Casos prácticos / Obra y campo
Obra y campo

Respaldar una estimación con sus números generadores

Mida el período contra el catálogo de conceptos, elabore un número generador que muestre cómo se llegó a cada volumen, ligue los que fueron ordenados a la nota de bitácora que los ordenó, y presente la estimación con su aritmética adjunta en lugar de después de que se la pidan.

6 pasos16 minContratista generalSubcontratista especialistaGestora de proyectos / construcción

Cómo funciona, paso a paso

6 pasos a lo largo de la plataforma - qué hacer en cada uno y por qué importa.

1

Open the catalogo de conceptos the contract pays on

Presupuesto

Load the catalogo de conceptos exactly as it was awarded: every concepto with its clave, its unit, its contract quantity and its precio unitario. Do not tidy it, do not merge lines and do not renumber. The estimacion pays these lines and nothing else, so the catalogo is the only list a generador is allowed to point at.

Por que: A generador written against an activity, a floor or a crew has nowhere to land, because the estimacion is settled concepto by concepto and the reviewer works down the catalogo. Renumbering is worse than measuring wrongly: a wrong volume is corrected in the next period, a renumbered catalogo makes every past estimacion unreadable against the current one.

EntradaSigned contract and its catalogoPrecios unitarios as awardedResultadoConceptos with unit and contract quantityUnit of measurement per concepto
2

Measure the period against the drawing that governs

Cubicación

Take the period off the drawings, subdivided the way the generador will show it: by eje, by nivel, by tramo or by whatever grid the works are actually built on. Record the sheet number and the revision each figure came from as you measure, not afterwards.

Por que: Drawings are reissued mid job and the reviewer will be holding a different revision from the one you measured. A generador that names its sheet and revision can be rechecked in a minute; one that does not has to be measured again from scratch by somebody who was not there, and the volume that comes back is never the one you claimed.

EntradaDrawings with their revisionWork executed in the periodResultadoVolumes by eje, nivel and tramoSheet and revision behind each figure
3

Write one numero generador per concepto

Avance

For each concepto write the generador the reviewer will read: the location, the dimensions as measured, the arithmetic that turns them into a volume, and the total. Where the shape is not obvious, the croquis goes with it. Show the cumulative volume and the volume claimed this period side by side, because the estimacion pays the difference between two cumulative figures and not a figure of its own.

Por que: The residencia de obra checks generadores, not totals, and it has fifteen days under article 54 LOPSRM to review and authorise before the twenty natural day payment period can start. A total with nothing behind it cannot be authorised inside those fifteen days even by somebody who believes you, so it comes back, and the period starts again with the next estimacion rather than with this one.

EntradaMeasured volumes for the periodGeneradores of earlier periodsResultadoNumero generador per conceptoVolume claimed this period
4

Cite the bitacora note behind instructed work

Diario de obra

Where a generador covers work that was instructed, varied, accelerated or executed under a condition the contract did not foresee, cite the nota de bitacora that recorded it. The bitacora de obra is the instrument of communication between the parties under the reglamento of the LOPSRM, so the note is not a memory aid, it is the paper the instruction lives on.

Por que: At the finiquito the question is almost never whether the work was built. It is whether it was ordered, by whom and on what date, and a generador that cannot name its nota is a volume the reviewer has no way to accept without taking your word for it. Nobody signs a finiquito on somebody's word.

EntradaGeneradores that lean on an instructionNotas de bitacora for the periodResultadoNota number cited on the generadorInstruction traceable to its author
5

Take out what the catalogo does not carry

Órdenes de cambio

Where a generador runs past the contract quantity, or measures something the catalogo does not carry at all, lift it out of the estimacion and raise it as a concepto extraordinario or fuera de catalogo, with its own precio unitario integrated the way the reglamento requires and its own authorisation. Put it back into an estimacion only once it has been authorised.

Por que: An extraordinario carried quietly inside an ordinary line is the most common reason a Mexican finiquito does not close. It passes while nobody is looking at that concepto, it fails at the audit that reads the catalogo against the paid volumes, and by then the work is a year old and the people who agreed it verbally have moved on.

EntradaVolumes past the contract quantityWork the catalogo does not carryResultadoConcepto fuera de catalogo raisedEstimacion left with contract lines only
6

Present the estimacion as one package, on the day

Finanzas

Carry each generador total onto its concepto line, price it at the awarded precio unitario, and hand the estimacion over as one package: the lines, the generadores, the croquis, the photographs and the test results the specification calls for. Record the date you presented it, separately from the date it is authorised.

Por que: Two different dates drive two different obligations under article 54 LOPSRM, and keeping only one of them is how a contractor loses an argument it was winning. The presentation date is what shows you met the cut-off; the authorisation date is what starts the twenty natural days for payment. Written down as they happen, both are facts. Reconstructed later, both are claims.

EntradaGeneradores, croquis and evidencePrecios unitarios as awardedResultadoEstimacion presented with its backupDate of presentation on record
Módulos

Módulos de este playbook

6 / 190 módulos de la plataforma

El mercado para el que está escrito este caso

México

Todo en este caso sigue la forma en que la obra se mide, se valora y se paga en este mercado. Los documentos, el desglose de costes y las reglas de pago son los que se usan allí, no una versión genérica.

Normas que sigue

  • CFDI 4.0
  • Ley de Obras Publicas

No tienes que configurar nada de eso a mano. La primera vez que abres la plataforma te pregunta en qué mercado trabajas. Elige este y ajusta el idioma de la interfaz, carga la base de costes correspondiente, registra la clasificación de costes y añade un proyecto de ejemplo que puedes abrir enseguida.

Las comprobaciones de este mercado también vienen con la plataforma. Actívalas una vez y un presupuesto al que le falte algo que el mercado espera queda señalado mientras trabajas en él, no después de presentar la oferta.

Más en Obra y campo

Obra y campo

Gestionar la jornada de obra

Cierra la jornada como es debido: anota el diario, imputa las horas de mano de obra y maquin…

4 pasos9 minAbrir
Obra y campo

Responder una RFI

Convierte una pregunta surgida en el tajo en una solicitud registrada, dirígela a la parte r…

3 pasos9 minAbrir