案例 / 现场与作业
现场与作业

为每一份 estimación 都附上完整的工程量计算书

按 conceptos 目录计量本期完成量,为每个数量写出 número generador,说明这个数量是怎么算出来的,把受指令新增的部分与下达指令的 bitácora 记录挂钩,在提交 estimación 时就把算量附在后面,而不是等别人来要。

6 个步骤16 分钟总承包商专业分包商项目/施工管理公司

运作方式,逐步说明

贯穿平台的 6 个步骤 - 每一步做什么,以及为什么重要。

1

Open the catalogo de conceptos the contract pays on

工程量清单

Load the catalogo de conceptos exactly as it was awarded: every concepto with its clave, its unit, its contract quantity and its precio unitario. Do not tidy it, do not merge lines and do not renumber. The estimacion pays these lines and nothing else, so the catalogo is the only list a generador is allowed to point at.

原因: A generador written against an activity, a floor or a crew has nowhere to land, because the estimacion is settled concepto by concepto and the reviewer works down the catalogo. Renumbering is worse than measuring wrongly: a wrong volume is corrected in the next period, a renumbered catalogo makes every past estimacion unreadable against the current one.

输入Signed contract and its catalogoPrecios unitarios as awarded成果Conceptos with unit and contract quantityUnit of measurement per concepto
2

Measure the period against the drawing that governs

工程量计算

Take the period off the drawings, subdivided the way the generador will show it: by eje, by nivel, by tramo or by whatever grid the works are actually built on. Record the sheet number and the revision each figure came from as you measure, not afterwards.

原因: Drawings are reissued mid job and the reviewer will be holding a different revision from the one you measured. A generador that names its sheet and revision can be rechecked in a minute; one that does not has to be measured again from scratch by somebody who was not there, and the volume that comes back is never the one you claimed.

输入Drawings with their revisionWork executed in the period成果Volumes by eje, nivel and tramoSheet and revision behind each figure
3

Write one numero generador per concepto

进度

For each concepto write the generador the reviewer will read: the location, the dimensions as measured, the arithmetic that turns them into a volume, and the total. Where the shape is not obvious, the croquis goes with it. Show the cumulative volume and the volume claimed this period side by side, because the estimacion pays the difference between two cumulative figures and not a figure of its own.

原因: The residencia de obra checks generadores, not totals, and it has fifteen days under article 54 LOPSRM to review and authorise before the twenty natural day payment period can start. A total with nothing behind it cannot be authorised inside those fifteen days even by somebody who believes you, so it comes back, and the period starts again with the next estimacion rather than with this one.

输入Measured volumes for the periodGeneradores of earlier periods成果Numero generador per conceptoVolume claimed this period
4

Cite the bitacora note behind instructed work

施工日志

Where a generador covers work that was instructed, varied, accelerated or executed under a condition the contract did not foresee, cite the nota de bitacora that recorded it. The bitacora de obra is the instrument of communication between the parties under the reglamento of the LOPSRM, so the note is not a memory aid, it is the paper the instruction lives on.

原因: At the finiquito the question is almost never whether the work was built. It is whether it was ordered, by whom and on what date, and a generador that cannot name its nota is a volume the reviewer has no way to accept without taking your word for it. Nobody signs a finiquito on somebody's word.

输入Generadores that lean on an instructionNotas de bitacora for the period成果Nota number cited on the generadorInstruction traceable to its author
5

Take out what the catalogo does not carry

变更单

Where a generador runs past the contract quantity, or measures something the catalogo does not carry at all, lift it out of the estimacion and raise it as a concepto extraordinario or fuera de catalogo, with its own precio unitario integrated the way the reglamento requires and its own authorisation. Put it back into an estimacion only once it has been authorised.

原因: An extraordinario carried quietly inside an ordinary line is the most common reason a Mexican finiquito does not close. It passes while nobody is looking at that concepto, it fails at the audit that reads the catalogo against the paid volumes, and by then the work is a year old and the people who agreed it verbally have moved on.

输入Volumes past the contract quantityWork the catalogo does not carry成果Concepto fuera de catalogo raisedEstimacion left with contract lines only
6

Present the estimacion as one package, on the day

财务

Carry each generador total onto its concepto line, price it at the awarded precio unitario, and hand the estimacion over as one package: the lines, the generadores, the croquis, the photographs and the test results the specification calls for. Record the date you presented it, separately from the date it is authorised.

原因: Two different dates drive two different obligations under article 54 LOPSRM, and keeping only one of them is how a contractor loses an argument it was winning. The presentation date is what shows you met the cut-off; the authorisation date is what starts the twenty natural days for payment. Written down as they happen, both are facts. Reconstructed later, both are claims.

输入Generadores, croquis and evidencePrecios unitarios as awarded成果Estimacion presented with its backupDate of presentation on record
模块

此方案使用的模块

190 个平台模块中的 6

The market this case is written for

墨西哥

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CFDI 4.0
  • Ley de Obras Publicas

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

更多 现场与作业 案例

现场与作业

收尾现场一天的工作

妥善收尾一天的工作:记录日志、登记人工和机械工时、上传照片并记录安全观察,让这一天以可依赖的证据形式留存下来。

4 个步骤9 分钟打开
现场与作业

答复一份RFI

将现场提出的问题转化为可跟踪的请求,推动到负责给出答复的一方,并将回复归档,使其成为项目记录的一部分。

3 个步骤9 分钟打开
现场与作业

记录计工计料与时间材料

把已下达指令的额外工作转化为能获得赔付的索赔:施工发生的同时记录人工、机械和材料,当天就取得签认,再依据合同提交。

3 个步骤9 分钟打开