Amortise the anticipo before the last estimacion

Record what the anticipo is for and what secures it, invoice it with its own CFDI, spend it on what it was granted for, take the amortizacion off every estimacion in proportion, and read the outstanding balance every period so the last one is not the one that discovers it.

6 steps16 minGeneral contractorSpecialist subcontractorDeveloper / client

How it works, step by step

6 steps across the platform - what you do at each one, and why it matters.

1

Record what the anticipo is for and what secures it

Contracts

Put four things on the contract record: the amount of the anticipo, the parts it is granted in and the purpose of each, the fianza de anticipo that secures it, and the proportion at which it will be amortised, which follows from the anticipo against the contract amount rather than from a negotiation.

Contracts screen in OpenConstructionERP: Record what the anticipo is for and what secures it (Amortise the anticipo before the last estimacion)
Contracts: Record what the anticipo is for and what secures it

Why: Everything downstream reads these four numbers, and each of them lives in a different document today: the amount in the contract, the security with the insurer, the proportion in somebody's spreadsheet. Recorded once against the contract, the monthly amortizacion is computed rather than remembered, and the person who computes it in month nineteen does not have to have been there in month one.

InContract and its anticipo clauseFianza de anticipo as issuedOutAnticipo recorded with its purposesAmortisation proportion on record
2

Invoice the anticipo with its own CFDI

Finance

The anticipo is invoiced on its own CFDI when it is received, not netted quietly against the first estimacion. Record the UUID it was stamped with, because the CFDIs raised against later estimaciones have to relate back to it as the anticipo is consumed.

Finance screen in OpenConstructionERP: Invoice the anticipo with its own CFDI (Amortise the anticipo before the last estimacion)
Finance: Invoice the anticipo with its own CFDI

Why: Without that relationship the same peso is invoiced twice: once when the advance arrived and again inside the estimacion that repaid it. Both documents are stamped, both are real, and the excess is only found when somebody totals the year's CFDIs against the contract amount and gets a number larger than the contract.

InFianza delivered and acceptedAnticipo amount and IVAOutCFDI for the anticipo, stampedReference the estimaciones will relate to
3

Spend it on what it was granted for

Procurement

Place the orders the anticipo was granted for and mark them as such: the site installations, offices and stores and the movement of plant against the first part; the materials and the permanently installed equipment against the second. Keep the spend traceable back to the part that funded it.

Procurement screen in OpenConstructionERP: Spend it on what it was granted for (Amortise the anticipo before the last estimacion)
Procurement: Spend it on what it was granted for

Why: The anticipo is granted for named purposes under the LOPSRM, and the convocante can ask what it went on. That question is easy in month two and impossible in month twenty. There is a commercial reason as well as an audit one: an anticipo spent on general cash flow leaves the works with the materials still unbought and the repayment already running.

InAnticipo received, by partMobilisation and buying planOutOrders placed against the anticipoSpend traceable to its purpose
4

Take the amortizacion off in proportion, every period

Progress

Apply the recorded proportion to what the estimacion earned and deduct that, so a period that measures more repays more. Show the amortizacion as its own line on the estimacion and on the CFDI raised against it, next to the fondo de garantia rather than merged with it.

Progress screen in OpenConstructionERP: Take the amortizacion off in proportion, every period (Amortise the anticipo before the last estimacion)
Progress: Take the amortizacion off in proportion, every period

Why: A flat monthly deduction is the standard error and it fails in both directions. Too small and the works finish with the anticipo still outstanding, which turns the final estimacion into a debt; too large and it takes back the working capital the anticipo was granted to provide, in the months the job most needs it. Proportional repayment is self correcting and needs nobody to watch it.

InEstimacion for the periodAmortisation proportionOutAmortizacion for the periodNet amount payable
5

Read the outstanding balance every period

Event Reconciliation

Put the anticipo granted next to the amortizacion taken to date and carry the difference forward as a running balance, with the period it is projected to reach zero. Compare that period against the programmed completion every month, not once a year.

Why: The balance is the only figure that answers what you have really been paid, and it is the one nobody prints, because the estimacion shows the month and the ledger shows the cash. It also governs two other things: the fianza de anticipo stays alive while any of it is outstanding, and the unamortised part sits outside ajuste de costos, so a claim computed over the whole certified value quietly overstates itself.

InAmortizacion to dateAnticipo grantedOutAnticipo outstanding this periodPeriod it reaches zero
6

Reach zero before the finiquito, not during it

Close-out

Two or three periods out from completion, check that the remaining work is enough to absorb the remaining balance at the contract proportion. Where it is not, deal with it while there are still estimaciones to deal with it in, and take the settled balance into the finiquito rather than discovering it there.

Close-out screen in OpenConstructionERP: Reach zero before the finiquito, not during it (Amortise the anticipo before the last estimacion)
Close-out: Reach zero before the finiquito, not during it

Why: An anticipo still outstanding when the works finish stops being an advance and becomes a debt, payable in cash rather than out of work, and it holds the fianza de anticipo open and its premium running. Found three periods early it is an adjustment to the amortisation; found at the finiquito it is a cheque.

InBalance at the last estimacionWork left to certifyOutAnticipo fully amortisedFianza de anticipo clear to cancel
Modules

Modules in this playbook

6 / 190 platform modules

The market this case is written for

Mexico

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CFDI 4.0
  • Ley de Obras Publicas

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.