Juhtumid / Hankemenetlus ja hankimine
Hankemenetlus ja hankimine

Vii läbi pakkumine AS 4120 code of tendering'u alusel

Kutsu ainult pakkujaid, kellele annaksid lepingu, väljasta üks identne dokumendikomplekt tähtajaga, vasta igale küsimusele addendum'iga kõigile, ava alles pärast tähtaega, taseeri vastavad ja alternatiivsed pakkumised eraldi, ja anna leping registreeritud heakskiiduga, mitte teise hinnaringiga.

6 sammu15 minPeatöövõtjaKulunõustamine / QSProjekti- / ehitusjuhtimisbürooArendaja / klient

Kuidas see töötab, samm-sammult

6 sammu läbi platvormi - mida teete igas ja miks see loeb.

1

Invite only the tenderers you would actually award to

Alltöövõtjate kataloog

Build the invitation list from capability, current capacity, licence and insurance rather than from the last job's list, and keep it short enough that every name on it has a real chance. Record why each candidate is in or out.

Miks: The code asks a principal to invite only tenderers it is prepared to accept, and the reason is economic rather than moral. A tender costs a builder real money to price, so a list of eight where two were ever in contention teaches the market to load the price or to decline the next invitation, and the principal pays for it either way.

SisendMarket of available buildersCapability and capacityVäljundShortlist you would award toReasons the rest are out
2

Issue one identical set with a stated closing time

Hanked

Issue the same documents to every tenderer at the same time: the drawings and their revisions, the bill, the conditions of contract with the Annexure filled in, and the conditions of tendering, including the closing time and place, whether alternative tenders are accepted and on what terms, and how long the offer must stand open.

Miks: Everything the code protects flows from every tenderer pricing the same document. A revision that reached three of five is not a documentation slip, it is an unequal tender, and the only honest remedy once it is discovered is to extend the period for everyone and pay for the time.

SisendShortlist you would award toDrawings, bill and conditionsVäljundOne identical document set issuedClosing time and place stated
3

Answer a question once and send it to everybody

Kirjavahetus

Log every question in the correspondence register as it arrives, answer it as a numbered addendum issued to all tenderers, and never answer a substantive question by telephone. Where an answer changes the scope late in the period, extend the closing time rather than assume the tenderers can absorb it.

Miks: The tenderer who asks the good question is the one who read the documents properly, and answering only them rewards the reading by handing the answer to nobody else. The code calls that unequal information, and a losing tenderer who finds out about it has a complaint that survives the award.

SisendTenderer questionsAnswers from the design teamVäljundAddendum issued to everyoneQuestion and answer trail
4

Hold them closed until the closing time

Pakkumuste haldus

Take the tenders in without opening them, record the time each one arrived, and open them together after the close. Deal with a late tender under the rule the conditions of tendering stated, before you know what it says.

Miks: A tender opened early is a price that can be repeated to somebody else, and the code treats the confidentiality of a submitted offer as absolute. The rule about late tenders has to be applied blind for the same reason: a decision made after reading the number is a decision about the number.

SisendSubmitted tendersClosing timeVäljundTenders opened after the closeRegister of what arrived when
5

Level the conforming offers before you look at the alternatives

Pakkumuste haldus

Compare the conforming tenders against each other first, item by item, and clear up an ambiguity by asking that tenderer what it means rather than by adjusting their price yourself. Assess an alternative tender separately, on what it changes and what it is worth, and only where the conditions of tendering allowed one.

Miks: Mixing an alternative into the conforming comparison compares two different buildings on price, which is how a cheaper offer wins by leaving something out. Clarification is allowed and correction is not, and the line between them is whether the tenderer or the assessor decided what the price now means.

SisendTenders opened after the closeThe bill they all pricedVäljundConforming offers levelledAlternatives assessed on their own
6

Award through a recorded approval, not a second round of prices

Kinnitusmarsruudid

Put the recommendation through the approval route that has the authority to commit the money, with the levelled comparison attached, and advise the unsuccessful tenderers once it is decided. Do not take the lowest price back to the others to be beaten.

Miks: Using one tender to move another is the practice the code exists to stop, and it is self defeating over a market as small as Australian construction: the builders find out, and the discount is recovered on the first variation of the job you just shopped. An approval with the comparison attached is also the only durable answer to the question of why this builder was chosen.

SisendConforming offers levelledRecommendation to awardVäljundAward approved and datedUnsuccessful tenderers advised
Moodulid

Selle tegevusjuhendi moodulid

5 / 190 platvormi moodulit

The market this case is written for

Austraalia

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • AS 4000
  • Security of Payment Act

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Rohkem valdkonnas Hankemenetlus ja hankimine

Hankemenetlus ja hankimine

Vii läbi hange mahutabelist

Vii hinnastatud mahutabel turule: paketi see, kutsu alltöövõtjad, ühtlusta nende pakkumused…

5 sammu12 minAva
Hankemenetlus ja hankimine

Osta materjale mahutabelist

Osta kogused, mille juba hinnastasid: tõsta väljanõue mahutabelist, esita tellimus tarnijale…

4 sammu10 minAva
Hankemenetlus ja hankimine

Võrdle pakkumusi ja sõlmi hange

Võta kaust tagastatud pakkumustest, mis kunagi täpselt ei sobi, taanda need samale mahule ni…

3 sammu12 minAva