Casos prácticos / Comercial y contratos
Comercial y contratos

Valorar una variation bajo AS 4000

Establezca que existe una direction antes de que nadie la construya, mantenga el registro de costos mientras el trabajo ocurre, valórela en el orden que fija la cláusula 36, presente la claim dentro del plazo que permite el contrato, llévela a la siguiente progress claim se acuerde o no, y ajuste la suma contractual.

6 pasos16 minContratista generalSubcontratista especialistaConsultoría de costes / QSGestora de proyectos / construcción

Cómo funciona, paso a paso

6 pasos a lo largo de la plataforma - qué hacer en cada uno y por qué importa.

1

Establish there is a direction before it is built

Modificaciones

Raise the variation the day the change appears, with the date, who asked, what changed and whether a written direction from the Superintendent exists yet. Where it does not, ask for one and record that you asked, in writing, before the work starts.

Por que: Clause 36 makes the Superintendent's direction the thing that turns extra work into a variation, and an architect or a client representative walking the site is usually neither the Superintendent nor authorised to direct one. Work built on a conversation is work you are asking to be paid for as a favour, and the answer arrives after it is already in the building.

EntradaInstruction or site requestContract scopeResultadoVariation raised and datedDirected or awaiting a direction
2

Keep the record while the work is in front of you

Evidencia de reclamaciones

Collect the daily labour, plant and material records for the varied work as it happens, have them signed on site by the Superintendent's representative where the contract asks for that, and attach the photographs and the delivery dockets to the same entry.

Por que: Every valuation route in clause 36 except an agreed price ends up resting on what the work actually took. Records signed at the time settle that in a sentence; records assembled afterwards start a second argument about whether the record is true, and that one is lost even when the claim is good.

EntradaWork as it is carried outLabour, plant and materials usedResultadoDaywork records signedEvidence pack for the valuation
3

Value it in the order the clause sets

Presupuesto

Work down clause 36 in order rather than jumping to the answer you want. A price the parties have already agreed governs; failing that, the rates and prices in the contract, applied to the varied quantity; failing that, rates in the contract used as a basis where the work is comparable; and only where none of those reach it, reasonable rates and prices. Record which route the valuation used and why the ones above it did not apply.

Por que: Naming the route is what makes the number reviewable. A valuation that simply arrives at a figure invites the Superintendent to arrive at a different one, and there is then nothing in dispute except two opinions. A valuation that says which limb of the clause it used and why the earlier limbs did not fit can be disagreed with on a point, and points get resolved.

EntradaVariation raised and datedContract rates and pricesResultadoVariation valuedWhich valuation route was used
4

Lodge the claim inside the time bar

Modificaciones

Serve the claim in the form and inside the period the contract requires, and record the date it went. AS 4000 puts a notification requirement around claims other than progress claims in clause 41, and the Annexure may shorten the period further, so read the Annexure rather than assuming the printed default.

Por que: A time bar does not care whether the claim was good. It is the one defence a principal can run without engaging with the merits at all, and it succeeds on a date rather than on an argument. The claim that is worth the most is usually the one that took the longest to price, which is exactly the one that misses the window.

EntradaVariation valuedTime the contract allowsResultadoClaim lodged in timeDate of lodgement on record
5

Carry it into the progress claim, agreed or not

Finanzas

Include the valued variation in the next progress claim as its own line, showing what you claim and what has been certified, so an amount in dispute is a visible difference on one line rather than a shortfall on the total.

Por que: A variation held back until it is agreed is a variation that is never claimed and never certified, and the money sits with the contractor for the length of the job. Claiming it keeps it on the record, keeps it inside the payment machinery the contract and the state statute provide, and makes the disagreement about one line instead of the month.

EntradaClaim lodged in timeCurrent claim periodResultadoVariation in the progress claimDisputed amount visible
6

Adjust the contract sum and keep it running

Contratos

Post the agreed or determined amount against the contract so the contract sum moves as each variation closes, and keep the list of open variations with what each one is claimed at beside it.

Por que: A final account is either a running total that both parties have been reading all along or an event, and the event version takes months. Every variation closed as it happened is one fewer item in a negotiation held at the point where the contractor most needs the money and has the least leverage.

EntradaAgreed or determined amountContract sum beforeResultadoContract sum adjustedRunning final account
Módulos

Módulos de este playbook

5 / 190 módulos de la plataforma

El mercado para el que está escrito este caso

Australia

Todo en este caso sigue la forma en que la obra se mide, se valora y se paga en este mercado. Los documentos, el desglose de costes y las reglas de pago son los que se usan allí, no una versión genérica.

Normas que sigue

  • AS 4000
  • Security of Payment Act

No tienes que configurar nada de eso a mano. La primera vez que abres la plataforma te pregunta en qué mercado trabajas. Elige este y ajusta el idioma de la interfaz, carga la base de costes correspondiente, registra la clasificación de costes y añade un proyecto de ejemplo que puedes abrir enseguida.

Las comprobaciones de este mercado también vienen con la plataforma. Actívalas una vez y un presupuesto al que le falte algo que el mercado espera queda señalado mientras trabajas en él, no después de presentar la oferta.

Más en Comercial y contratos

Comercial y contratos

Solicitud de pago y conciliación

Valora la obra ejecutada este periodo frente al contrato, presenta la solicitud con su docum…