Revisar un presupuesto antes de enviarlo
Pasa un presupuesto valorizado por las reglas de validación, resuelve cada advertencia y err…
Take the quantities off the drawings, build the bill in the trade order the standard system uses, price Bill No 1 preliminaries as fixed, value related and time related charges, and issue a pricing document a contractor can tender on without asking you what a rate covers.
7 pasos a lo largo de la plataforma - qué haces en cada uno y por qué importa.
Scale the tender drawings, measure element by element and keep each measurement attached to the sheet and the area it came from, so a quantity can be traced back to the line on the drawing that produced it.
Por que: A bill without a measurement trail cannot be remeasured, and remeasurement is exactly what clause 26.9 of the JBCC principal building agreement asks for when quantities in the priced document turn out to be wrong. Quantities that can be pointed back at a drawing settle that in an afternoon; quantities that exist only as totals turn it into a dispute.
Lay the bill out in the trade sections the ASAQS Standard System of Measuring Building Work uses, write each item description to the unit and the coverage rule that section gives it, and keep civil engineering work in its own bill measured to SANS 1200.
Por que: The standard system exists so that an item description carries a known coverage: what the rate includes and what has to be measured separately. A bill written in a house style makes every tenderer guess at that boundary, and a bill priced on different guesses is not a comparison of prices, it is a comparison of assumptions.
Set out the preliminaries as Bill No 1 and split every item into the category it belongs to: fixed charges that happen once regardless of value or time, value related charges that move with the contract value, and time related charges that move with the construction period.
Por que: Clause 26.9 of the JBCC principal building agreement adjusts preliminaries on exactly this split when the contract value or the period changes, and a lump sum preliminaries figure gives it nothing to work with. A contractor who has priced site establishment as a fixed charge and site management as a time related charge gets paid for an extension of time; one who lumped them together argues for it.
Price each item from a written build-up rather than from memory: the labour constant, the material with its waste allowance, and the plant the item needs, so the rate can be taken apart again by anyone who asks.
Por que: Clause 26.2 of the JBCC principal building agreement values work of a similar character at the rates in the priced document, and work that is not similar at rates based on them. Both of those need a rate you can open up. A rate held in one estimator's head prices the tender and then cannot value a single instruction for the next two years.
In the bill's Markups & Overheads panel, load the South African markup template, set overheads and profit against the cost element each belongs to, and decide whether the contract carries contract price adjustment. Where it does, the adjustment is the Haylett formula worked on the Statistics South Africa work group indices named in the contract data.
Por que: A fixed price bid on a two year building contract is a bet on the rand price of steel and cement, and contract price adjustment is the mechanism the market uses instead of that bet. Deciding it at tender rather than at the first cement increase is what keeps the decision commercial rather than adversarial, and clause 26.9 of the JBCC principal building agreement expects the basis to be in the priced document already.
Check the bill for the faults that survive a read-through: an item with a unit that does not match its description, a quantity of zero left in from a superseded drawing, a rate that is an order of magnitude away from its neighbours, a section that carries no preliminaries at all.
Por que: An error in a bill of quantities issued for tender is not a private mistake. Under clause 23.2 of the JBCC principal building agreement an inaccurate quantity in the priced document is a ground for revising the date for practical completion with an adjustment of the contract value, so the employer pays for it twice, in money and in time.
Export the bill as the pricing document tenderers price into, with the bill summary that carries the section totals, the preliminaries and the provisional sums, budgetary allowances and prime cost amounts stated separately.
Por que: Clause 17.1.13 of the JBCC principal building agreement lets the principal agent instruct the expenditure of budgetary allowances, prime cost amounts and provisional sums, and clause 26.9 adjusts them against what was actually spent. That only works if they were shown separately at tender. A bill that buries them inside trade totals cannot be adjusted without reopening the whole price.
6 / 190 módulos de la plataforma
Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.
Standards it follows
You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.
The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.
Pasa un presupuesto valorizado por las reglas de validación, resuelve cada advertencia y err…
Toma conceptos con precio de una base de datos de costos real, arma el catálogo con ellos, a…
Convierte una estimación de un solo valor en un rango, corre una simulación Monte Carlo sobr…