Mõõda hoone mahutabel ASAQS-i standardsüsteemi järgi

Võta mahud joonistelt, ehita mahutabel üles selles tööliikide järjekorras, mida standardsüsteem kasutab, hinnasta Bill No 1 üldkulud püsitasudena, väärtusest sõltuvate ja ajast sõltuvate tasudena, ning väljasta hinnastamisdokument, mille alusel töövõtja saab pakkumuse teha, ilma et ta peaks sinult küsima, mida üks hind katab.

7 sammu14 minKulunõustamine / QSPeatöövõtjaArendaja / klient

Kuidas see töötab, samm-sammult

7 sammu läbi platvormi - mida teete igas ja miks see loeb.

1

Take the quantities off the drawings

PDF-mõõtmised

Scale the tender drawings, measure element by element and keep each measurement attached to the sheet and the area it came from, so a quantity can be traced back to the line on the drawing that produced it.

Miks: A bill without a measurement trail cannot be remeasured, and remeasurement is exactly what clause 26.9 of the JBCC principal building agreement asks for when quantities in the priced document turn out to be wrong. Quantities that can be pointed back at a drawing settle that in an afternoon; quantities that exist only as totals turn it into a dispute.

SisendTender drawingsSpecificationVäljundMeasured quantitiesMeasurement trail
2

Build the bill in the standard trade order

Mahutabel

Lay the bill out in the trade sections the ASAQS Standard System of Measuring Building Work uses, write each item description to the unit and the coverage rule that section gives it, and keep civil engineering work in its own bill measured to SANS 1200.

Miks: The standard system exists so that an item description carries a known coverage: what the rate includes and what has to be measured separately. A bill written in a house style makes every tenderer guess at that boundary, and a bill priced on different guesses is not a comparison of prices, it is a comparison of assumptions.

SisendMeasured quantitiesMeasurement standardVäljundStructured billItem descriptions
3

Price Bill No 1 in the three charge categories

Ettevalmistustööd

Set out the preliminaries as Bill No 1 and split every item into the category it belongs to: fixed charges that happen once regardless of value or time, value related charges that move with the contract value, and time related charges that move with the construction period.

Miks: Clause 26.9 of the JBCC principal building agreement adjusts preliminaries on exactly this split when the contract value or the period changes, and a lump sum preliminaries figure gives it nothing to work with. A contractor who has priced site establishment as a fixed charge and site management as a time related charge gets paid for an extension of time; one who lumped them together argues for it.

SisendConstruction periodSite constraintsVäljundBill No 1Three charge categories
4

Build the rates from labour, material and plant

Koostised

Price each item from a written build-up rather than from memory: the labour constant, the material with its waste allowance, and the plant the item needs, so the rate can be taken apart again by anyone who asks.

Miks: Clause 26.2 of the JBCC principal building agreement values work of a similar character at the rates in the priced document, and work that is not similar at rates based on them. Both of those need a rate you can open up. A rate held in one estimator's head prices the tender and then cannot value a single instruction for the next two years.

SisendBill itemsLabour and material pricesVäljundRate build-upsPriced items
5

Set the markups and decide on price adjustment

Mahutabel

In the bill's Markups & Overheads panel, load the South African markup template, set overheads and profit against the cost element each belongs to, and decide whether the contract carries contract price adjustment. Where it does, the adjustment is the Haylett formula worked on the Statistics South Africa work group indices named in the contract data.

Miks: A fixed price bid on a two year building contract is a bet on the rand price of steel and cement, and contract price adjustment is the mechanism the market uses instead of that bet. Deciding it at tender rather than at the first cement increase is what keeps the decision commercial rather than adversarial, and clause 26.9 of the JBCC principal building agreement expects the basis to be in the priced document already.

SisendDirect costCPAP indicesVäljundMarkup ratesTender sum
6

Run the bill through validation before it goes out

Valideerimine

Check the bill for the faults that survive a read-through: an item with a unit that does not match its description, a quantity of zero left in from a superseded drawing, a rate that is an order of magnitude away from its neighbours, a section that carries no preliminaries at all.

Miks: An error in a bill of quantities issued for tender is not a private mistake. Under clause 23.2 of the JBCC principal building agreement an inaccurate quantity in the priced document is a ground for revising the date for practical completion with an adjustment of the contract value, so the employer pays for it twice, in money and in time.

SisendPriced billValidation rulesVäljundValidation reportCorrected items
7

Issue the pricing document and its summary

Aruanded

Export the bill as the pricing document tenderers price into, with the bill summary that carries the section totals, the preliminaries and the provisional sums, budgetary allowances and prime cost amounts stated separately.

Miks: Clause 17.1.13 of the JBCC principal building agreement lets the principal agent instruct the expenditure of budgetary allowances, prime cost amounts and provisional sums, and clause 26.9 adjusts them against what was actually spent. That only works if they were shown separately at tender. A bill that buries them inside trade totals cannot be adjusted without reopening the whole price.

SisendValidated billTenderer listVäljundPricing documentBill summary
Moodulid

Selle tegevusjuhendi moodulid

6 / 190 platvormi moodulit

The market this case is written for

Lõuna-Aafrika Vabariik

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • JBCC 6.2
  • SANS 1921

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Rohkem valdkonnas Kalkuleerimine ja hindamine

Kalkuleerimine ja hindamine

Määra reserv kulude riskist

Muuda ühepunktiline hinnang vahemikuks, jooksuta Monte Carlo tõeliselt ebakindlate ridade ül…

3 sammu11 minAva