Tapaukset / Kaupallinen ja sopimukset
Kaupallinen ja sopimukset

Anna maksuvaatimus tiedoksi Construction Contracts Act -lain nojalla

Mittaa jakso aikataulua vasten, anna maksuvaatimus tiedoksi, seuraa arkipäiviä, jotka maksajalla on vastatakseen maksuaikataululla, anna verolasku aikataulun mukaisesta summasta ja pidä vakuudet siellä, missä laki vaatii ne pidettävän.

8 vaihetta12 minPääurakoitsijaErikoisaliurakoitsijaKustannuskonsultointi / määrälaskenta

Näin se toimii, vaihe vaiheelta

8 vaihetta läpi alustan - mitä teet kussakin ja miksi sillä on merkitystä.

1

Measure the period schedule item by schedule item

Edistyminen

Record what was executed against each schedule item for the period as a percentage of its contract quantity. The earned quantity follows from that percentage and the design quantity, and the earned amount from the same percentage and the position total, so one honest number per line produces the whole valuation.

Kuvakaappaus, vaihe 1: Measure the period schedule item by schedule item (Edistyminen, Anna maksuvaatimus tiedoksi Construction Contracts Act -lain nojalla)
Edistyminen: Measure the period schedule item by schedule item

Miksi: A progress valuation built from a single project percentage cannot be checked and therefore cannot be approved without a conversation. Measured line by line, the disagreement is about one schedule item rather than about the whole month, and the rest of the money moves while that one is settled.

SyöteContract scheduleWork executed this periodTulosPercent complete per schedule itemEarned quantities for the period
2

Value it at the contract rates

Määräluettelot

Read the valuation back against the bill and check the rates it used are the contract rates. Where a schedule item has been measured past the quantity the contract carries, deal with it as a change to the position with an order behind it rather than as a larger figure on the same line.

Kuvakaappaus, vaihe 2: Value it at the contract rates (Määräluettelot, Anna maksuvaatimus tiedoksi Construction Contracts Act -lain nojalla)
Määräluettelot: Value it at the contract rates

Miksi: A variation certified quietly is one the client can refuse at the final account, months after the work was built and paid for down the chain. Raising it as a change while it is small is the only version of that conversation where you are not asking to be paid for work already done.

SyöteEarned quantities for the periodContract ratesTulosProgress valuation for the periodVariations flagged
3

Apply retentions and previous payments

Talous

Take the cumulative valuation, subtract what has already been certified, and apply retentions at the contract percentage. The figure that leaves this step is the one the payment claim is raised for, and the backup behind it is the measure that produced it.

Kuvakaappaus, vaihe 3: Apply retentions and previous payments (Talous, Anna maksuvaatimus tiedoksi Construction Contracts Act -lain nojalla)
Talous: Apply retentions and previous payments

Miksi: Interim payments are cumulative, so the month's money is a difference between two totals rather than a total of its own. Computing it from the cumulative figure is what stops a line being paid twice or dropped entirely when a period is re-measured. Retention money on a commercial construction contract is held on trust and has to be identifiable as such, and since October 2023 it has to sit in a separate bank account and be reported to the party it is held from. A figure that exists only as a deduction line on a claim is not identifiable, and the party who needs it to be is the one who is not holding it.

SyöteCumulative progress valuationPrevious payments and retentionsTulosRetentions held to dateNet due for the period
4

Issue the payment claim against the approved figure

Talous

Raise the payment claim against the approved progress valuation, carrying retentions and any deduction the contract provides for, and reference the progress valuation on it. The claim has to state that it is made under the Act and say how the amount was calculated, and since 1 December 2015 every payment claim, commercial or residential, must also be accompanied by the prescribed Form 1 notice explaining the payer's obligations. A claim that does none of this is a request for money rather than a payment claim, and it carries none of the Act's consequences for ignoring it. The tax invoice follows for GST and is not the document the Act counts from.

Kuvakaappaus, vaihe 4: Issue the payment claim against the approved figure (Talous, Anna maksuvaatimus tiedoksi Construction Contracts Act -lain nojalla)
Talous: Issue the payment claim against the approved figure

Miksi: A demand for a figure nobody approved is one that will be returned, and the clock does not start on a returned document. Matching it to the progress valuation also means the accounts and the valuation tell the same story at year end without anybody reconciling them by hand.

SyöteProgress valuation for the periodNet due for the periodTulosPayment claim servedTax invoice issued
5

Open the payment clock on the right day

Maksukello

Open a clock over the payment claim starting from the day the payment claim is served, under the Construction Contracts Act. Payment falls due 20 working days later, and the clock records that date rather than leaving it to be worked out when somebody asks. Twenty working days is the Act's default where the contract is silent. NZS 3910 and most commercial forms set their own shorter periods, and where they do the contract's date governs, so read the default the clock gives against the contract before relying on it.

Miksi: The single most expensive mistake in interim payment is starting the count on the wrong event, because every deadline behind it inherits the error and none of them look wrong. Anchoring on the day the payment claim is served once makes the whole chain checkable.

SyötePayment claim servedDate of serviceTulosOpen payment clockDue date computed
6

Read the dates the regime computes

Maksukello

Read back the dates the Construction Contracts Act produces from the day the payment claim is served. The sum payable leads, the due date and the final date for payment sit under it, and the derivation spells out each date against the provision it came from, so every one of them can be quoted rather than asserted. Working days exclude weekends, public holidays and the year-end closedown the Act sets out, which is why a December claim does not answer on the same arithmetic as a June one.

Miksi: Deadlines that are typed in are deadlines that are typed in wrong, and a payment regime has more of them than anyone holds in their head. A derivation you can read out loud is what turns a phone call about a late payment into a quotable line.

SyöteOpen payment clockStatutory regime on recordTulosDate a payment schedule is dueFinal date for payment
7

Watch the clock count each deadline down

Maksukello

Come back to the list as the month runs. It says how many clocks the project carries and how many are past their final date, badges the overdue ones and fills the breach register underneath. Open an overdue one and the findings name the sum outstanding, the days it has run past the final date and the rate interest runs at.

Miksi: Reading a clock is what writes its register, so a quiet register on a project nobody opens is telling you about the reading and not about the payments. Nobody misses a deadline on purpose; they miss it because the day it mattered looked like every other day. A claim nobody answered is worth more than a claim answered badly, and it looks like nothing at all until somebody counts the days. That is the one reading on this screen that turns silence into an amount payable.

SyöteOpen clocks on the projectFinal dates for paymentTulosClaims answered by no payment scheduleBreach register rows
8

Escalate with the record already assembled

Asiakirjat

When the clock has run out, give notice of intention to suspend and refer it to adjudication. The record the steps above produced, dates, approvals and the documents themselves, is the case, and it is assembled already rather than reconstructed under time pressure.

Kuvakaappaus, vaihe 8: Escalate with the record already assembled (Asiakirjat, Anna maksuvaatimus tiedoksi Construction Contracts Act -lain nojalla)
Asiakirjat: Escalate with the record already assembled

Miksi: The difference between a claim that is paid and one that is argued about is almost never the merits. It is whether the dates and the documents were kept as the work happened, because reconstructing them afterwards is expensive and looks exactly like inventing them.

SyötePassed deadlinesClaims, schedules and service datesTulosNotice of intention to suspendEntitlement preserved
Moduulit

Tämän playbookin moduulit

5 / 190 alustan moduulia

The market this case is written for

Uusi-Seelanti

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • NZS 3910
  • Construction Contracts Act

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Lisää aiheesta Kaupallinen ja sopimukset

Kaupallinen ja sopimukset

Hallinnoi aliurakkapakettia

Myönnä urakkapaketti aliurakoitsijalle, kirjaa se aliurakkasopimukseksi maksuerätaulukon ja…

3 vaihetta11 minAvaa
Kaupallinen ja sopimukset

Maksuerähakemus ja täsmäytys

Arvota tämän kauden tehty työ sopimusta vasten, tee maksuerähakemus näyttöineen, ja täsmäytä…

3 vaihetta12 minAvaa