Inspecionar o trabalho e encerrar uma não conformidade
Inspecione o trabalho face aos seus critérios de aceitação, levante uma não conformidade ass…
Identifique os volumes do código a que a obra é construída, leve o projeto a revisão, aprove os materiais antes de serem encomendados, verifique os documentos de conformidade dos produtos importados, ensaie contra a cláusula e não contra o caderno de encargos, e deixe um processo de conformidade que outra pessoa consiga ler.
7 passos ao longo da plataforma - o que fazer em cada um e por que importa.
Record the volumes that govern the job and the edition of each: SBC 201 for the general requirements, the 300 series for the structure, SBC 401 for electrical, SBC 601 for energy and SBC 801 for fire protection, together with whichever others the occupancy pulls in. Give each one a named discipline owner.
Por quê: A specification that says the works shall comply with the Saudi Building Code has said almost nothing, because the code is a shelf of volumes with editions. Naming volume and edition is what lets a reviewer check a clause and a contractor price to a standard rather than to a phrase, and it is the difference between an argument about the clause and an argument about which book you were both reading.
Route the drawings and calculations through the reviewing parties in order, the licensed engineering office that will certify the submission last, and record every comment against the clause it cites and the revision that answered it.
Por quê: The permit is issued on a design an engineering office has put its name to, so the office's comments are not opinions, they are the conditions of the certificate. Answering them in a marked up PDF that nobody keeps means the same comment returns three revisions later, and the reviewer, who does keep a record, reads the repetition as a design that is not being controlled.
Raise a submittal for each material and system, with the clause it answers, the test evidence or type approval behind it and the standard it is certified to, and get it approved or refused with a date. Where a substitution is proposed on price or on lead time, run it through the same route rather than around it.
Por quê: The expensive failure is never the product that was refused, it is the one nobody submitted. Material that arrives on site with no approval behind it is material somebody will have to justify after it is built in, and the cost of taking it out is paid by whoever cannot show the paper. A dated approval is also the record that decides who pays when the code compliance of an installed system is questioned.
For every imported product covered by a Saudi technical regulation, confirm the supplier holds a product certificate of conformity and that each consignment is accompanied by a shipment certificate, both issued electronically through the national conformity platform, and file them against the purchase order rather than in the freight forwarder's email.
Por quê: Conformity certification is a customs gate, not a quality nicety. A consignment of cable or of fire rated doors that arrives without its shipment certificate sits at the port while the certificate is chased, and the delay lands on the critical path of whichever trade was waiting. Checking it at the order stage costs an email and moves the risk to the supplier who can actually fix it.
Work the inspection and test plan on site with the code clause named on each hold point: concrete sampled and tested at the frequency the structural volumes require, earthworks compaction proven, fire stopping inspected before it is concealed, and every result signed by whoever witnessed it.
Por quê: A test result without the clause it answers is a number in a folder. Named against the clause, the same result closes a hold point and can be handed to a reviewer without a covering explanation. The hold points that matter most are the ones that get covered up, because the only alternative evidence is opening the work again.
Where work does not meet the clause, raise it as a non-conformance naming the volume and the clause, the extent of the work affected and the proposed disposition, whether that is rework, repair, a concession sought from the designer or acceptance as is, and close it with the evidence that the disposition was carried out.
Por quê: Non-conformances handled informally are handled twice, once quietly on site and once loudly at handover when the reviewer asks about the same pour. Recorded, the item has an extent, an owner and an end, and a concession granted by the designer is a decision with a name on it rather than a rumour that the engineer said it was fine.
Assemble the file the building will be judged on: approved submittals with their conformity certificates, test and inspection records, closed non-conformances and the as built drawings, indexed by the code volume and clause each item answers.
Por quê: The file is read by people who were not there, at completion, at the sale of the asset, and after an incident. Indexed by clause it answers a question in a minute. Filed by trade and date it answers nothing, and the practical effect is that work which was compliant gets treated as unproven, which costs the same as being wrong.
7 / 190 módulos da plataforma
Tudo neste caso segue a forma como a obra é medida, orçada e paga neste mercado. Os documentos, a decomposição de custos e as regras de pagamento são os que se usam lá, não uma versão genérica.
Normas que ele segue
Você não precisa configurar nada disso na mão. Na primeira vez que abre a plataforma, ela pergunta em que mercado você trabalha. Escolha este e ela ajusta o idioma da interface, carrega a base de custos correspondente, registra a classificação de custos e adiciona um projeto de exemplo que você pode abrir na hora.
As verificações deste mercado também vêm com a plataforma. Ative uma vez e um orçamento ao qual falte algo que o mercado espera é sinalizado enquanto você trabalha nele, e não depois que a proposta já saiu.
Inspecione o trabalho face aos seus critérios de aceitação, levante uma não conformidade ass…
Informe a equipa sobre os perigos reais deste turno, registe quem esteve presente, e depois…
Apresente ao projetista o produto que pretende comprar com os dados que o sustentam, faça-o…