Cases / Aflevering og livscyklus
Aflevering og livscyklus

Luk obra med acta de entrega-recepción og finiquito

Luk bitácora, giv besked om, at arbejdet er afsluttet, ryd bemærkningerne, underskriv acta de entrega-recepción, gør alt op i finiquito, ophæv kontrakten med en acta administrativa, og kør derefter de tolv måneder med vicios ocultos, som overlever det hele.

7 trin22 minHovedentreprenørUdvikler / bygherreProjekt- / byggeledelsesfirma

Sådan fungerer det, trin for trin

7 trin gennem platformen - hvad du gør i hvert, og hvorfor det betyder noget.

1

Close the bitacora and index what it proves

Byggedagbog

Read the bitacora from the first note to the last and close it with the nota de cierre. Before you do, list the notes the finiquito will lean on: the instructions behind conceptos extraordinarios, the suspensions, the extensions of time, and anything left answered by silence. Where a matter is still open, close it in a note now rather than leaving it to be argued after the record is shut.

Hvorfor: The bitacora is the instrument of communication between the parties under the reglamento of the LOPSRM, which makes it the record both sides are held to and not a site notebook. Everything you will want to say at the finiquito has to already be in it, because a note added after the works finished carries no weight and a claim with no note behind it carries none either.

InputNotas de bitacora across the jobMatters still open in itResultatBitacora closed with its nota de cierreIndex of the notes the finiquito relies on
2

Give written notice that the works are terminated

Korrespondance

Notify the dependencia in writing that the works are terminated, attaching what it needs to verify them, and record the date the notice went and the date it was received. The verification period the contract sets runs from that receipt, so it is a dated fact rather than a courtesy.

Hvorfor: Everything after this step is counted from a date, and the notice is the first of them. Without it the works can be complete for months while the file says nothing happened, and the contractor has no way to show it was waiting rather than late. A phone call to the residencia is not a notice, however well it was received.

InputWorks complete against the catalogoTests and commissioning resultsResultatWritten notice of termination, datedVerification period running
3

Clear the observations before the reception, not after

Mangelliste

Take the observations raised on the verification walk as a list with an owner, a date and the evidence that closes each one, and work it down before the acta is signed. Where an observation is not defective work but a change the dependencia is asking for, say so at the time and price it, rather than absorbing it to get the acta signed.

Hvorfor: Observations left open at the reception do not disappear, they move into the twelve months of vicios ocultos, where they are secured by your own guarantee and dealt with by a crew that has been demobilised. The same repair costs a fraction of the price while there is still a site, and the pressure to sign the acta first and fix afterwards is at its highest in exactly that week.

InputObservations from the verification walkEspecificaciones the work is judged againstResultatObservations with an owner and a dateEach one cleared with its evidence
4

Sign the acta de entrega-recepcion fisica

Afslutning

Receive the works formally: the acta de entrega-recepcion with the parties, the date, the works received and the state they were received in, and with it the handover pack, the as-built drawings, the manuals, the equipment warranties and the test results. The guarantee against vicios ocultos has to already be in the dependencia's hands, because article 66 LOPSRM wants it before the works are received rather than after.

Hvorfor: This is the date the rest of the close-out is measured from and the date the twelve months of vicios ocultos start, so it is worth an argument to get it right on the paper. It is also the point where risk moves: after it the works are the dependencia's to operate and yours to answer for, which are two different things and are commonly assumed to be one.

InputObservations clearedVicios ocultos security in placeResultatActa de entrega-recepcion signedManuals, warranties and as-built handed over
5

Settle everything at once in the finiquito

Finans

Bring the whole contract onto one page within the period the LOPSRM allows after the reception: everything certified and paid, the volumes executed against the catalogo, conceptos extraordinarios authorised, ajuste de costos claimed and resolved, the anticipo amortised, the fondo de garantia, retenciones and any penas convencionales. The result is one balance, owed one way or the other, and the fiscal document that settles it follows the balance.

Hvorfor: The finiquito is where every loose end from three years arrives at once, and it is settled from records rather than from memory: a generador nobody kept, an extraordinario agreed verbally or an ajuste never formally requested is simply not in it. It is also not optional and it does not wait for you. Where one party will not take part, the other may make the finiquito and notify it, so the choice is between being in the room and being told what was decided there.

InputEstimaciones paid to dateAnticipo, ajuste, retenciones and penasResultatFiniquito with a single balanceFinal CFDI or credit note raised
6

Extinguish the contract by acta administrativa

E-signaturer

Once the finiquito is settled, sign the acta administrativa that gives the rights and obligations of the parties as extinguished, and file it with the contract. Take it straight to the afianzadora, because it is the document that lets the fianza de cumplimiento be cancelled.

Hvorfor: This is the step everybody assumes has happened, because the works are handed over, the money is settled and the team has gone. Without it the contract is still formally alive, the fianza de cumplimiento cannot be released, and the bonding capacity it consumes is still committed against a job that ended two years ago.

InputFiniquito agreed and settledSignatories on both sidesResultatActa administrativa signedFianza de cumplimiento clear to cancel
7

Run the twelve months of vicios ocultos to their end

Garantier & mangelansvar

Open a register that runs from the date on the acta for the twelve months article 66 LOPSRM sets, with an owner and a route for anything reported. Record each defect, what was done and whether it was your responsibility or a matter of use and maintenance, and diarise the expiry so the security can be released the week it ends.

Hvorfor: The twelve months are the only part of the contract that is live while nobody is looking at it, and a defect reported to a site email that stopped being read is still a defect you are answerable for. Keeping the register also settles the argument that actually arises, which is almost never whether the fault exists but whether it is a hidden vice or the way the building has been used.

InputDate of the acta de entrega-recepcionDefects reported in the periodResultatDefects register for the twelve monthsExpiry date and release of the security
Moduler

Moduler i denne playbook

7 / 190 platformmoduler

The market this case is written for

Mexico

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CFDI 4.0
  • Ley de Obras Publicas

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Mere inden for Aflevering og livscyklus

Aflevering og livscyklus

Aflever og afslut sagen

Afslut sagen rent: arbejd mangellisten ned til nul, bekræft at hver inspektion er bestået og…

5 trin14 minÅbn
Aflevering og livscyklus

Som udført og O&M-aflevering

Saml som udført-dokumentationen, bevis at kvalitetsmappen ikke har huller, og udsted så en d…

3 trin12 minÅbn
Aflevering og livscyklus

Gennemfør en afleveringsinspektion

Gå det færdige arbejde igennem med bygherren, registrér hvad der består og hvad der ikke gør…

3 trin11 minÅbn