케이스 / 적산 및 원가
적산 및 원가

자원법으로 GESN 표준품셈에 따라 smeta를 작성하기

계약이 지정한 표준품셈집을 가져와 각 품셈을 노무, 장비, 자재 소요량으로 전개하고, 그 자원들을 현재 시세로 단가화하여 lokalnaya smeta(부분견적)로 산출함으로써, 각 단가가 그 출처가 된 품셈까지 거슬러 열리도록 한다.

7단계14 분종합건설사전문건설사원가 컨설팅 / 적산 업체시행사 / 발주처

작동 방식, 단계별로

플랫폼 전반에 걸친 7단계 - 각 단계에서 무엇을 하는지, 그리고 왜 중요한지.

1

Pick the norm collection the job is priced on

단가 데이터베이스

Open the cost database and choose the collection the job is actually priced on: GESN when you will price the resources yourself, FER when a federal unit rate governs, TER when the region has approved its own territorial rates. Record the edition alongside it, because a norm number is only unique inside its edition.

스크린샷, 1단계: Pick the norm collection the job is priced on (단가 데이터베이스, 자원법으로 GESN 표준품셈에 따라 smeta를 작성하기)
단가 데이터베이스: Pick the norm collection the job is priced on

이유: GESN and FER are two readings of the same federal norm base, published together as FSNB, while TER are the territorial equivalents a region approves for its own territory. GESN carries physical consumption and no prices, FER and TER carry rates already priced in base year money. Starting on the wrong one is not a rounding error: it decides whether the resource method is open to you at all, and whether state expertise will accept the result.

입력Contract or technical assignmentRegion of the works결과Selected norm collectionEdition on record
2

Expand each norm into the resources it fixes

품셈

Open the norm and read what it contains: man hours by trade grade, machine hours by machine type, and the material quantity per unit of measure. Adjust a quantity only where the technical part of the collection allows it, and write down the clause you relied on next to the change.

이유: The consumption inside a GESN norm is the state's statement of what the work takes, and it is the half of the price nobody is free to invent. A resource quantity moved without the technical part behind it is the first thing an expertise reviewer writes up, because it can be spotted without recalculating anything.

입력Norm numberTechnical part of the collection결과Resource list per unitClause behind any adjustment
3

Price the resources at current money

자원 카탈로그

Give every resource a price: the hourly wage for the grade in this region, the machine hour rate with the operator in it, and the material price from your own quotes delivered to site rather than ex works. Keep the source and the date on each price.

스크린샷, 3단계: Price the resources at current money (자원 카탈로그, 자원법으로 GESN 표준품셈에 따라 smeta를 작성하기)
자원 카탈로그: Price the resources at current money

이유: This is the step that makes the method resource based rather than index based. A price without a named source cannot be defended when the customer asks where the figure came from, and a price without a date cannot be re-based when the job runs into the following year.

입력Supplier quotesRegional wage per grade결과Priced resource catalogueSource and date per price
4

Compose the work you repeat into assemblies

일위대가

Where the same combination of norms and resources comes back section after section, save it once as an assembly with its own unit of measure, so the next section and the next project start from it instead of from the norm list again.

스크린샷, 4단계: Compose the work you repeat into assemblies (일위대가, 자원법으로 GESN 표준품셈에 따라 smeta를 작성하기)
일위대가: Compose the work you repeat into assemblies

이유: A smeta of several thousand positions cannot be kept consistent line by line, and inconsistency between two identical items in different sections is exactly what a reviewer picks up. An assembly also carries the reasoning with it, which is what lets a second estimator take over your file without rebuilding it.

입력Norms that recurPriced resources결과Saved assemblyAssembly unit rate
5

Post the positions into the lokalnaya smeta

내역서

Enter each priced position with its quantity from the takeoff, grouped into sections the way the working drawings divide the work, and keep the norm number, the unit of measure and the resource-built rate on every line.

스크린샷, 5단계: Post the positions into the lokalnaya smeta (내역서, 자원법으로 GESN 표준품셈에 따라 smeta를 작성하기)
내역서: Post the positions into the lokalnaya smeta

이유: The lokalnaya smeta is the document every summary above it is built from: object smetas sum the locals and the svodnyy smetnyy raschet sums the objects. A wrong quantity or a wrong norm number here is wrong in every summary above it, and the summaries are what the customer actually reads.

입력Quantities from the takeoffResource-built rates결과Lokalnaya smetaSections matching the drawings
6

Apply NR and SP on the base each is calculated from

내역서

In the bill's Markups & Overheads panel, apply the Russian template to bring in the national stack in its order, overheads (NR), estimated profit (SP), the reserve line and NDS, then set the NR and SP rate for each type of work from the norms rather than leaving one rate on the whole bill. Read what each line is applied to: the shipped template carries NR and SP as an effective percentage of direct cost, because a bill markup can take direct cost or the running total as its base and payroll is neither.

스크린샷, 6단계: Apply NR and SP on the base each is calculated from (내역서, 자원법으로 GESN 표준품셈에 따라 smeta를 작성하기)
내역서: Apply NR and SP on the base each is calculated from

이유: The norm sets NR and SP against payroll, worker wages plus machine operator wages, and by type of work, not against the position total. An effective percentage of direct cost keeps the bill total right for a typical work mix and wrong in its sensitivity, so on a bill whose labour share is far from typical rebuild the markup on the resource decomposition rather than trusting the line. Applying either to material or equipment cost inflates the smeta in a way a reviewer finds by arithmetic alone.

입력Type of work per sectionLabour cost per position결과NR applied by tradeSP applied by trade
7

Read the resource summary the method produces

자원 요약

Open the summary the smeta rolls up to: total man hours, machine hours by machine type and material quantities by nomenclature across the whole estimate, and read it against what the job plausibly needs in crews, plant and deliveries.

스크린샷, 7단계: Read the resource summary the method produces (자원 요약, 자원법으로 GESN 표준품셈에 따라 smeta를 작성하기)
자원 요약: Read the resource summary the method produces

이유: The output of the resource method is not only a total in roubles. The same summary is what the works schedule, the crew plan and the material procurement are built from, and it is the norm baseline that the M-29 material reconciliation will later compare actual consumption against.

입력Completed smetaMaterial nomenclature결과Man hours and machine hoursMaterial quantities by nomenclature
모듈

이 플레이북의 모듈

플랫폼 190개 모듈 중 6개

The market this case is written for

러시아

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • GESN/FER
  • KS-2 / KS-3

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

적산 및 원가 카테고리의 더 보기

적산 및 원가

발송 전 견적 점검

산출된 내역서를 검증 규칙에 통과시켜 모든 경고와 오류를 해결한 뒤, 발주자에게 바로 전달할 수 있는 깨끗한 보고서를 내보냅니다.

3단계8 분열기
적산 및 원가

원가 데이터베이스로 견적 산정하기

실제 원가 데이터베이스에서 가격 항목을 가져와 내역서를 작성하고, 반복되는 조합을 어셈블리로 묶은 뒤, 입찰 금액을 확정하기 전에 검토를 실행합니다.

4단계12 분열기
적산 및 원가

비용 리스크로 예비비 산정하기

단일 값 견적을 범위로 바꾸고, 실제로 불확실한 항목에 대해 몬테카를로 시뮬레이션을 실행하여 P50~P90 분포를 읽고, 항목별로 근거를 설명할 수 있는 예비비를 설…

3단계11 분열기