Casos prácticos / Obra y campo
Obra y campo

Gestionar deberes de PCBU superpuestos en una obra compartida

Identifique los riesgos y qué es reasonably practicable respecto de ellos, liste cada otro negocio que trabaja en la obra, acuerde por escrito quién hace qué donde los deberes se superponen, contrate a los trabajadores que realmente hacen el trabajo, lleve el registro diario, notifique lo que deba notificarse, y dé a los officers algo con qué ejercer due diligence.

7 pasos15 minContratista generalSubcontratista especialistaGestora de proyectos / construcciónPropietario / operador (FM)

Cómo funciona, paso a paso

7 pasos a lo largo de la plataforma - qué hacer en cada uno y por qué importa.

1

Name the risks and what is reasonably practicable about them

Seguridad

Work through the risks the job actually creates, eliminate what can be eliminated and minimise the rest, and write down the reasoning: how likely the harm is, how serious it would be, what is known about the risk and about ways of controlling it, and what those controls cost relative to that. Keep the reasoning with the control rather than only the control.

Por que: Reasonably practicable is a defined test in this Act, not a general appeal to common sense, and it is applied afterwards by someone reading a file. A control with no reasoning behind it is indistinguishable from a control that was chosen because it was cheap, and the difference between those two is the whole of a defence.

EntradaWork planned for the siteSite and its surroundingsResultadoRisks named and rankedControls and why they are enough
2

List every business the site has a duty alongside

Directorio de subcontratistas

Keep a live list of every business working on or into the site, not only the direct subcontractors: labour hire, plant hire with an operator, scaffolders, testing and surveying, the client's own trades. Record a named person for each, with the work they are here to do and the period they are here for.

Por que: You cannot consult, cooperate and coordinate with a business you have not written down, and the ones that get left off a list are exactly the ones that arrive for two days, do something high risk and leave. Plant hire with an operator is the classic: the operator is another PCBU's worker, working under your site rules, on your programme.

EntradaSubcontracts and hire agreementsWho is on site this monthResultadoEvery PCBU on the site listedA named person for each one
3

Agree who does what where the duties overlap

Gestión HSE

Take the risks that more than one business touches, scaffold and edge protection, traffic and pedestrian movements, services, lifting over other trades, and agree in writing who provides the control, who inspects it, who may alter it and how a change is told to everyone else. Review the agreement when the trades on site change, not only at the start.

Por que: The Act requires each PCBU to consult, cooperate with and coordinate activities with the others so far as their duties overlap, and it does not let any of them contract out of the duty itself. What an agreement can do is stop two businesses each assuming the other inspected the scaffold, which is the exact shape of most serious harm on a multi-trade site.

EntradaEvery PCBU on the site listedRisks more than one of them touchesResultadoWho does what, in writingRisks nobody had taken
4

Engage the people who actually do the work

Supervisión de Obra

Induct every crew onto the site controls and the agreement behind them, brief changes when they happen rather than at the next monthly meeting, and give workers a real route to raise a hazard, through health and safety representatives where the site has them. Record who was briefed on what and when.

Por que: Worker engagement and participation is a duty in its own right under this Act and not a courtesy, and it is also the cheapest source of information a site has. The person who knows the excavation is moving is the person standing in it, and whether that reaches the site office is a question about the route, not about the person.

EntradaWho does what, in writingCrews arriving on siteResultadoInductions and briefings recordedA route for workers to raise things
5

Keep the daily record the same way every day

Diario de obra

Record each day as it runs: who was on site, what work went on, the weather where it mattered, the safety observations made and what was done about them, and any change to a shared control. Close out the actions rather than only raising them.

Por que: A diary kept every day is evidence and a diary written up in the week after an incident is a liability, and the two are easy to tell apart. It is also the record that answers the only question an investigation really asks, which is what the business knew and when it knew it.

EntradaWhat happened on the dayWho was on siteResultadoDaily record kept as it happensActions raised and closed
6

Notify what the Act says must be notified

Formularios y listas de comprobación

Keep two notification routines running from the same set of forms. Particular hazardous construction work, such as deep excavation, work at height above the prescribed limit and certain lifting, has to be notified to the regulator at least 24 hours before it starts. A notifiable event, a death, a notifiable injury or illness or a notifiable incident, has to be notified as soon as possible after it happens, and the site left undisturbed except to help someone or make it safe.

Por que: These are the two duties most often discovered after the fact, and both carry offences of their own regardless of whether anyone was hurt. Disturbing a scene is the one that does lasting damage: it destroys the evidence that would have shown what the controls actually were, and the business that cleared the site is the business that cannot now prove anything about it.

EntradaEvent or hazardous work plannedWhat has to be notifiedResultadoNotification sent and loggedScene preserved where required
7

Give the officers something they can act on

Informes

Report to the people who govern the business, not only to the ones who run the site: what the risks across the portfolio are, what resources have been put against them, what events happened and what was done, and where the same hazard keeps coming back on different jobs. Show the actions that are still open as well as the ones closed.

Por que: An officer of a PCBU owes a personal duty to exercise due diligence, which means keeping up to date, understanding the operations and their hazards, and making sure the business has and uses appropriate resources and processes. That duty cannot be discharged from a summary that only carries good news, and a board that was never shown the open actions is a board that cannot say it knew.

EntradaSite records across projectsEvents, actions and notificationsResultadoWhat the officers are shownWhere the same risk keeps returning
Módulos

Módulos de este playbook

7 / 190 módulos de la plataforma

El mercado para el que está escrito este caso

Nueva Zelanda

Todo en este caso sigue la forma en que la obra se mide, se valora y se paga en este mercado. Los documentos, el desglose de costes y las reglas de pago son los que se usan allí, no una versión genérica.

Normas que sigue

  • NZS 3910
  • Construction Contracts Act

No tienes que configurar nada de eso a mano. La primera vez que abres la plataforma te pregunta en qué mercado trabajas. Elige este y ajusta el idioma de la interfaz, carga la base de costes correspondiente, registra la clasificación de costes y añade un proyecto de ejemplo que puedes abrir enseguida.

Las comprobaciones de este mercado también vienen con la plataforma. Actívalas una vez y un presupuesto al que le falte algo que el mercado espera queda señalado mientras trabajas en él, no después de presentar la oferta.

Más en Obra y campo

Obra y campo

Gestionar la jornada de obra

Cierra la jornada como es debido: anota el diario, imputa las horas de mano de obra y maquin…

4 pasos9 minAbrir
Obra y campo

Responder una RFI

Convierte una pregunta surgida en el tajo en una solicitud registrada, dirígela a la parte r…

3 pasos9 minAbrir