Saudi Building Code 준수를 입증하기

해당 공사가 따르는 코드 권(volume)을 명시하고, 설계를 검토 절차에 부치고, 자재를 발주하기 전에 승인하고, 수입 제품의 적합성 서류를 확인하고, 사양이 아니라 조항에 대해 시험하고, 다른 사람도 읽을 수 있는 준수 파일을 남긴다.

7단계17 분설계 / 엔지니어링 업체종합건설사PM/CM 업체시행사 / 발주처

작동 방식, 단계별로

플랫폼 전반에 걸친 7단계 - 각 단계에서 무엇을 하는지, 그리고 왜 중요한지.

1

Name the code volumes this building is built to

품질 관리

Record the volumes that govern the job and the edition of each: SBC 201 for the general requirements, the 300 series for the structure, SBC 401 for electrical, SBC 601 for energy and SBC 801 for fire protection, together with whichever others the occupancy pulls in. Give each one a named discipline owner.

이유: A specification that says the works shall comply with the Saudi Building Code has said almost nothing, because the code is a shelf of volumes with editions. Naming volume and edition is what lets a reviewer check a clause and a contractor price to a standard rather than to a phrase, and it is the difference between an argument about the clause and an argument about which book you were both reading.

입력Design brief and occupancyContract specification결과Code register for the jobA discipline owner per volume
2

Take the design through review before it goes to the authority

권한 검토

Route the drawings and calculations through the reviewing parties in order, the licensed engineering office that will certify the submission last, and record every comment against the clause it cites and the revision that answered it.

이유: The permit is issued on a design an engineering office has put its name to, so the office's comments are not opinions, they are the conditions of the certificate. Answering them in a marked up PDF that nobody keeps means the same comment returns three revisions later, and the reviewer, who does keep a record, reads the repetition as a design that is not being controlled.

입력Design drawings and calculationsCode register결과Review comments closedDesign certified for submission
3

Approve the material before anybody orders it

제출물

Raise a submittal for each material and system, with the clause it answers, the test evidence or type approval behind it and the standard it is certified to, and get it approved or refused with a date. Where a substitution is proposed on price or on lead time, run it through the same route rather than around it.

이유: The expensive failure is never the product that was refused, it is the one nobody submitted. Material that arrives on site with no approval behind it is material somebody will have to justify after it is built in, and the cost of taking it out is paid by whoever cannot show the paper. A dated approval is also the record that decides who pays when the code compliance of an installed system is questioned.

입력Specification clauseProposed product결과Material approvedSubstitutions refused
4

Check the conformity documents on anything imported

조달

For every imported product covered by a Saudi technical regulation, confirm the supplier holds a product certificate of conformity and that each consignment is accompanied by a shipment certificate, both issued electronically through the national conformity platform, and file them against the purchase order rather than in the freight forwarder's email.

이유: Conformity certification is a customs gate, not a quality nicety. A consignment of cable or of fire rated doors that arrives without its shipment certificate sits at the port while the certificate is chased, and the delay lands on the critical path of whichever trade was waiting. Checking it at the order stage costs an email and moves the risk to the supplier who can actually fix it.

입력Purchase ordersImported consignments결과Conformity certificates heldConsignments clear customs
5

Test against the clause, not against the delivery note

검사

Work the inspection and test plan on site with the code clause named on each hold point: concrete sampled and tested at the frequency the structural volumes require, earthworks compaction proven, fire stopping inspected before it is concealed, and every result signed by whoever witnessed it.

이유: A test result without the clause it answers is a number in a folder. Named against the clause, the same result closes a hold point and can be handed to a reviewer without a covering explanation. The hold points that matter most are the ones that get covered up, because the only alternative evidence is opening the work again.

입력Approved materialsInspection and test plan결과Test results against the clauseSigned inspection records
6

Raise a non-conformance when a clause is not met

부적합

Where work does not meet the clause, raise it as a non-conformance naming the volume and the clause, the extent of the work affected and the proposed disposition, whether that is rework, repair, a concession sought from the designer or acceptance as is, and close it with the evidence that the disposition was carried out.

이유: Non-conformances handled informally are handled twice, once quietly on site and once loudly at handover when the reviewer asks about the same pour. Recorded, the item has an extent, an owner and an end, and a concession granted by the designer is a decision with a name on it rather than a rumour that the engineer said it was fine.

입력Failed tests and findingsClause not met결과Non-conformance raisedDisposition agreed
7

Leave a compliance file somebody else can read

문서

Assemble the file the building will be judged on: approved submittals with their conformity certificates, test and inspection records, closed non-conformances and the as built drawings, indexed by the code volume and clause each item answers.

이유: The file is read by people who were not there, at completion, at the sale of the asset, and after an incident. Indexed by clause it answers a question in a minute. Filed by trade and date it answers nothing, and the practical effect is that work which was compliant gets treated as unproven, which costs the same as being wrong.

입력Approvals, tests, closuresAs built drawings결과Compliance fileIndexed by clause
모듈

이 플레이북의 모듈

플랫폼 190개 모듈 중 7

The market this case is written for

사우디아라비아

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • Saudi Building Code
  • Government Tenders and Procurement Law

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

품질 및 안전 카테고리의 더 보기

품질 및 안전

공사 검사 및 부적합(NCR) 종결하기

인수 기준에 따라 공사를 검사하고, 불합격 즉시 부적합(NCR)을 제기한 뒤, 시정 조치를 진행하고 재검사하여 하자가 실제로 해결되었음을 기록으로 남깁니다.

3단계10 분열기
품질 및 안전

툴박스 토크 및 안전 점검

이번 근무조가 실제로 마주할 위험 요소를 브리핑하고, 참석자를 기록한 뒤, 순회 점검을 통해 합의한 통제 수단이 실제로 갖춰져 있는지 증명합니다.

2단계8 분열기
품질 및 안전

자재 제출물 승인 받기

구매하려는 제품 자료를 근거와 함께 설계자에게 제출하고, 사양서와 대조해 검토받은 후 승인된 경우에만 발주로 진행한다.

3단계9 분열기