Mobilise the site and set up logistics

Get the site ready before work starts: run the mobilisation checklist for hoarding, welfare and utilities, then set the logistics plan for access, deliveries, cranes and laydown.

3 kroků10 minGenerální dodavatelProjektový / stavební manažerSpecializovaný subdodavatel

Jak to funguje, krok za krokem

3 kroků napříč platformou - co na každém uděláte a proč na tom záleží.

1

Run the mobilisation checklist

Site Mobilisation

Work the mobilisation checklist: hoarding and security, welfare and offices, temporary power and water, signage, first aid and the statutory notices, each with an owner and a date.

Proč: The item forgotten at mobilisation stops work later - no water for the concrete, no power for the tools. A checklist with owners and dates is what turns a chaotic start into a controlled one.

VstupContract startSite conditionsVýstupMobilisation checklist
2

Track set-up to complete

Site Mobilisation

Track each mobilisation task to done, chasing the long-lead connections and approvals that gate the site opening, until the establishment is genuinely complete.

Proč: A utility connection can take weeks of notice. Tracking the set-up as a live list is what surfaces the item that will hold up the start while there is still time to expedite it.

VstupMobilisation checklistVýstupSite established
3

Set the logistics plan

Logistika staveniště

Set the logistics plan: gates and access routes, delivery windows, crane and hoist positions and reach, laydown and waste areas, mapped against the busy phases of the programme.

Proč: Space is the scarcest resource on a tight site. A logistics plan that thinks ahead to the busy weeks is what stops trades fighting over the same crane and the same gate.

VstupEstablished siteProgramme peaksVýstupLogistics plan