Eine payment claim mit einem payment schedule beantworten

Erfassen Sie eine eingehende payment claim am Tag ihres Eingangs, öffnen Sie das Fenster, das der Act für die Antwort gibt, stellen Sie den geplanten Betrag fest, stellen Sie einen payment schedule zu, der zeigt, wie Sie gerechnet haben und warum er abweicht, und behalten Sie das Fenster jeder anderen laufenden claim im Blick.

6 Schritte12 Min.GeneralunternehmerProjektentwickler / BauherrProjekt- / Baumanagementbüro

So funktioniert es, Schritt für Schritt

6 Schritte über die Plattform hinweg - was Sie bei jedem tun und warum es zählt.

1

Log the claim on the day it is served

Dokumente

File every incoming claim against its contract with the date and the manner it was served, and settle straight away whether the document is a payment claim under the Act: is it in writing, does it identify the work and the period, does it state a claimed amount and how it was calculated, and does it say it is made under the Act. Where the payer is a residential occupier, check as well that the prescribed notices the regulations require came with it.

Warum: Every consequence in this case counts from the date of service, so the date is the single fact that must not be reconstructed later. Whether the document is a payment claim decides whether the count runs at all, and that question is far cheaper to answer on the day it lands than in the week the answer is already overdue.

EingangIncoming payment claimSubcontract payment termsErgebnisClaim logged with its service dateWhether it is a payment claim at all
2

Open the window you have to answer in

Zahlungsuhr

Put the claim on the clock from the day it was served and read back two dates: the last day a payment schedule can be provided, and the day payment falls due. The contract's own period governs where it sets one; where it is silent the Act gives 20 working days for the schedule. Working days exclude weekends, public holidays and the year-end closedown, so a December claim does not answer on the same arithmetic as a June one.

Warum: The two dates are different questions and they are routinely confused. Missing the second is late payment, which costs interest and goodwill. Missing the first is losing the argument entirely, because the claimed amount then becomes payable whatever the work was actually worth. Naming both on the day the claim arrives is what keeps a busy month from turning the cheaper mistake into the expensive one.

EingangClaim logged with its service dateResponse period the contract setsErgebnisLast day to answerDate payment falls due
3

Settle the scheduled amount and how you got there

Finanzen

Work out what you say the period is worth, line by line against the claim, and write down the calculation as you go: the quantity you accept, the rate you applied, the retention withheld and any amount deducted. Keep the difference attached to the line it came from rather than as one adjustment at the bottom.

Warum: A payment schedule that certifies less than was claimed has to show the manner in which the payer calculated the scheduled amount, so the calculation is not working paper, it is part of the document. Built line by line it also survives adjudication, where a lump-sum reduction with no derivation reads as a payer who reduced the claim first and looked for reasons afterwards.

EingangClaimed amount and its build-upYour own measure and recordsErgebnisScheduled amount settledManner of calculation written down
4

Serve a schedule that carries its reasons

Korrespondenz

Issue the payment schedule in writing to the claimant. It has to identify the payment claim it answers and state the scheduled amount, and where that is less than the amount claimed it has to give the manner of calculation, the reason for the difference and, for anything being withheld, the reason for withholding it. Send it against the contract record so the sent copy and its date are kept, not just the draft.

Warum: A schedule missing its reasons is treated as no schedule at all, which puts the payer in the same position as one who never answered. Note also that being unpaid yourself is not a reason the Act will hear: conditional payment provisions of the pay-when-paid kind are ineffective, so a subcontractor's money does not wait on the principal's.

EingangScheduled amount settledManner of calculation written downErgebnisPayment schedule servedReasons for the difference recorded
5

Watch every claim you are still holding

Fristen

Keep the answer dates for every open claim across every project on one list, each with the person who owes the schedule, and let it warn you a few days out rather than on the morning it expires. Include the claims you intend to certify in full, because those are the ones that get left in a tray.

Warum: Nobody misses this deadline on a claim they are arguing about. It is missed on the routine ones, on the week somebody is on leave, and on the claim that arrived by an inbox nobody was reading. A list with an owner against each row is the only version of this that survives a busy month.

EingangClaims still openLast day to answerErgebnisAnswers falling due this weekNamed owner for each one
6

Read what an unanswered claim would cost you

Berichte

Read the gap between what was claimed and what was scheduled across the portfolio, next to the claims that have no schedule against them yet. The second number is the exposure: it is what becomes payable if the window closes, regardless of what the work was worth.

Warum: Boards understand this regime when it is a figure and not a rule. One project answering late is an administrative problem; the same figure repeated across six projects is a working capital risk, and it is the kind that arrives as a court filing rather than as a warning.

EingangClaims answered by nothingScheduled against claimedErgebnisAmount at risk of becoming payableWhere answers keep running late
Module

Module in diesem Playbook

6 / 190 Plattform-Modulen

Der Markt, für den dieses Fallbeispiel geschrieben ist

Neuseeland

Alles in diesem Fallbeispiel folgt der Art, wie Bauleistungen in diesem Markt aufgemessen, kalkuliert und abgerechnet werden. Die Formulare, die Kostengliederung und die Zahlungsregeln sind die, die dort gelten, und keine allgemeine Fassung davon.

Standards, denen es folgt

  • NZS 3910
  • Construction Contracts Act

Das müssen Sie nicht von Hand einrichten. Beim ersten Start fragt die Plattform, in welchem Markt Sie arbeiten. Wählen Sie diesen aus, und sie stellt die Oberflächensprache ein, lädt die passende Kostendatenbank, hinterlegt die Kostengliederung und legt ein Beispielprojekt an, das Sie sofort öffnen können.

Die Prüfregeln für diesen Markt sind ebenfalls dabei. Einmal eingeschaltet, fällt eine Kalkulation, der etwas Marktübliches fehlt, schon während der Arbeit auf und nicht erst nach der Abgabe.

Mehr aus Kaufmännisch & Verträge

Kaufmännisch & Verträge

Nachunternehmerpaket abwickeln

Ein Gewerkepaket an einen Nachunternehmer vergeben, es mit einem Zahlungsplan und Sicherheit…

3 Schritte11 Min.Öffnen
Kaufmännisch & Verträge

Zahlungsantrag und Abgleich

Bewerten Sie die in dieser Periode erbrachte Leistung gegen den Vertrag, stellen Sie den Zah…

3 Schritte12 Min.Öffnen