Fallbeispiele / Kalkulation & Kosten
Kalkulation & Kosten

Ein Straßen-orçamento aus der SICRO-Basis bepreisen

Laden Sie SICRO für den Bundesstaat und den Referenzmonat, bauen Sie die Stundenkosten jeder Maschine auf, wandeln Sie die Transportdistanzen in Transportpositionen um, setzen Sie die serviços zu SICRO-Koeffizienten zusammen, und bepreisen Sie das orçamento mit dokumentierten Annahmen.

6 Schritte20 Min.GeneralunternehmerKosten- / MengenberatungFachnachunternehmer

So funktioniert es, Schritt für Schritt

6 Schritte über die Plattform hinweg - was Sie bei jedem tun und warum es zählt.

1

Bring in SICRO for the state and the reference month

Kostendatenbank

Load the SICRO tables for the state the road runs through and the reference month the edital names, and keep both on the record with the prices. Load the matching equipment and insumo tables rather than mixing a new servico table with equipment costs you already had.

Warum: SICRO prices differ by state because fuel, aggregate and labour do, and a road that crosses a boundary can legitimately need two tables. Fixing which table applies to which stretch now is a paragraph. Doing it after the proposals are open is a dispute in which both sides are quoting real published prices.

EingangSICRO reference pricesReference date the edital namesErgebnisPriced reference base loadedState and reference month recorded
2

Build the hourly cost of every machine

Geräte & Fuhrpark

For each machine the method needs, set the ownership cost, the fuel and lubricant, the maintenance and the operator, and split the result into a productive hour and an idle hour. Do it for the plant that waits as well as the plant that works, the water truck and the roller included.

Warum: On a road contract the machines are the estimate. A single hourly cost averaged across productive and idle time prices a fleet that is always either working or parked, and no earthworks operation behaves that way. The two-rate split is what lets the composicao say honestly that the excavator drives the cycle and the trucks wait on it.

EingangMachines the method needsOwnership and operating ratesErgebnisHourly cost per machineProductive and idle hours separated
3

Turn the haul distances into measured transport

Massenermittlung

Measure what moves and how far: cut to fill, borrow pit to embankment, quarry to plant, plant to laydown. Work out the distancia media de transporte for each pairing and carry it as a measured item rather than as a note beside a volume.

Warum: Transport is often the largest single cost on an earthworks job and it is the one most often taken from a drawing rather than from the ground. A DMT measured against real borrow pits and real access roads is a number both sides can check. A DMT assumed to be the straight-line distance is a claim waiting to happen the first week the trucks run.

EingangEarthwork quantities by originHaul distance to each destinationErgebnisDistancia media de transporteTransport items measured
4

Compose each servico around the machine that sets the pace

Baugruppen

Build each servico as an assembly whose production per hour comes from one machine, and let the rest of the fleet follow it as productive or idle hours. Keep the material, the labour and the transport as their own components so the cost of a cubic metre can be read apart from the cost of moving it.

Warum: A road composicao where every machine works at full production prices a fleet that never queues, and it is always the cheapest way to be wrong. Naming the machine that sets the pace makes the estimate say what the site will do, and it tells the planner which single piece of plant the programme depends on.

EingangHourly cost per machineSICRO coefficients per servicoErgebnisComposicao with a built-up rateProduction per hour on the record
5

Price the orcamento and total it per lote

Leistungsverzeichnis

Apply the composicoes to the positions, carry the transport as its own set of items, and total the bill by lote and by segment so each stretch can be read on its own. Check that the earthworks balance in the bill matches the one the transport was measured from.

Warum: A road contract is usually awarded and measured by lote, so a total that only exists for the whole scheme has to be rebuilt by hand for every conversation. And an earthworks balance that disagrees with the transport measured against it means one of the two is describing a road that was not designed.

EingangComposicao with a built-up rateTransport items measuredErgebnisPriced bill positionsTotal per lote
6

Record the SICRO reference and the haul assumptions

Kalkulationsgrundlage

Write down which SICRO table and month priced the work, which borrow pits and quarries the transport assumed, and which of those are not yet licensed or contracted. Name the assumptions that would move the price if they turn out differently.

Warum: The borrow pit is the assumption that changes most often and costs most when it does. Named in the basis of estimate before the bid, a pit that turns out to be unavailable is a variation with a documented starting point. Unnamed, it is a cost the contractor carries while explaining that everybody knew.

EingangDistancia media de transporteState and reference month recordedErgebnisAssumptions reportRisk items named
Module

Module in diesem Playbook

6 / 190 Plattform-Modulen

Der Markt, für den dieses Fallbeispiel geschrieben ist

Brasilien

Alles in diesem Fallbeispiel folgt der Art, wie Bauleistungen in diesem Markt aufgemessen, kalkuliert und abgerechnet werden. Die Formulare, die Kostengliederung und die Zahlungsregeln sind die, die dort gelten, und keine allgemeine Fassung davon.

Standards, denen es folgt

  • Lei 14.133
  • SINAPI
  • ABNT NBR 12721

Das müssen Sie nicht von Hand einrichten. Beim ersten Start fragt die Plattform, in welchem Markt Sie arbeiten. Wählen Sie diesen aus, und sie stellt die Oberflächensprache ein, lädt die passende Kostendatenbank, hinterlegt die Kostengliederung und legt ein Beispielprojekt an, das Sie sofort öffnen können.

Die Prüfregeln für diesen Markt sind ebenfalls dabei. Einmal eingeschaltet, fällt eine Kalkulation, der etwas Marktübliches fehlt, schon während der Arbeit auf und nicht erst nach der Abgabe.

Mehr aus Kalkulation & Kosten