Případy / Předání a životní cyklus
Předání a životní cyklus

Nastavte zajištění a doveďte dílo ke konečnému dokončení

Zvolte zajištění, které smlouva nabízí, získejte výměnou záruku objednatele za zaplacení, držte v každém certifikátu správné procento a proveďte dílo praktickým dokončením, záruční dobou a konečným dokončením tak, aby se každé zadržení uvolnilo v den, kdy má.

7 kroků14 minGenerální dodavatelDeveloper / klientProjektová / stavební manažerská firma

Jak to funguje, krok za krokem

7 kroků napříč platformou - co na každém uděláte a proč na tom záleží.

1

Choose the security and write down the sequence

Smlouvy

Read clause 11.0 and pick: a variable construction guarantee at ten per cent of the contract sum, a fixed construction guarantee at five per cent plus a five per cent payment reduction, or no guarantee with the employer withholding up to ten per cent under clause 11.4.1. Then write down the completion sequence the form uses, because on civil engineering work under the general conditions of contract for construction works there are three certificates rather than two.

Snímek obrazovky, krok 1: Choose the security and write down the sequence (Smlouvy, Nastavte zajištění a doveďte dílo ke konečnému dokončení)
Smlouvy: Choose the security and write down the sequence

Proč: The three choices cost different amounts of working capital at different moments, and a contractor that lets the employer decide has usually ended up with the most expensive one. The sequence matters for the same reason: under the general conditions of contract for construction works the defects liability period begins on the Certificate of Completion rather than at practical completion, so a contractor running that form on JBCC habits waits a year longer than it needs to for the second half of its retention.

VstupSigned contractCash flow forecastVýstupSecurity chosenCompletion sequence
2

Lodge your guarantee and ask for theirs

Dokumenty

Issue the construction guarantee on the form the contract carries, record its expiry, and note the clause 11.2.1 duty to maintain or replace it at least twenty working days before it lapses. Then pursue the employer's guarantee for payment, which clause 11.5.1 requires within fifteen working days of acceptance of the tender, the same period clause 11.1 gives you for yours.

Snímek obrazovky, krok 2: Lodge your guarantee and ask for theirs (Dokumenty, Nastavte zajištění a doveďte dílo ke konečnému dokončení)
Dokumenty: Lodge your guarantee and ask for theirs

Proč: The two securities are a pair and only one of them is usually chased. Clause 11.6 gives the contractor a ten working day notice and then the right to suspend where the employer's guarantee for payment is not given, and clause 11.10 has the contractor waive its lien over the works on receiving it, so a contractor that never received one has given up nothing and should not behave as though it had.

VstupGuarantee formsGuarantor detailsVýstupGuarantee lodgedGuarantee for payment
3

Hold the right percentage in every certificate

Finance

Apply the reduction the chosen security calls for, certificate by certificate. Where the fixed construction guarantee was chosen, clause 25.12 pays ninety five per cent up to practical completion, ninety seven and a half per cent up to but excluding the final payment certificate, and one hundred per cent in it. Where no guarantee was given, clause 11.4.1 does the same job at ten per cent falling to two and a half.

Snímek obrazovky, krok 3: Hold the right percentage in every certificate (Finance, Nastavte zajištění a doveďte dílo ke konečnému dokončení)
Finance: Hold the right percentage in every certificate

Proč: This is the largest single amount of the contractor's money the employer holds and the easiest to lose track of, because it is spread across twenty certificates. Recording the percentage against every certificate with the event that releases it means the release happens on the certificate after that event rather than on the day somebody notices, and that difference is usually months of cash.

VstupPayment certificatesSecurity chosenVýstupAmount heldRelease dates
4

Give the notice and take the list that comes back

Kontroly

Give the principal agent at least five working days notice of the anticipated inspection date under clause 19.2.2, walk the works, and take the list of outstanding items for practical completion issued under clause 19.3.1. Work it to zero and call the re-inspection.

Snímek obrazovky, krok 4: Give the notice and take the list that comes back (Kontroly, Nastavte zajištění a doveďte dílo ke konečnému dokončení)
Kontroly: Give the notice and take the list that comes back

Proč: Clause 19.4 of the JBCC principal building agreement gives the contractor a remedy for a principal agent who goes quiet. Where the list for practical completion or the certificate is not issued within five working days after the inspection period, the contractor gives notice, and if a further five working days pass, practical completion is deemed to have been achieved on the date of that notice. Every step of that is a written notice, so a contractor that phones instead has no date to count from and nothing to deem.

VstupNotice of inspectionCompleted worksVýstupList for practical completionInspection dates
5

Take practical completion and read what it changes

Uzavření

Get the certificate of practical completion issued under clause 19.3.3, together with the list for completion under clause 19.3.4, and record the date on it. That date is the one the defects liability period, the penalty for late completion and the reduction in the security all count from.

Proč: Practical completion moves several things at once: the employer becomes entitled to possession under clause 19.5, the penalty under clause 24.0 stops running, and the security steps down. Under the general conditions of contract for construction works the equivalent moment is split, and it is the Certificate of Completion, not practical completion, that returns the performance guarantee within fourteen days, starts the defects liability period and halves the retention.

VstupCleared listRe-inspectionVýstupCertificate of practical completionList for completion
6

Work the defects liability period to its end date

Seznam vad

The defects liability period begins the calendar day after practical completion and ends ninety calendar days from that date, or when the list for completion has been dealt with, whichever is later. Under clause 21.3.1 the contractor rectifies no later than ten working days before it expires, so plan the last inspection well inside the ninety days.

Snímek obrazovky, krok 6: Work the defects liability period to its end date (Seznam vad, Nastavte zajištění a doveďte dílo ke konečnému dokončení)
Seznam vad: Work the defects liability period to its end date

Proč: Ninety calendar days is short, and the ten working day margin at the end of it is shorter still. A contractor that treats the period as three months of grace discovers in week eleven that the remaining items had to be finished in week ten, and the items it did not reach are the ones that keep the final completion certificate and the last of the security out of reach.

VstupList for completionDefects reportedVýstupItems closedPeriod end date
7

Get final completion certified and the security released

Záruky a odpovědnost za vady

After the last inspection the principal agent has ten working days under clause 21.6 to issue either a list for final completion or the certificate of final completion. Collect the subcontractor guarantees and warranties, which are ceded to the employer at final completion under clauses 21.10 and 21.11, and release what remains of the security.

Snímek obrazovky, krok 7: Get final completion certified and the security released (Záruky a odpovědnost za vady, Nastavte zajištění a doveďte dílo ke konečnému dokončení)
Záruky a odpovědnost za vady: Get final completion certified and the security released

Proč: Clause 21.12 makes the certificate of final completion conclusive evidence that the works are satisfactory, other than for latent defects, so it is worth having and worth having on a date you can prove. It is also the date the latent defects liability period in clause 22.0 is measured from, which makes it the single most important date to record at the end of a South African building contract.

VstupRectified defectsSubcontractor warrantiesVýstupCertificate of final completionWarranties ceded
Moduly

Moduly v tomto playbooku

7 / 190 modulů platformy

The market this case is written for

Jihoafrická republika

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • JBCC 6.2
  • SANS 1921

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Více v kategorii Předání a životní cyklus

Předání a životní cyklus

Předání a uzavření

Dokončete zakázku načisto: dotáhněte seznam vad na nulu, potvrďte, že každá kontrola prošla…

5 kroků14 minOtevřít