Notificar uma reclamação de pagamento ao abrigo do Construction Contracts Act

Meça o período face ao calendário, notifique a reclamação de pagamento, vigie os dias úteis de que o pagador dispõe para responder com um calendário de pagamento, emita a fatura fiscal pelo valor calendarizado e mantenha as retenções onde a Lei exige que sejam mantidas.

8 etapas12 minEmpreiteiro geralSubempreiteiro especializadoConsultoria de custos / QS

Como funciona, passo a passo

8 passos ao longo da plataforma - o que fazer em cada um e por que importa.

1

Measure the period schedule item by schedule item

Avanço

Record what was executed against each schedule item for the period as a percentage of its contract quantity. The earned quantity follows from that percentage and the design quantity, and the earned amount from the same percentage and the position total, so one honest number per line produces the whole valuation.

Por quê: A progress valuation built from a single project percentage cannot be checked and therefore cannot be approved without a conversation. Measured line by line, the disagreement is about one schedule item rather than about the whole month, and the rest of the money moves while that one is settled.

EntradaContract scheduleWork executed this periodResultadoPercent complete per schedule itemEarned quantities for the period
2

Value it at the contract rates

Planilha Orçamentária

Read the valuation back against the bill and check the rates it used are the contract rates. Where a schedule item has been measured past the quantity the contract carries, deal with it as a change to the position with an order behind it rather than as a larger figure on the same line.

Por quê: A variation certified quietly is one the client can refuse at the final account, months after the work was built and paid for down the chain. Raising it as a change while it is small is the only version of that conversation where you are not asking to be paid for work already done.

EntradaEarned quantities for the periodContract ratesResultadoProgress valuation for the periodVariations flagged
3

Apply retentions and previous payments

Finanças

Take the cumulative valuation, subtract what has already been certified, and apply retentions at the contract percentage. The figure that leaves this step is the one the payment claim is raised for, and the backup behind it is the measure that produced it.

Por quê: Interim payments are cumulative, so the month's money is a difference between two totals rather than a total of its own. Computing it from the cumulative figure is what stops a line being paid twice or dropped entirely when a period is re-measured. Retention money on a commercial construction contract is held on trust and has to be identifiable as such, and since October 2023 it has to sit in a separate bank account and be reported to the party it is held from. A figure that exists only as a deduction line on a claim is not identifiable, and the party who needs it to be is the one who is not holding it.

EntradaCumulative progress valuationPrevious payments and retentionsResultadoRetentions held to dateNet due for the period
4

Issue the payment claim against the approved figure

Finanças

Raise the payment claim against the approved progress valuation, carrying retentions and any deduction the contract provides for, and reference the progress valuation on it. The claim has to state that it is made under the Act and say how the amount was calculated, and since 1 December 2015 every payment claim, commercial or residential, must also be accompanied by the prescribed Form 1 notice explaining the payer's obligations. A claim that does none of this is a request for money rather than a payment claim, and it carries none of the Act's consequences for ignoring it. The tax invoice follows for GST and is not the document the Act counts from.

Por quê: A demand for a figure nobody approved is one that will be returned, and the clock does not start on a returned document. Matching it to the progress valuation also means the accounts and the valuation tell the same story at year end without anybody reconciling them by hand.

EntradaProgress valuation for the periodNet due for the periodResultadoPayment claim servedTax invoice issued
5

Open the payment clock on the right day

Relógio de pagamento

Open a clock over the payment claim starting from the day the payment claim is served, under the Construction Contracts Act. Payment falls due 20 working days later, and the clock records that date rather than leaving it to be worked out when somebody asks. Twenty working days is the Act's default where the contract is silent. NZS 3910 and most commercial forms set their own shorter periods, and where they do the contract's date governs, so read the default the clock gives against the contract before relying on it.

Por quê: The single most expensive mistake in interim payment is starting the count on the wrong event, because every deadline behind it inherits the error and none of them look wrong. Anchoring on the day the payment claim is served once makes the whole chain checkable.

EntradaPayment claim servedDate of serviceResultadoOpen payment clockDue date computed
6

Read the dates the regime computes

Relógio de pagamento

Read back the dates the Construction Contracts Act produces from the day the payment claim is served. The sum payable leads, the due date and the final date for payment sit under it, and the derivation spells out each date against the provision it came from, so every one of them can be quoted rather than asserted. Working days exclude weekends, public holidays and the year-end closedown the Act sets out, which is why a December claim does not answer on the same arithmetic as a June one.

Por quê: Deadlines that are typed in are deadlines that are typed in wrong, and a payment regime has more of them than anyone holds in their head. A derivation you can read out loud is what turns a phone call about a late payment into a quotable line.

EntradaOpen payment clockStatutory regime on recordResultadoDate a payment schedule is dueFinal date for payment
7

Watch the clock count each deadline down

Relógio de pagamento

Come back to the list as the month runs. It says how many clocks the project carries and how many are past their final date, badges the overdue ones and fills the breach register underneath. Open an overdue one and the findings name the sum outstanding, the days it has run past the final date and the rate interest runs at.

Por quê: Reading a clock is what writes its register, so a quiet register on a project nobody opens is telling you about the reading and not about the payments. Nobody misses a deadline on purpose; they miss it because the day it mattered looked like every other day. A claim nobody answered is worth more than a claim answered badly, and it looks like nothing at all until somebody counts the days. That is the one reading on this screen that turns silence into an amount payable.

EntradaOpen clocks on the projectFinal dates for paymentResultadoClaims answered by no payment scheduleBreach register rows
8

Escalate with the record already assembled

Documentos

When the clock has run out, give notice of intention to suspend and refer it to adjudication. The record the steps above produced, dates, approvals and the documents themselves, is the case, and it is assembled already rather than reconstructed under time pressure.

Por quê: The difference between a claim that is paid and one that is argued about is almost never the merits. It is whether the dates and the documents were kept as the work happened, because reconstructing them afterwards is expensive and looks exactly like inventing them.

EntradaPassed deadlinesClaims, schedules and service datesResultadoNotice of intention to suspendEntitlement preserved
Módulos

Módulos deste playbook

5 / 190 módulos da plataforma

O mercado para o qual este caso foi escrito

Nova Zelândia

Tudo neste caso segue a forma como a obra é medida, orçada e paga neste mercado. Os documentos, a decomposição de custos e as regras de pagamento são os que se usam lá, não uma versão genérica.

Normas que ele segue

  • NZS 3910
  • Construction Contracts Act

Você não precisa configurar nada disso na mão. Na primeira vez que abre a plataforma, ela pergunta em que mercado você trabalha. Escolha este e ela ajusta o idioma da interface, carrega a base de custos correspondente, registra a classificação de custos e adiciona um projeto de exemplo que você pode abrir na hora.

As verificações deste mercado também vêm com a plataforma. Ative uma vez e um orçamento ao qual falte algo que o mercado espera é sinalizado enquanto você trabalha nele, e não depois que a proposta já saiu.

Mais em Comercial e contratos

Comercial e contratos

Gerir um pacote de subempreitada

Adjudique um pacote de trabalhos a um subempreiteiro, coloque-o num subcontrato com um mapa…

3 etapas11 minAbrir
Comercial e contratos

Fatura de pagamento e conciliação

Valorize o trabalho executado neste período face ao contrato, apresente a fatura com a evidê…

3 etapas12 minAbrir