Cobre GST num pagamento progressivo no momento certo

Fixe a taxa uma vez, defina se o preço do contrato inclui ou exclui GST, apure o time of supply do trabalho pago em prestações, coloque a taxable supply information em cada pedido, declare no período correcto e guarde os registos que o Act exige.

6 etapas13 minEmpreiteiro geralSubempreiteiro especializadoConsultoria de custos / QS

Como funciona, passo a passo

6 passos ao longo da plataforma - o que fazer em cada um e por que importa.

1

Set the rate once with the date it took effect

Taxas de imposto

Record GST at 15 percent with the date it took effect, 1 October 2010, so that anything valued before that date is computed at the rate that applied then rather than at today's. Keep it as one setting the whole system reads instead of a number typed into each template.

Por quê: A rate that lives in six templates is a rate that will be six different numbers the first time it changes, and the errors will be in the templates nobody uses often. Holding the effective date beside it is what lets an old valuation, a retrospective claim or a long-running contract be recomputed correctly instead of being quietly restated at the current rate.

EntradaGST registrationWhere the work is suppliedResultadoRate set once, used everywhereEffective date on record
2

Settle whether the price includes it, and when payment falls due

Contratos

Record two things off the contract: whether the contract price is stated inclusive or exclusive of GST, and the rule that decides when a progress payment becomes due, which on a construction contract is usually a number of working days after a claim is served or certified. Both belong on the contract record where the person raising claims can see them.

Por quê: An inclusive price misread as exclusive is a thirteen percent error on the whole contract, and it survives review because both readings produce a plausible number. The due date rule matters for a different reason: it is one of the three dates the time of supply test looks at, so a contract term is doing tax work whether or not anybody in the finance team has read it.

EntradaContract price and payment termsWhen a payment becomes dueResultadoInclusive or exclusive settledDue date rule on record
3

Fix the time of supply for the instalment

Finanças

For each progress payment take the earliest of three dates: the date the payment becomes due under the contract, the date it is actually received, and the date an invoice is issued for it. That date decides the period the GST belongs to. Deal with the retention slice separately, because retention money is accounted for when it becomes payable rather than when it was deducted from the claim.

Por quê: This is where construction differs from ordinary trading and where the money is lost. On the invoice basis the tax can fall due in a period when the payer has not paid, so a slow client funds its own delay out of your account. Knowing the date in advance turns that into a planned outflow rather than a surprise in the week the return is filed.

EntradaProgress claim for the periodDue date rule on recordResultadoTime of supply for the instalmentRetention slice timed separately
4

Check every document carries the taxable supply information

Validação

Run the check over the documents you issue: the supplier's name and GST number, the date, a description of the work, the amount and the GST, and the recipient's details where the value requires them. Since 1 April 2023 this is taxable supply information rather than a document that has to be headed tax invoice, and it may be spread across more than one document as long as the set is complete.

Por quê: The obligation is now about information rather than about a form, which is easier to satisfy and easier to fail quietly, because a document that looks like every other invoice can be missing the one field that lets your customer claim the input tax. They discover it at their return, months later, and the correction lands on the relationship as well as on the paperwork.

EntradaClaims and invoices issuedInformation the Act requiresResultadoDocuments carrying what they mustDocuments missing a field
5

Line the periods up with the cash

Relatórios

Read the output tax the period carries against the input tax on what you bought, and read both against when the money actually moves. Record which accounting basis the business is on, because the invoice basis and the payments basis put the same job's tax in different periods, and the payments basis is only open to smaller registered persons.

Por quê: A construction business fails on cash rather than on margin, and GST is one of the largest predictable outflows it has. Read a month ahead it is a payment to plan for. Read on the due date it is the reason a subcontractor waits, and that has consequences under a different Act entirely.

EntradaTime of supply per instalmentTaxable period and accounting basisResultadoOutput and input tax for the periodCash the return will take
6

Keep the records for as long as the Act asks

Documentos

File the claims, the taxable supply information, the credit notes and the workings behind each return together, project by project, and keep them for seven years. Keep the workings, not only the outputs, because a query is always about how a figure was arrived at rather than about what it was.

Por quê: Seven years is longer than most construction businesses keep their project folders and longer than most of the people who built the job stay in it. A query about a return from four years ago is answered in an hour by a business that filed the workings and in a fortnight by one that has to rebuild them from bank statements.

EntradaClaims, invoices and returnsWorkings behind each figureResultadoRecords kept for seven yearsOne place to answer a query from
Módulos

Módulos deste playbook

6 / 190 módulos da plataforma

O mercado para o qual este caso foi escrito

Nova Zelândia

Tudo neste caso segue a forma como a obra é medida, orçada e paga neste mercado. Os documentos, a decomposição de custos e as regras de pagamento são os que se usam lá, não uma versão genérica.

Normas que ele segue

  • NZS 3910
  • Construction Contracts Act

Você não precisa configurar nada disso na mão. Na primeira vez que abre a plataforma, ela pergunta em que mercado você trabalha. Escolha este e ela ajusta o idioma da interface, carrega a base de custos correspondente, registra a classificação de custos e adiciona um projeto de exemplo que você pode abrir na hora.

As verificações deste mercado também vêm com a plataforma. Ative uma vez e um orçamento ao qual falte algo que o mercado espera é sinalizado enquanto você trabalha nele, e não depois que a proposta já saiu.

Mais em Comercial e contratos

Comercial e contratos

Gerir um pacote de subempreitada

Adjudique um pacote de trabalhos a um subempreiteiro, coloque-o num subcontrato com um mapa…

3 etapas11 minAbrir
Comercial e contratos

Fatura de pagamento e conciliação

Valorize o trabalho executado neste período face ao contrato, apresente a fatura com a evidê…

3 etapas12 minAbrir