Obračunajte GST na progress payment u pravom trenutku

Utvrdite stopu jednom zauvijek, odredite je li ugovorena cijena s GST-om ili bez njega, izračunajte time of supply za radove plaćene u ratama, unesite taxable supply information na svaki claim, prijavite u pravom poreznom razdoblju i vodite evidencije koje Act zahtijeva.

6 koraka13 minGlavni izvođačSpecijalizirani podizvođačKonzalting za troškove / QS

Kako funkcionira, korak po korak

6 koraka kroz platformu - što radite u svakom i zašto je važno.

1

Set the rate once with the date it took effect

Porezne stope

Record GST at 15 percent with the date it took effect, 1 October 2010, so that anything valued before that date is computed at the rate that applied then rather than at today's. Keep it as one setting the whole system reads instead of a number typed into each template.

Snimka zaslona, korak 1: Set the rate once with the date it took effect (Porezne stope, Obračunajte GST na progress payment u pravom trenutku)
Porezne stope: Set the rate once with the date it took effect

Zašto: A rate that lives in six templates is a rate that will be six different numbers the first time it changes, and the errors will be in the templates nobody uses often. Holding the effective date beside it is what lets an old valuation, a retrospective claim or a long-running contract be recomputed correctly instead of being quietly restated at the current rate.

UlazGST registrationWhere the work is suppliedRezultatRate set once, used everywhereEffective date on record
2

Settle whether the price includes it, and when payment falls due

Ugovori

Record two things off the contract: whether the contract price is stated inclusive or exclusive of GST, and the rule that decides when a progress payment becomes due, which on a construction contract is usually a number of working days after a claim is served or certified. Both belong on the contract record where the person raising claims can see them.

Snimka zaslona, korak 2: Settle whether the price includes it, and when payment falls due (Ugovori, Obračunajte GST na progress payment u pravom trenutku)
Ugovori: Settle whether the price includes it, and when payment falls due

Zašto: An inclusive price misread as exclusive is a thirteen percent error on the whole contract, and it survives review because both readings produce a plausible number. The due date rule matters for a different reason: it is one of the three dates the time of supply test looks at, so a contract term is doing tax work whether or not anybody in the finance team has read it.

UlazContract price and payment termsWhen a payment becomes dueRezultatInclusive or exclusive settledDue date rule on record
3

Fix the time of supply for the instalment

Financije

For each progress payment take the earliest of three dates: the date the payment becomes due under the contract, the date it is actually received, and the date an invoice is issued for it. That date decides the period the GST belongs to. Deal with the retention slice separately, because retention money is accounted for when it becomes payable rather than when it was deducted from the claim.

Snimka zaslona, korak 3: Fix the time of supply for the instalment (Financije, Obračunajte GST na progress payment u pravom trenutku)
Financije: Fix the time of supply for the instalment

Zašto: This is where construction differs from ordinary trading and where the money is lost. On the invoice basis the tax can fall due in a period when the payer has not paid, so a slow client funds its own delay out of your account. Knowing the date in advance turns that into a planned outflow rather than a surprise in the week the return is filed.

UlazProgress claim for the periodDue date rule on recordRezultatTime of supply for the instalmentRetention slice timed separately
4

Check every document carries the taxable supply information

Validacija

Run the check over the documents you issue: the supplier's name and GST number, the date, a description of the work, the amount and the GST, and the recipient's details where the value requires them. Since 1 April 2023 this is taxable supply information rather than a document that has to be headed tax invoice, and it may be spread across more than one document as long as the set is complete.

Snimka zaslona, korak 4: Check every document carries the taxable supply information (Validacija, Obračunajte GST na progress payment u pravom trenutku)
Validacija: Check every document carries the taxable supply information

Zašto: The obligation is now about information rather than about a form, which is easier to satisfy and easier to fail quietly, because a document that looks like every other invoice can be missing the one field that lets your customer claim the input tax. They discover it at their return, months later, and the correction lands on the relationship as well as on the paperwork.

UlazClaims and invoices issuedInformation the Act requiresRezultatDocuments carrying what they mustDocuments missing a field
5

Line the periods up with the cash

Izvješća

Read the output tax the period carries against the input tax on what you bought, and read both against when the money actually moves. Record which accounting basis the business is on, because the invoice basis and the payments basis put the same job's tax in different periods, and the payments basis is only open to smaller registered persons.

Snimka zaslona, korak 5: Line the periods up with the cash (Izvješća, Obračunajte GST na progress payment u pravom trenutku)
Izvješća: Line the periods up with the cash

Zašto: A construction business fails on cash rather than on margin, and GST is one of the largest predictable outflows it has. Read a month ahead it is a payment to plan for. Read on the due date it is the reason a subcontractor waits, and that has consequences under a different Act entirely.

UlazTime of supply per instalmentTaxable period and accounting basisRezultatOutput and input tax for the periodCash the return will take
6

Keep the records for as long as the Act asks

Dokumenti

File the claims, the taxable supply information, the credit notes and the workings behind each return together, project by project, and keep them for seven years. Keep the workings, not only the outputs, because a query is always about how a figure was arrived at rather than about what it was.

Snimka zaslona, korak 6: Keep the records for as long as the Act asks (Dokumenti, Obračunajte GST na progress payment u pravom trenutku)
Dokumenti: Keep the records for as long as the Act asks

Zašto: Seven years is longer than most construction businesses keep their project folders and longer than most of the people who built the job stay in it. A query about a return from four years ago is answered in an hour by a business that filed the workings and in a fortnight by one that has to rebuild them from bank statements.

UlazClaims, invoices and returnsWorkings behind each figureRezultatRecords kept for seven yearsOne place to answer a query from
Moduli

Moduli u ovom playbooku

6 / 190 modula platforme

The market this case is written for

Novi Zeland

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • NZS 3910
  • Construction Contracts Act

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Više u kategoriji Komercijala i ugovori

Komercijala i ugovori

Vodite podizvođački paket

Dodijelite paket radova podizvođaču, sklopite podugovor s tabelarnim pregledom vrijednosti i…

3 koraka11 minOtvori
Komercijala i ugovori

Zahtjev za plaćanje i usklađivanje

Vrednujte radove izvedene u ovom razdoblju u odnosu na ugovor, podnesite zahtjev za plaćanje…

3 koraka12 minOtvori