Sette sammen BDI under Acórdão 2622/2013-TCU

Flytt administração local ut av BDI og inn i orçamento, prissett risiko og garantier der de hører hjemme, fastsett skatteposten uten skattene som ikke skal være i den, og publiser en demonstrativo som viser hvert tall mot referanseintervallet.

6 trinn16 minHovedentreprenørKostnadsrådgivning / kalkulasjonSpesialisert underentreprenør

Slik fungerer det, steg for steg

6 trinn gjennom plattformen - hva du gjør i hvert og hvorfor det betyr noe.

1

Take administracao local out of the BDI

Rigg og drift

Price the site management, the canteiro de obras, the mobilizacao and the desmobilizacao as their own items with a quantity and a duration, and take the same cost out of the percentage. Keep the monthly items monthly, so a job that runs long is paid for the months it actually ran.

Skjermbilde, trinn 1: Take administracao local out of the BDI (Rigg og drift, Sette sammen BDI under Acórdão 2622/2013-TCU)
Rigg og drift: Take administracao local out of the BDI

Hvorfor: Acordao 2622/2013-TCU holds that administracao local is a direct cost of this job and belongs in the orcamento where it can be measured, not inside a BDI applied to work executed. The practical difference shows up on a job that is delayed for reasons that are not yours: as a measured monthly item the extra months are payable, as a percentage of the same work they are not, because the work did not grow.

InndataSite team and site facilitiesContract durationResultatAdministracao local as bill itemsSame cost out of the BDI
2

Price the risco, the seguro and the garantia

Avsetninger og reserver

Set the three terms separately and take each from something real: the risk term from the register of what could go wrong on this job, the insurance term from a broker's quote for this scope, the guarantee term from what the bank charges you for a performance bond of this size and length.

Skjermbilde, trinn 2: Price the risco, the seguro and the garantia (Avsetninger og reserver, Sette sammen BDI under Acórdão 2622/2013-TCU)
Avsetninger og reserver: Price the risco, the seguro and the garantia

Hvorfor: These three are the terms most often copied from the last job, and they are the ones that vary most between jobs. A guarantee priced on a two year contract and reused on a five year one is wrong by a factor the profit term cannot absorb, and it is invisible because the BDI still totals to a number that looks normal.

InndataRisk register for the jobInsurance and guarantee quotesResultatRisk, insurance and guarantee ratesReason recorded per rate
3

Set the tax term, and only the taxes that belong in it

Mengdefortegnelse

Build the tax term from the levies that fall on the invoice: the municipal service tax at the rate of the city where the work is done, the federal turnover contributions at the rate your regime charges, and the payroll contribution on turnover where the company has taken that option. Record which taxes you deliberately kept out and why.

Skjermbilde, trinn 3: Set the tax term, and only the taxes that belong in it (Mengdefortegnelse, Sette sammen BDI under Acórdão 2622/2013-TCU)
Mengdefortegnelse: Set the tax term, and only the taxes that belong in it

Hvorfor: Acordao 2622/2013-TCU holds that corporate income tax and the social contribution on net profit do not belong in the BDI, because they are levied on the result rather than on the invoice, and a contractor who includes them is paid for them by the client and again out of margin. Municipal rates also differ from city to city, so a term carried over from the last job is a real error even when the arithmetic is perfect.

InndataTax regime of the companyRate of the city where the work isResultatTax term of the BDI rateTaxes deliberately left out
4

Assemble the BDI in the markups panel

Mengdefortegnelse

In the bill's Markups & Overheads panel enter the central office overhead, the risk, the insurance, the guarantee, the finance charge, the profit and the tax term as separate figures, so the BDI is composed rather than typed. Check that the tax term divides rather than multiplies, because it is charged on the price you invoice and not on the cost you carry.

Skjermbilde, trinn 4: Assemble the BDI in the markups panel (Mengdefortegnelse, Sette sammen BDI under Acórdão 2622/2013-TCU)
Mengdefortegnelse: Assemble the BDI in the markups panel

Hvorfor: A BDI entered as one number cannot be checked, cannot be adjusted term by term when the client questions one of them, and hides the single most common arithmetic error in Brazilian estimating, which is applying the tax term as a simple addition. Composed, the same figure is a short table anybody can follow.

InndataRisk, insurance and guarantee ratesTax term of the BDI rateResultatBDI rate applied to the billPrice with the markup visible
5

Place every term against the reference range

Kalkylegrunnlag

Record on the basis of estimate where each term sits relative to the reference range published for this type of work, and write a sentence for any term that sits outside it. Say what about this job puts it there, in terms of the job rather than of the company.

Hvorfor: The ranges in Acordao 2622/2013-TCU are the first thing an analyst reaches for, and a term above the range with a written reason is a discussion while the same term without one is a finding. Writing it during the estimate costs a paragraph, writing it afterwards means reconstructing a decision nobody remembers making.

InndataBDI rate applied to the billReference range for this work typeResultatJustification report per termTerms outside the range named
6

Publish the demonstrativo with the proposal

Rapporter

Export the BDI as its own sheet showing every term and the formula that combines them, and send it with the proposal rather than on request. Where the edital asks for a differentiated BDI for supplied equipment, publish that one beside it instead of averaging the two.

Skjermbilde, trinn 6: Publish the demonstrativo with the proposal (Rapporter, Sette sammen BDI under Acórdão 2622/2013-TCU)
Rapporter: Publish the demonstrativo with the proposal

Hvorfor: A proposal carrying a bare percentage invites the analyst to reconstruct it, and their reconstruction will not be yours. Published as a sheet, the same figure arrives already explained, and a differentiated BDI for equipment supply is either declared or it is treated as an attempt to earn a construction markup on a purchase.

InndataJustification report per termPrice with the markup visibleResultatBDI demonstrativo for the proposalOne version everyone quotes
Moduler

Moduler i denne playbooken

5 / 190 plattformmoduler

The market this case is written for

Brasil

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • Lei 14.133
  • SINAPI
  • ABNT NBR 12721

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Mer innen Kommersielt og kontrakter

Kommersielt og kontrakter

Kjør en underentreprenørpakke

Tildel en fagpakke til en underentreprenør, legg den på en underentreprise med betalingsplan…

3 trinn11 minÅpne
Kommersielt og kontrakter

Betalingskrav og avstemming

Verdisett arbeidet utført denne perioden mot kontrakten, send inn kravet med dokumentasjonen…

3 trinn12 minÅpne