引渡し検収記録と finiquito で工事を締める

bitácora を閉じ、工事終了の通知を出し、指摘事項を解消し、acta de entrega-recepción に署名し、finiquito ですべてを一度に清算し、行政上の終了文書で契約を消滅させ、その後、これらすべてより長く残る 12 か月の隠れた瑕疵の期間を進める。

7ステップ22 分総合建設会社デベロッパー / 発注者プロジェクト / 施工管理会社

仕組みをステップごとに

プラットフォーム全体で7ステップ - 各ステップで何をするか、そしてなぜ重要か。

1

Close the bitacora and index what it proves

工事日報

Read the bitacora from the first note to the last and close it with the nota de cierre. Before you do, list the notes the finiquito will lean on: the instructions behind conceptos extraordinarios, the suspensions, the extensions of time, and anything left answered by silence. Where a matter is still open, close it in a note now rather than leaving it to be argued after the record is shut.

理由: The bitacora is the instrument of communication between the parties under the reglamento of the LOPSRM, which makes it the record both sides are held to and not a site notebook. Everything you will want to say at the finiquito has to already be in it, because a note added after the works finished carries no weight and a claim with no note behind it carries none either.

入力Notas de bitacora across the jobMatters still open in it出力Bitacora closed with its nota de cierreIndex of the notes the finiquito relies on
2

Give written notice that the works are terminated

やり取り

Notify the dependencia in writing that the works are terminated, attaching what it needs to verify them, and record the date the notice went and the date it was received. The verification period the contract sets runs from that receipt, so it is a dated fact rather than a courtesy.

理由: Everything after this step is counted from a date, and the notice is the first of them. Without it the works can be complete for months while the file says nothing happened, and the contractor has no way to show it was waiting rather than late. A phone call to the residencia is not a notice, however well it was received.

入力Works complete against the catalogoTests and commissioning results出力Written notice of termination, datedVerification period running
3

Clear the observations before the reception, not after

パンチリスト

Take the observations raised on the verification walk as a list with an owner, a date and the evidence that closes each one, and work it down before the acta is signed. Where an observation is not defective work but a change the dependencia is asking for, say so at the time and price it, rather than absorbing it to get the acta signed.

理由: Observations left open at the reception do not disappear, they move into the twelve months of vicios ocultos, where they are secured by your own guarantee and dealt with by a crew that has been demobilised. The same repair costs a fraction of the price while there is still a site, and the pressure to sign the acta first and fix afterwards is at its highest in exactly that week.

入力Observations from the verification walkEspecificaciones the work is judged against出力Observations with an owner and a dateEach one cleared with its evidence
4

Sign the acta de entrega-recepcion fisica

完了

Receive the works formally: the acta de entrega-recepcion with the parties, the date, the works received and the state they were received in, and with it the handover pack, the as-built drawings, the manuals, the equipment warranties and the test results. The guarantee against vicios ocultos has to already be in the dependencia's hands, because article 66 LOPSRM wants it before the works are received rather than after.

理由: This is the date the rest of the close-out is measured from and the date the twelve months of vicios ocultos start, so it is worth an argument to get it right on the paper. It is also the point where risk moves: after it the works are the dependencia's to operate and yours to answer for, which are two different things and are commonly assumed to be one.

入力Observations clearedVicios ocultos security in place出力Acta de entrega-recepcion signedManuals, warranties and as-built handed over
5

Settle everything at once in the finiquito

財務

Bring the whole contract onto one page within the period the LOPSRM allows after the reception: everything certified and paid, the volumes executed against the catalogo, conceptos extraordinarios authorised, ajuste de costos claimed and resolved, the anticipo amortised, the fondo de garantia, retenciones and any penas convencionales. The result is one balance, owed one way or the other, and the fiscal document that settles it follows the balance.

理由: The finiquito is where every loose end from three years arrives at once, and it is settled from records rather than from memory: a generador nobody kept, an extraordinario agreed verbally or an ajuste never formally requested is simply not in it. It is also not optional and it does not wait for you. Where one party will not take part, the other may make the finiquito and notify it, so the choice is between being in the room and being told what was decided there.

入力Estimaciones paid to dateAnticipo, ajuste, retenciones and penas出力Finiquito with a single balanceFinal CFDI or credit note raised
6

Extinguish the contract by acta administrativa

電子署名

Once the finiquito is settled, sign the acta administrativa that gives the rights and obligations of the parties as extinguished, and file it with the contract. Take it straight to the afianzadora, because it is the document that lets the fianza de cumplimiento be cancelled.

理由: This is the step everybody assumes has happened, because the works are handed over, the money is settled and the team has gone. Without it the contract is still formally alive, the fianza de cumplimiento cannot be released, and the bonding capacity it consumes is still committed against a job that ended two years ago.

入力Finiquito agreed and settledSignatories on both sides出力Acta administrativa signedFianza de cumplimiento clear to cancel
7

Run the twelve months of vicios ocultos to their end

保証と瑕疵担保

Open a register that runs from the date on the acta for the twelve months article 66 LOPSRM sets, with an owner and a route for anything reported. Record each defect, what was done and whether it was your responsibility or a matter of use and maintenance, and diarise the expiry so the security can be released the week it ends.

理由: The twelve months are the only part of the contract that is live while nobody is looking at it, and a defect reported to a site email that stopped being read is still a defect you are answerable for. Keeping the register also settles the argument that actually arises, which is almost never whether the fault exists but whether it is a hidden vice or the way the building has been used.

入力Date of the acta de entrega-recepcionDefects reported in the period出力Defects register for the twelve monthsExpiry date and release of the security
モジュール

このプレイブックのモジュール

プラットフォーム 190 モジュール中 7

The market this case is written for

メキシコ

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CFDI 4.0
  • Ley de Obras Publicas

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

引き渡しとライフサイクルの他のケース

引き渡しとライフサイクル

引き渡しと竣工処理を行う

案件をきれいに終える。手直しリストをゼロにし、すべての検査が合格し未解決の不適合がないことを確認し、竣工図書一式をまとめ、署名済みの引き渡しを発行する。

5ステップ14 分開く
引き渡しとライフサイクル

竣工図と維持管理マニュアルの引渡し

竣工記録をまとめ、品質ファイルに漏れがないことを確認したうえで、運営者が実際に建物を管理・運用できる維持管理マニュアルを発行します。

3ステップ12 分開く
引き渡しとライフサイクル

引き渡し受入検査を実施する

施主と共に完成した工事を巡回し、受入基準に照らして合否を記録し、不具合リストをゼロまで解消し、清算された引き渡し受入を発行する。

3ステップ11 分開く