Casos prácticos / Obra y campo
Obra y campo

Registrar la obra ante el IMSS y verificar el REPSE antes de subcontratar

Registre los trabajos en el SIROC dentro de los días que concede el reglamento, mantenga la asistencia y la nómina de acuerdo entre sí, verifique el registro en el REPSE de un especialista antes de contratarlo, avise al IMSS de la subcontratación, y reúna la evidencia mensual antes de cada pago.

7 pasos20 minContratista generalSubcontratista especialistaGestora de proyectos / construcción

Cómo funciona, paso a paso

7 pasos a lo largo de la plataforma - qué hacer en cada uno y por qué importa.

1

Register the obra in SIROC in the first week

Movilización del sitio

Put the SIROC registration on the mobilisation checklist alongside the hoarding and the site office, with an owner and a date. It carries the type of work, where it is and the tasks that will be carried out, and it is due within five working days of the works starting, under article 12 of the Reglamento del Seguro Social Obligatorio para los Trabajadores de la Construccion por Obra o Tiempo Determinado. Keep the reference against the project once it is filed.

Por que: Five working days is roughly the time it takes to get the site fenced, so this obligation competes with everything else in the noisiest week of the job and loses. It is also the record every later IMSS question is answered from: without an obra registered, the contributions your workers generate have no work to attach to, and reconciling them afterwards is a task nobody has budgeted.

EntradaContract, site address and start dateType of work and what will be doneResultadoObra registered in SIROCRegistration reference on the project
2

Keep a record of who was actually on site

Tiempo de obra

Record attendance by day and by worker, and keep your own employees separate from the people a subcontractor brought. Do it as part of the daily routine rather than as a monthly reconstruction, because the value of the record is that it was written on the day.

Por que: The line between your workforce and somebody else's is the line the whole subcontracting reform turns on, and it is drawn on site rather than in the contract. A specialist whose people take their instructions from your foreman, use your tools and appear on your attendance list is not providing a specialised service whatever the contract says, and that is precisely how an inspection reads it.

EntradaCrews on site, own and subcontractedHours worked in the periodResultadoWho was on site, by dayOwn workers separated from subcontracted
3

Make the payroll agree with the site record

Nómina

Run the payroll from the attendance rather than beside it, so the workers paid, the workers registered with IMSS and the workers on site are the same list. Keep the contributions attributable to this obra visible against the project, because that is the form the IMSS question takes.

Por que: Three lists that should be identical are maintained by three different people, and nothing compares them until somebody outside the firm does. The gap is rarely fraud; it is a worker who started on Monday and was registered on Thursday, repeated across a year. Reconciled monthly it is a small correction, reconciled at an inspection it is an assessment.

EntradaAttendance for the periodCategories and salario baseResultadoPayroll agreeing with the site recordContributions attributable to the obra
4

Verify the REPSE before you engage, not before you pay

Directorio de subcontratistas

Check two things in the STPS register and file the evidence with the date you checked it: that the provider holds a current REPSE, and that the activity it is registered for actually covers the work you are asking for. Then check the other half, which is your own: that the work is a specialised service or work outside your corporate purpose and predominant economic activity, rather than the placing of people at your disposal, which is prohibited.

Por que: A payment to a provider that should have been registered and was not is not deductible for ISR, and the IVA on it is not creditable, so the cost of the mistake is the subcontract value plus the tax that was supposed to come back. The registration also has a term and can be lost, so a REPSE verified once at engagement is not evidence of anything two years later, and the verification has to carry a date to be worth filing.

EntradaSpecialist you intend to engageWhat the subcontract really coversResultadoREPSE registration verified and datedRegistered activity matched to the scope
5

Notify the subcontract inside its five days

Presentaciones a Autoridad

Give notice of the subcontract to IMSS within five working days of the day it was signed, using the format the system requires, and log the submission and its acknowledgement against the project alongside every other filing to an authority. The count runs from signature, not from the day the subcontractor first turns up.

Por que: Signature and mobilisation can be weeks apart, and the deadline attaches to the earlier of them, so a subcontract signed in good time and started later is already late before anybody has done anything wrong. Logging the acknowledgement matters as much as filing: an obligation you believe you met is worth nothing at an inspection without the receipt.

EntradaSubcontract signed, with its dateObra registration in SIROCResultadoSubcontract notified to IMSSFiling logged with its acknowledgement
6

Hold the monthly evidence before you pay

Adquisiciones

Make the monthly pack a condition of payment rather than a request: the REPSE still current, the opinion del cumplimiento de obligaciones fiscales, evidence that the IMSS and housing fund contributions for the period were paid, and the CFDI de nomina of the people who did the work. Release the payment against the pack, not against the promise of it.

Por que: This is the only leverage that exists. Once the money has gone the documents arrive slowly or not at all, and the exposure is yours rather than theirs, because it is your deduction that fails and, where a subcontractor does not pay its workers' contributions, your works those workers were on. A pack that is a condition of payment arrives every month without anybody chasing it.

EntradaSubcontractor invoice for the monthCompliance documents for the periodResultadoPayment released against evidenceMonthly pack on file
7

Close the obra and archive what proves it

Cierre

File the closure of the works in SIROC when they finish, and archive the labour compliance pack with the rest of the close-out documents: the registration and its amendments, the subcontract notices, the monthly evidence and the payroll reconciliations, kept together and kept for as long as the tax and social security records have to be kept.

Por que: An obra left open goes on looking like a live site to IMSS long after the hoarding came down, and it is the finished jobs that get audited, because the people who ran them have moved on and the folders have been split between offices. Archived as one pack at the close, the answer to an inspection two years later is one folder rather than a fortnight.

EntradaDate the works finishedFilings made across the jobResultadoObra closed in SIROCLabour compliance pack archived
Módulos

Módulos de este playbook

7 / 190 módulos de la plataforma

El mercado para el que está escrito este caso

México

Todo en este caso sigue la forma en que la obra se mide, se valora y se paga en este mercado. Los documentos, el desglose de costes y las reglas de pago son los que se usan allí, no una versión genérica.

Normas que sigue

  • CFDI 4.0
  • Ley de Obras Publicas

No tienes que configurar nada de eso a mano. La primera vez que abres la plataforma te pregunta en qué mercado trabajas. Elige este y ajusta el idioma de la interfaz, carga la base de costes correspondiente, registra la clasificación de costes y añade un proyecto de ejemplo que puedes abrir enseguida.

Las comprobaciones de este mercado también vienen con la plataforma. Actívalas una vez y un presupuesto al que le falte algo que el mercado espera queda señalado mientras trabajas en él, no después de presentar la oferta.

Más en Obra y campo

Obra y campo

Gestionar la jornada de obra

Cierra la jornada como es debido: anota el diario, imputa las horas de mano de obra y maquin…

4 pasos9 minAbrir
Obra y campo

Responder una RFI

Convierte una pregunta surgida en el tajo en una solicitud registrada, dirígela a la parte r…

3 pasos9 minAbrir