction or eventDate of awarenessRezultatNotice issuedSubstantiation deadline
4

Open a change with a number and an owner

Ordine de schimbare

Open a numbered change carrying the instruction or the event, its clause, the notice date, the quotation or claim due date, and the person who owes the next move. Keep it open until both the money and the time have been settled, not until one of them has.

Captură de ecran, pasul 4: Open a change with a number and an owner (Ordine de schimbare, Evaluarea unui compensation event și a unei contract instruction JBCC)
Ordine de schimbare: Open a change with a number and an owner

De ce: Clause 23.8 of the JBCC agreement deems the principal agent's failure to act within twenty working days a refusal, which starts a dispute clock the contractor has to notice for itself. On NEC clause 64 lets the Project Manager assess the event where the quotation is not submitted or not accepted. Both are silences that cost the party that was not watching, and a register with an owner and a due date is what makes silence visible.

IntrareIssued noticeChanged scopeRezultatChange register entryStatus and owner
5

Value the change on the rules the contract gives

Modificări contract

Under the JBCC principal building agreement work through clause 26.2 in order: work of a similar character at the rates in the priced document, work that is not of a similar character at rates based on those rates, and only where neither applies the actual cost of labour, plant and materials plus a ten per cent mark-up, with omissions taken out at priced document rates. On NEC the change to the Prices is assessed on the effect on Defined Cost plus the Fee, forecast forward rather than measured back.

Captură de ecran, pasul 5: Value the change on the rules the contract gives (Modificări contract, Evaluarea unui compensation event și a unei contract instruction JBCC)
Modificări contract: Value the change on the rules the contract gives

De ce: These are two genuinely different theories of value and using the wrong one loses real money in a predictable direction. A JBCC valuation reaches cost plus ten per cent only after the bill rates have been ruled out, so a contractor who starts at cost concedes the argument. An NEC assessment is a forecast, so a contractor who waits to measure the actual cost has valued it on the wrong basis and usually late.

IntrarePriced document ratesLabour, plant and materialsRezultatValuationStated basis
6

Show the delay on the programme, not in a letter

Program 4D

Take the accepted programme, put the event into it and show what moves on the critical path and by how much. On NEC the effect on the Completion Date belongs in the same quotation as the money. Under the JBCC agreement it is a separate claim, and clause 23.1 lists the grounds that revise the date without adjusting the contract value while clause 23.2 lists those that revise it with an adjustment.

De ce: The penalty for late completion under clause 24.0 of the JBCC agreement runs from the revised date for practical completion, and it is deducted through the payment certificates. An extension of time that was never granted because nobody demonstrated the critical path is a penalty paid every week until the job ends, and the difference between the clause 23.1 and clause 23.2 grounds is whether you also get paid for the time.

IntrareAccepted programmeDelay evidenceRezultatExtension claimedRevised completion date
7

Get the settled amount into the next certificate

Finanțe

Carry the agreed valuation into the next payment certificate rather than holding it for the final account, and close the change with the amount and the time both recorded against it.

Captură de ecran, pasul 7: Get the settled amount into the next certificate (Finanțe, Evaluarea unui compensation event și a unei contract instruction JBCC)
Finanțe: Get the settled amount into the next certificate

De ce: Clause 26.10 of the JBCC principal building agreement requires the final account within sixty working days of practical completion, and clause 26.11 deems it accepted if the contractor does not respond within thirty working days. A change settled month by month arrives at that deadline as arithmetic. A folder of unsettled changes arrives as a negotiation with a deadline attached to it.

IntrareAgreed valuationCertificate periodRezultatAmount certifiedFinal account line
Module

Modulele acestui playbook

7 / 190 module ale platformei

The market this case is written for

Africa de Sud

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • JBCC 6.2
  • SANS 1921

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Mai multe în Comercial și contracte