ضمانتیں مقرر کریں اور فائنل کمپلیشن تک کام چلائیں

کنٹریکٹ کی پیش کردہ security چنیں، اس کے بدلے میں employer کی پیمنٹ گارنٹی حاصل کریں، ہر سرٹیفکیٹ میں صحیح فیصد روکیں، اور کام کو practical completion، defects liability period اور final completion سے گزاریں تاکہ ہر ہولڈ اسی دن جاری ہو جو اسے ہونا چاہیے۔

7 مراحل14 منٹجنرل کنٹریکٹرڈیولپر / کلائنٹپروجیکٹ / تعمیراتی مینجمنٹ فرم

یہ کیسے کام کرتا ہے، قدم بہ قدم

7 قدم پوری پلیٹ فارم میں - ہر قدم پر کیا کرنا ہے اور یہ کیوں اہم ہے۔

1

Choose the security and write down the sequence

کنٹریکٹس

Read clause 11.0 and pick: a variable construction guarantee at ten per cent of the contract sum, a fixed construction guarantee at five per cent plus a five per cent payment reduction, or no guarantee with the employer withholding up to ten per cent under clause 11.4.1. Then write down the completion sequence the form uses, because on civil engineering work under the general conditions of contract for construction works there are three certificates rather than two.

اسکرین شاٹ، قدم 1: Choose the security and write down the sequence (کنٹریکٹس, ضمانتیں مقرر کریں اور فائنل کمپلیشن تک کام چلائیں)
کنٹریکٹس: Choose the security and write down the sequence

کیوں: The three choices cost different amounts of working capital at different moments, and a contractor that lets the employer decide has usually ended up with the most expensive one. The sequence matters for the same reason: under the general conditions of contract for construction works the defects liability period begins on the Certificate of Completion rather than at practical completion, so a contractor running that form on JBCC habits waits a year longer than it needs to for the second half of its retention.

اندر جاتا ہےSigned contractCash flow forecastباہر آتا ہےSecurity chosenCompletion sequence
2

Lodge your guarantee and ask for theirs

دستاویزات

Issue the construction guarantee on the form the contract carries, record its expiry, and note the clause 11.2.1 duty to maintain or replace it at least twenty working days before it lapses. Then pursue the employer's guarantee for payment, which clause 11.5.1 requires within fifteen working days of acceptance of the tender, the same period clause 11.1 gives you for yours.

اسکرین شاٹ، قدم 2: Lodge your guarantee and ask for theirs (دستاویزات, ضمانتیں مقرر کریں اور فائنل کمپلیشن تک کام چلائیں)
دستاویزات: Lodge your guarantee and ask for theirs

کیوں: The two securities are a pair and only one of them is usually chased. Clause 11.6 gives the contractor a ten working day notice and then the right to suspend where the employer's guarantee for payment is not given, and clause 11.10 has the contractor waive its lien over the works on receiving it, so a contractor that never received one has given up nothing and should not behave as though it had.

اندر جاتا ہےGuarantee formsGuarantor detailsباہر آتا ہےGuarantee lodgedGuarantee for payment
3

Hold the right percentage in every certificate

مالیات

Apply the reduction the chosen security calls for, certificate by certificate. Where the fixed construction guarantee was chosen, clause 25.12 pays ninety five per cent up to practical completion, ninety seven and a half per cent up to but excluding the final payment certificate, and one hundred per cent in it. Where no guarantee was given, clause 11.4.1 does the same job at ten per cent falling to two and a half.

اسکرین شاٹ، قدم 3: Hold the right percentage in every certificate (مالیات, ضمانتیں مقرر کریں اور فائنل کمپلیشن تک کام چلائیں)
مالیات: Hold the right percentage in every certificate

کیوں: This is the largest single amount of the contractor's money the employer holds and the easiest to lose track of, because it is spread across twenty certificates. Recording the percentage against every certificate with the event that releases it means the release happens on the certificate after that event rather than on the day somebody notices, and that difference is usually months of cash.

اندر جاتا ہےPayment certificatesSecurity chosenباہر آتا ہےAmount heldRelease dates
4

Give the notice and take the list that comes back

معائنے

Give the principal agent at least five working days notice of the anticipated inspection date under clause 19.2.2, walk the works, and take the list of outstanding items for practical completion issued under clause 19.3.1. Work it to zero and call the re-inspection.

اسکرین شاٹ، قدم 4: Give the notice and take the list that comes back (معائنے, ضمانتیں مقرر کریں اور فائنل کمپلیشن تک کام چلائیں)
معائنے: Give the notice and take the list that comes back

کیوں: Clause 19.4 of the JBCC principal building agreement gives the contractor a remedy for a principal agent who goes quiet. Where the list for practical completion or the certificate is not issued within five working days after the inspection period, the contractor gives notice, and if a further five working days pass, practical completion is deemed to have been achieved on the date of that notice. Every step of that is a written notice, so a contractor that phones instead has no date to count from and nothing to deem.

اندر جاتا ہےNotice of inspectionCompleted worksباہر آتا ہےList for practical completionInspection dates
5

Take practical completion and read what it changes

کلوز آؤٹ

Get the certificate of practical completion issued under clause 19.3.3, together with the list for completion under clause 19.3.4, and record the date on it. That date is the one the defects liability period, the penalty for late completion and the reduction in the security all count from.

کیوں: Practical completion moves several things at once: the employer becomes entitled to possession under clause 19.5, the penalty under clause 24.0 stops running, and the security steps down. Under the general conditions of contract for construction works the equivalent moment is split, and it is the Certificate of Completion, not practical completion, that returns the performance guarantee within fourteen days, starts the defects liability period and halves the retention.

اندر جاتا ہےCleared listRe-inspectionباہر آتا ہےCertificate of practical completionList for completion
6

Work the defects liability period to its end date

پنچ لسٹ

The defects liability period begins the calendar day after practical completion and ends ninety calendar days from that date, or when the list for completion has been dealt with, whichever is later. Under clause 21.3.1 the contractor rectifies no later than ten working days before it expires, so plan the last inspection well inside the ninety days.

اسکرین شاٹ، قدم 6: Work the defects liability period to its end date (پنچ لسٹ, ضمانتیں مقرر کریں اور فائنل کمپلیشن تک کام چلائیں)
پنچ لسٹ: Work the defects liability period to its end date

کیوں: Ninety calendar days is short, and the ten working day margin at the end of it is shorter still. A contractor that treats the period as three months of grace discovers in week eleven that the remaining items had to be finished in week ten, and the items it did not reach are the ones that keep the final completion certificate and the last of the security out of reach.

اندر جاتا ہےList for completionDefects reportedباہر آتا ہےItems closedPeriod end date
7

Get final completion certified and the security released

وارنٹیاں اور خامیوں کی ذمہ داری

After the last inspection the principal agent has ten working days under clause 21.6 to issue either a list for final completion or the certificate of final completion. Collect the subcontractor guarantees and warranties, which are ceded to the employer at final completion under clauses 21.10 and 21.11, and release what remains of the security.

اسکرین شاٹ، قدم 7: Get final completion certified and the security released (وارنٹیاں اور خامیوں کی ذمہ داری, ضمانتیں مقرر کریں اور فائنل کمپلیشن تک کام چلائیں)
وارنٹیاں اور خامیوں کی ذمہ داری: Get final completion certified and the security released

کیوں: Clause 21.12 makes the certificate of final completion conclusive evidence that the works are satisfactory, other than for latent defects, so it is worth having and worth having on a date you can prove. It is also the date the latent defects liability period in clause 22.0 is measured from, which makes it the single most important date to record at the end of a South African building contract.

اندر جاتا ہےRectified defectsSubcontractor warrantiesباہر آتا ہےCertificate of final completionWarranties ceded
ماڈیولز

اس سیناریو کے ماڈیولز

7 / 190 پلیٹ فارم ماڈیولز

The market this case is written for

جنوبی افریقہ

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • JBCC 6.2
  • SANS 1921

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Handover اور lifecycle میں مزید

Handover اور lifecycle

ہینڈ اوور اور کلوز آؤٹ کریں

کام صاف طریقے سے مکمل کریں: پنچ لسٹ کو صفر تک لے جائیں، تصدیق کریں کہ ہر معائنہ پاس ہوا اور…

5 مراحل14 منٹکھولیں
Handover اور lifecycle

ایز بلٹ اور O and M ہینڈ اوور

ایز بلٹ ریکارڈ اکٹھا کریں، ثابت کریں کہ کوالٹی فائل میں کوئی خلا نہیں، پھر ایک آپریشن اور می…

3 مراحل12 منٹکھولیں