Cerrar la obra con el acta de entrega-recepción y el finiquito

Cierre la bitácora, dé aviso de terminación de los trabajos, atienda las observaciones, firme el acta de entrega-recepción, liquide todo en el finiquito, extinga el contrato mediante acta administrativa y después corra los doce meses de vicios ocultos que sobreviven a todo lo demás.

7 pasos22 minContratista generalPromotor / clienteGestora de proyectos / construcción

Cómo funciona, paso a paso

7 pasos a lo largo de la plataforma - qué hacer en cada uno y por qué importa.

1

Close the bitacora and index what it proves

Diario de obra

Read the bitacora from the first note to the last and close it with the nota de cierre. Before you do, list the notes the finiquito will lean on: the instructions behind conceptos extraordinarios, the suspensions, the extensions of time, and anything left answered by silence. Where a matter is still open, close it in a note now rather than leaving it to be argued after the record is shut.

Por que: The bitacora is the instrument of communication between the parties under the reglamento of the LOPSRM, which makes it the record both sides are held to and not a site notebook. Everything you will want to say at the finiquito has to already be in it, because a note added after the works finished carries no weight and a claim with no note behind it carries none either.

EntradaNotas de bitacora across the jobMatters still open in itResultadoBitacora closed with its nota de cierreIndex of the notes the finiquito relies on
2

Give written notice that the works are terminated

Correspondencia

Notify the dependencia in writing that the works are terminated, attaching what it needs to verify them, and record the date the notice went and the date it was received. The verification period the contract sets runs from that receipt, so it is a dated fact rather than a courtesy.

Por que: Everything after this step is counted from a date, and the notice is the first of them. Without it the works can be complete for months while the file says nothing happened, and the contractor has no way to show it was waiting rather than late. A phone call to the residencia is not a notice, however well it was received.

EntradaWorks complete against the catalogoTests and commissioning resultsResultadoWritten notice of termination, datedVerification period running
3

Clear the observations before the reception, not after

Lista de pendientes

Take the observations raised on the verification walk as a list with an owner, a date and the evidence that closes each one, and work it down before the acta is signed. Where an observation is not defective work but a change the dependencia is asking for, say so at the time and price it, rather than absorbing it to get the acta signed.

Por que: Observations left open at the reception do not disappear, they move into the twelve months of vicios ocultos, where they are secured by your own guarantee and dealt with by a crew that has been demobilised. The same repair costs a fraction of the price while there is still a site, and the pressure to sign the acta first and fix afterwards is at its highest in exactly that week.

EntradaObservations from the verification walkEspecificaciones the work is judged againstResultadoObservations with an owner and a dateEach one cleared with its evidence
4

Sign the acta de entrega-recepcion fisica

Cierre

Receive the works formally: the acta de entrega-recepcion with the parties, the date, the works received and the state they were received in, and with it the handover pack, the as-built drawings, the manuals, the equipment warranties and the test results. The guarantee against vicios ocultos has to already be in the dependencia's hands, because article 66 LOPSRM wants it before the works are received rather than after.

Por que: This is the date the rest of the close-out is measured from and the date the twelve months of vicios ocultos start, so it is worth an argument to get it right on the paper. It is also the point where risk moves: after it the works are the dependencia's to operate and yours to answer for, which are two different things and are commonly assumed to be one.

EntradaObservations clearedVicios ocultos security in placeResultadoActa de entrega-recepcion signedManuals, warranties and as-built handed over
5

Settle everything at once in the finiquito

Finanzas

Bring the whole contract onto one page within the period the LOPSRM allows after the reception: everything certified and paid, the volumes executed against the catalogo, conceptos extraordinarios authorised, ajuste de costos claimed and resolved, the anticipo amortised, the fondo de garantia, retenciones and any penas convencionales. The result is one balance, owed one way or the other, and the fiscal document that settles it follows the balance.

Por que: The finiquito is where every loose end from three years arrives at once, and it is settled from records rather than from memory: a generador nobody kept, an extraordinario agreed verbally or an ajuste never formally requested is simply not in it. It is also not optional and it does not wait for you. Where one party will not take part, the other may make the finiquito and notify it, so the choice is between being in the room and being told what was decided there.

EntradaEstimaciones paid to dateAnticipo, ajuste, retenciones and penasResultadoFiniquito with a single balanceFinal CFDI or credit note raised
6

Extinguish the contract by acta administrativa

Firmas Electrónicas

Once the finiquito is settled, sign the acta administrativa that gives the rights and obligations of the parties as extinguished, and file it with the contract. Take it straight to the afianzadora, because it is the document that lets the fianza de cumplimiento be cancelled.

Por que: This is the step everybody assumes has happened, because the works are handed over, the money is settled and the team has gone. Without it the contract is still formally alive, the fianza de cumplimiento cannot be released, and the bonding capacity it consumes is still committed against a job that ended two years ago.

EntradaFiniquito agreed and settledSignatories on both sidesResultadoActa administrativa signedFianza de cumplimiento clear to cancel
7

Run the twelve months of vicios ocultos to their end

Garantías y responsabilidad por defectos

Open a register that runs from the date on the acta for the twelve months article 66 LOPSRM sets, with an owner and a route for anything reported. Record each defect, what was done and whether it was your responsibility or a matter of use and maintenance, and diarise the expiry so the security can be released the week it ends.

Por que: The twelve months are the only part of the contract that is live while nobody is looking at it, and a defect reported to a site email that stopped being read is still a defect you are answerable for. Keeping the register also settles the argument that actually arises, which is almost never whether the fault exists but whether it is a hidden vice or the way the building has been used.

EntradaDate of the acta de entrega-recepcionDefects reported in the periodResultadoDefects register for the twelve monthsExpiry date and release of the security
Módulos

Módulos de este playbook

7 / 190 módulos de la plataforma

El mercado para el que está escrito este caso

México

Todo en este caso sigue la forma en que la obra se mide, se valora y se paga en este mercado. Los documentos, el desglose de costes y las reglas de pago son los que se usan allí, no una versión genérica.

Normas que sigue

  • CFDI 4.0
  • Ley de Obras Publicas

No tienes que configurar nada de eso a mano. La primera vez que abres la plataforma te pregunta en qué mercado trabajas. Elige este y ajusta el idioma de la interfaz, carga la base de costes correspondiente, registra la clasificación de costes y añade un proyecto de ejemplo que puedes abrir enseguida.

Las comprobaciones de este mercado también vienen con la plataforma. Actívalas una vez y un presupuesto al que le falte algo que el mercado espera queda señalado mientras trabajas en él, no después de presentar la oferta.

Más en Entrega y ciclo de vida

Entrega y ciclo de vida

Entregar y cerrar la obra

Termine el proyecto sin cabos sueltos: lleve la lista de repasos a cero, confirme que todas…

5 pasos14 minAbrir
Entrega y ciclo de vida

Entrega as-built y O&M

Reúne el registro as-built, demuestra que el expediente de calidad no tiene lagunas y entreg…

3 pasos12 minAbrir