Casos prácticos / Presupuestación y costes
Presupuestación y costes

Valorar un orçamento de carretera desde la base SICRO

Cargue el SICRO para el estado y el mes de referencia, construya el costo horario de cada máquina, convierta las distancias de acarreo en partidas de transporte, componga los serviços con coeficientes SICRO, y valore el orçamento con los supuestos escritos.

6 pasos20 minContratista generalConsultoría de costes / QSSubcontratista especialista

Cómo funciona, paso a paso

6 pasos a lo largo de la plataforma - qué hacer en cada uno y por qué importa.

1

Bring in SICRO for the state and the reference month

Base de datos de costes

Load the SICRO tables for the state the road runs through and the reference month the edital names, and keep both on the record with the prices. Load the matching equipment and insumo tables rather than mixing a new servico table with equipment costs you already had.

Por que: SICRO prices differ by state because fuel, aggregate and labour do, and a road that crosses a boundary can legitimately need two tables. Fixing which table applies to which stretch now is a paragraph. Doing it after the proposals are open is a dispute in which both sides are quoting real published prices.

EntradaSICRO reference pricesReference date the edital namesResultadoPriced reference base loadedState and reference month recorded
2

Build the hourly cost of every machine

Equipos y flota

For each machine the method needs, set the ownership cost, the fuel and lubricant, the maintenance and the operator, and split the result into a productive hour and an idle hour. Do it for the plant that waits as well as the plant that works, the water truck and the roller included.

Por que: On a road contract the machines are the estimate. A single hourly cost averaged across productive and idle time prices a fleet that is always either working or parked, and no earthworks operation behaves that way. The two-rate split is what lets the composicao say honestly that the excavator drives the cycle and the trucks wait on it.

EntradaMachines the method needsOwnership and operating ratesResultadoHourly cost per machineProductive and idle hours separated
3

Turn the haul distances into measured transport

Cubicación

Measure what moves and how far: cut to fill, borrow pit to embankment, quarry to plant, plant to laydown. Work out the distancia media de transporte for each pairing and carry it as a measured item rather than as a note beside a volume.

Por que: Transport is often the largest single cost on an earthworks job and it is the one most often taken from a drawing rather than from the ground. A DMT measured against real borrow pits and real access roads is a number both sides can check. A DMT assumed to be the straight-line distance is a claim waiting to happen the first week the trucks run.

EntradaEarthwork quantities by originHaul distance to each destinationResultadoDistancia media de transporteTransport items measured
4

Compose each servico around the machine that sets the pace

Partidas compuestas

Build each servico as an assembly whose production per hour comes from one machine, and let the rest of the fleet follow it as productive or idle hours. Keep the material, the labour and the transport as their own components so the cost of a cubic metre can be read apart from the cost of moving it.

Por que: A road composicao where every machine works at full production prices a fleet that never queues, and it is always the cheapest way to be wrong. Naming the machine that sets the pace makes the estimate say what the site will do, and it tells the planner which single piece of plant the programme depends on.

EntradaHourly cost per machineSICRO coefficients per servicoResultadoComposicao with a built-up rateProduction per hour on the record
5

Price the orcamento and total it per lote

Presupuesto

Apply the composicoes to the positions, carry the transport as its own set of items, and total the bill by lote and by segment so each stretch can be read on its own. Check that the earthworks balance in the bill matches the one the transport was measured from.

Por que: A road contract is usually awarded and measured by lote, so a total that only exists for the whole scheme has to be rebuilt by hand for every conversation. And an earthworks balance that disagrees with the transport measured against it means one of the two is describing a road that was not designed.

EntradaComposicao with a built-up rateTransport items measuredResultadoPriced bill positionsTotal per lote
6

Record the SICRO reference and the haul assumptions

Bases de la estimación

Write down which SICRO table and month priced the work, which borrow pits and quarries the transport assumed, and which of those are not yet licensed or contracted. Name the assumptions that would move the price if they turn out differently.

Por que: The borrow pit is the assumption that changes most often and costs most when it does. Named in the basis of estimate before the bid, a pit that turns out to be unavailable is a variation with a documented starting point. Unnamed, it is a cost the contractor carries while explaining that everybody knew.

EntradaDistancia media de transporteState and reference month recordedResultadoAssumptions reportRisk items named
Módulos

Módulos de este playbook

6 / 190 módulos de la plataforma

El mercado para el que está escrito este caso

Brasil

Todo en este caso sigue la forma en que la obra se mide, se valora y se paga en este mercado. Los documentos, el desglose de costes y las reglas de pago son los que se usan allí, no una versión genérica.

Normas que sigue

  • Lei 14.133
  • SINAPI
  • ABNT NBR 12721

No tienes que configurar nada de eso a mano. La primera vez que abres la plataforma te pregunta en qué mercado trabajas. Elige este y ajusta el idioma de la interfaz, carga la base de costes correspondiente, registra la clasificación de costes y añade un proyecto de ejemplo que puedes abrir enseguida.

Las comprobaciones de este mercado también vienen con la plataforma. Actívalas una vez y un presupuesto al que le falte algo que el mercado espera queda señalado mientras trabajas en él, no después de presentar la oferta.