案例 / 质量与安全
质量与安全

证明工程符合沙特建筑规范(SBC)

写明这项工程依据规范的哪些分册建造,让设计通过审查,在下单之前先批准材料,核查进口产品的合格证明文件,按规范条款而不是按规格书做检测,并留下一份别人也读得懂的合规档案。

7 个步骤17 分钟设计/工程顾问公司总承包商项目/施工管理公司开发商/业主

运作方式,逐步说明

贯穿平台的 7 个步骤 - 每一步做什么,以及为什么重要。

1

Name the code volumes this building is built to

质量管理

Record the volumes that govern the job and the edition of each: SBC 201 for the general requirements, the 300 series for the structure, SBC 401 for electrical, SBC 601 for energy and SBC 801 for fire protection, together with whichever others the occupancy pulls in. Give each one a named discipline owner.

原因: A specification that says the works shall comply with the Saudi Building Code has said almost nothing, because the code is a shelf of volumes with editions. Naming volume and edition is what lets a reviewer check a clause and a contractor price to a standard rather than to a phrase, and it is the difference between an argument about the clause and an argument about which book you were both reading.

输入Design brief and occupancyContract specification成果Code register for the jobA discipline owner per volume
2

Take the design through review before it goes to the authority

审核主管部门

Route the drawings and calculations through the reviewing parties in order, the licensed engineering office that will certify the submission last, and record every comment against the clause it cites and the revision that answered it.

原因: The permit is issued on a design an engineering office has put its name to, so the office's comments are not opinions, they are the conditions of the certificate. Answering them in a marked up PDF that nobody keeps means the same comment returns three revisions later, and the reviewer, who does keep a record, reads the repetition as a design that is not being controlled.

输入Design drawings and calculationsCode register成果Review comments closedDesign certified for submission
3

Approve the material before anybody orders it

提交物

Raise a submittal for each material and system, with the clause it answers, the test evidence or type approval behind it and the standard it is certified to, and get it approved or refused with a date. Where a substitution is proposed on price or on lead time, run it through the same route rather than around it.

原因: The expensive failure is never the product that was refused, it is the one nobody submitted. Material that arrives on site with no approval behind it is material somebody will have to justify after it is built in, and the cost of taking it out is paid by whoever cannot show the paper. A dated approval is also the record that decides who pays when the code compliance of an installed system is questioned.

输入Specification clauseProposed product成果Material approvedSubstitutions refused
4

Check the conformity documents on anything imported

采购

For every imported product covered by a Saudi technical regulation, confirm the supplier holds a product certificate of conformity and that each consignment is accompanied by a shipment certificate, both issued electronically through the national conformity platform, and file them against the purchase order rather than in the freight forwarder's email.

原因: Conformity certification is a customs gate, not a quality nicety. A consignment of cable or of fire rated doors that arrives without its shipment certificate sits at the port while the certificate is chased, and the delay lands on the critical path of whichever trade was waiting. Checking it at the order stage costs an email and moves the risk to the supplier who can actually fix it.

输入Purchase ordersImported consignments成果Conformity certificates heldConsignments clear customs
5

Test against the clause, not against the delivery note

检查

Work the inspection and test plan on site with the code clause named on each hold point: concrete sampled and tested at the frequency the structural volumes require, earthworks compaction proven, fire stopping inspected before it is concealed, and every result signed by whoever witnessed it.

原因: A test result without the clause it answers is a number in a folder. Named against the clause, the same result closes a hold point and can be handed to a reviewer without a covering explanation. The hold points that matter most are the ones that get covered up, because the only alternative evidence is opening the work again.

输入Approved materialsInspection and test plan成果Test results against the clauseSigned inspection records
6

Raise a non-conformance when a clause is not met

不符合项

Where work does not meet the clause, raise it as a non-conformance naming the volume and the clause, the extent of the work affected and the proposed disposition, whether that is rework, repair, a concession sought from the designer or acceptance as is, and close it with the evidence that the disposition was carried out.

原因: Non-conformances handled informally are handled twice, once quietly on site and once loudly at handover when the reviewer asks about the same pour. Recorded, the item has an extent, an owner and an end, and a concession granted by the designer is a decision with a name on it rather than a rumour that the engineer said it was fine.

输入Failed tests and findingsClause not met成果Non-conformance raisedDisposition agreed
7

Leave a compliance file somebody else can read

文档

Assemble the file the building will be judged on: approved submittals with their conformity certificates, test and inspection records, closed non-conformances and the as built drawings, indexed by the code volume and clause each item answers.

原因: The file is read by people who were not there, at completion, at the sale of the asset, and after an incident. Indexed by clause it answers a question in a minute. Filed by trade and date it answers nothing, and the practical effect is that work which was compliant gets treated as unproven, which costs the same as being wrong.

输入Approvals, tests, closuresAs built drawings成果Compliance fileIndexed by clause
模块

此方案使用的模块

190 个平台模块中的 7

The market this case is written for

沙特阿拉伯

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • Saudi Building Code
  • Government Tenders and Procurement Law

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

更多 质量与安全 案例

质量与安全

检查工程并关闭不符合项

依据验收标准检查工程,一旦不合格立即提出不符合项,推动整改并复检,使记录能证明缺陷已确实修复。