IMSS에 obra를 등록하고 하도급 전에 REPSE 확인하기

reglamento가 허용하는 일수 내에 공사를 SIROC에 등록하고, 출역과 급여가 서로 일치하도록 유지하고, 전문업체를 계약하기 전에 그 REPSE 등록을 확인하고, IMSS에 하도급 사실을 통지하고, 매 지급 전에 월별 증빙을 확보한다.

7단계20 분종합건설사전문건설사PM/CM 업체

작동 방식, 단계별로

플랫폼 전반에 걸친 7단계 - 각 단계에서 무엇을 하는지, 그리고 왜 중요한지.

1

Register the obra in SIROC in the first week

현장 동원

Put the SIROC registration on the mobilisation checklist alongside the hoarding and the site office, with an owner and a date. It carries the type of work, where it is and the tasks that will be carried out, and it is due within five working days of the works starting, under article 12 of the Reglamento del Seguro Social Obligatorio para los Trabajadores de la Construccion por Obra o Tiempo Determinado. Keep the reference against the project once it is filed.

스크린샷, 1단계: Register the obra in SIROC in the first week (현장 동원, IMSS에 obra를 등록하고 하도급 전에 REPSE 확인하기)
현장 동원: Register the obra in SIROC in the first week

이유: Five working days is roughly the time it takes to get the site fenced, so this obligation competes with everything else in the noisiest week of the job and loses. It is also the record every later IMSS question is answered from: without an obra registered, the contributions your workers generate have no work to attach to, and reconciling them afterwards is a task nobody has budgeted.

입력Contract, site address and start dateType of work and what will be done결과Obra registered in SIROCRegistration reference on the project
2

Keep a record of who was actually on site

현장 시간

Record attendance by day and by worker, and keep your own employees separate from the people a subcontractor brought. Do it as part of the daily routine rather than as a monthly reconstruction, because the value of the record is that it was written on the day.

스크린샷, 2단계: Keep a record of who was actually on site (현장 시간, IMSS에 obra를 등록하고 하도급 전에 REPSE 확인하기)
현장 시간: Keep a record of who was actually on site

이유: The line between your workforce and somebody else's is the line the whole subcontracting reform turns on, and it is drawn on site rather than in the contract. A specialist whose people take their instructions from your foreman, use your tools and appear on your attendance list is not providing a specialised service whatever the contract says, and that is precisely how an inspection reads it.

입력Crews on site, own and subcontractedHours worked in the period결과Who was on site, by dayOwn workers separated from subcontracted
3

Make the payroll agree with the site record

급여 관리

Run the payroll from the attendance rather than beside it, so the workers paid, the workers registered with IMSS and the workers on site are the same list. Keep the contributions attributable to this obra visible against the project, because that is the form the IMSS question takes.

이유: Three lists that should be identical are maintained by three different people, and nothing compares them until somebody outside the firm does. The gap is rarely fraud; it is a worker who started on Monday and was registered on Thursday, repeated across a year. Reconciled monthly it is a small correction, reconciled at an inspection it is an assessment.

입력Attendance for the periodCategories and salario base결과Payroll agreeing with the site recordContributions attributable to the obra
4

Verify the REPSE before you engage, not before you pay

협력업체 디렉터리

Check two things in the STPS register and file the evidence with the date you checked it: that the provider holds a current REPSE, and that the activity it is registered for actually covers the work you are asking for. Then check the other half, which is your own: that the work is a specialised service or work outside your corporate purpose and predominant economic activity, rather than the placing of people at your disposal, which is prohibited.

스크린샷, 4단계: Verify the REPSE before you engage, not before you pay (협력업체 디렉터리, IMSS에 obra를 등록하고 하도급 전에 REPSE 확인하기)
협력업체 디렉터리: Verify the REPSE before you engage, not before you pay

이유: A payment to a provider that should have been registered and was not is not deductible for ISR, and the IVA on it is not creditable, so the cost of the mistake is the subcontract value plus the tax that was supposed to come back. The registration also has a term and can be lost, so a REPSE verified once at engagement is not evidence of anything two years later, and the verification has to carry a date to be worth filing.

입력Specialist you intend to engageWhat the subcontract really covers결과REPSE registration verified and datedRegistered activity matched to the scope
5

Notify the subcontract inside its five days

권한 제출

Give notice of the subcontract to IMSS within five working days of the day it was signed, using the format the system requires, and log the submission and its acknowledgement against the project alongside every other filing to an authority. The count runs from signature, not from the day the subcontractor first turns up.

스크린샷, 5단계: Notify the subcontract inside its five days (권한 제출, IMSS에 obra를 등록하고 하도급 전에 REPSE 확인하기)
권한 제출: Notify the subcontract inside its five days

이유: Signature and mobilisation can be weeks apart, and the deadline attaches to the earlier of them, so a subcontract signed in good time and started later is already late before anybody has done anything wrong. Logging the acknowledgement matters as much as filing: an obligation you believe you met is worth nothing at an inspection without the receipt.

입력Subcontract signed, with its dateObra registration in SIROC결과Subcontract notified to IMSSFiling logged with its acknowledgement
6

Hold the monthly evidence before you pay

조달

Make the monthly pack a condition of payment rather than a request: the REPSE still current, the opinion del cumplimiento de obligaciones fiscales, evidence that the IMSS and housing fund contributions for the period were paid, and the CFDI de nomina of the people who did the work. Release the payment against the pack, not against the promise of it.

스크린샷, 6단계: Hold the monthly evidence before you pay (조달, IMSS에 obra를 등록하고 하도급 전에 REPSE 확인하기)
조달: Hold the monthly evidence before you pay

이유: This is the only leverage that exists. Once the money has gone the documents arrive slowly or not at all, and the exposure is yours rather than theirs, because it is your deduction that fails and, where a subcontractor does not pay its workers' contributions, your works those workers were on. A pack that is a condition of payment arrives every month without anybody chasing it.

입력Subcontractor invoice for the monthCompliance documents for the period결과Payment released against evidenceMonthly pack on file
7

Close the obra and archive what proves it

마감

File the closure of the works in SIROC when they finish, and archive the labour compliance pack with the rest of the close-out documents: the registration and its amendments, the subcontract notices, the monthly evidence and the payroll reconciliations, kept together and kept for as long as the tax and social security records have to be kept.

스크린샷, 7단계: Close the obra and archive what proves it (마감, IMSS에 obra를 등록하고 하도급 전에 REPSE 확인하기)
마감: Close the obra and archive what proves it

이유: An obra left open goes on looking like a live site to IMSS long after the hoarding came down, and it is the finished jobs that get audited, because the people who ran them have moved on and the folders have been split between offices. Archived as one pack at the close, the answer to an inspection two years later is one folder rather than a fortnight.

입력Date the works finishedFilings made across the job결과Obra closed in SIROCLabour compliance pack archived
모듈

이 플레이북의 모듈

플랫폼 190개 모듈 중 7개

The market this case is written for

멕시코

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CFDI 4.0
  • Ley de Obras Publicas

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

현장 및 작업 카테고리의 더 보기

현장 및 작업

현장 일일 업무 진행

하루를 제대로 마무리합니다. 작업일지를 기록하고, 노무 및 장비 시간을 등록하고, 사진을 업로드하고, 안전 관찰 사항을 기록하여 그날의 기록이 나중에 근거로 활용될…

4단계9 분열기
현장 및 작업

RFI 답변하기

현장에서 나온 질문을 추적 가능한 요청으로 전환하고, 답변 책임자에게 전달하여, 회신 내용을 기록으로 남깁니다.

3단계9 분열기
현장 및 작업

실비정산(데이워크) 및 시간자재 기록

지시된 추가 작업을 지급받는 클레임으로 전환합니다: 발생 즉시 노무, 장비, 자재를 기록하고, 당일 시트에 서명을 받은 뒤 계약에 따라 제출합니다.

3단계9 분열기