Planning & controls

Build a 4D construction sequence

Link model elements to schedule activities, play the build order back as a 4D animation, check it actually works on the ground and use the same view to drive and report progress.

4 steps12 minGeneral contractorProject / construction managerBIM / digital consultant

How it works, step by step

4 steps across the platform - what you do at each one, and why it matters.

1

Open the model

BIM Viewer

Open the coordinated model and confirm elements are grouped the way the job is built - by zone, level and pour - so they can be tied to activities cleanly.

Why: A model organised by design discipline does not match how the site is sequenced. Grouping it the way the work happens is what makes a 4D link meaningful rather than cosmetic.

InCoordinated modelBaseline programmeOutModel ready to link
2

Link elements to activities

Schedule

Map each element or group to the schedule activity that builds it, so every part of the model knows when it goes up and comes down.

Why: The link is what turns a static model and a flat programme into a moving picture. It also flushes out the elements nobody scheduled and the activities with nothing to build.

InModel elementsSchedule activitiesOutElements linked to time
3

Play and review the sequence

Schedule

Play the sequence and watch the build order: check access stays open, cranes can reach, temporary works come and go in time, and nothing is built before what holds it up.

Why: Finding an out-of-sequence pour or a blocked access on screen costs an hour. Finding it on site costs a week and a standing crew. The 4D review is where that saving is made.

InLinked modelOutSequence reviewedTime clashes found
4

Track progress against it

Progress

Use the 4D view to mark what is built and compare it to the planned sequence, so progress is shown as coloured geometry the whole team can read at a glance.

Why: A planned-versus-built model tells a client more in one image than a page of percentages. It makes slippage impossible to hide and easy to talk about honestly.

InAgreed sequenceOutVisual progress