IS 456에 따라 타설 카드부터 공시체 시험 결과까지 콘크리트를 관리하기

콘크리트 검사 및 시험 계획을 작성하고, 타설 시작 전마다 승인을 받고, 공시체를 채취한 타설과 연계해 제작·추적하고, 불합격 결과에 올바르게 대응하며, 인수인계에 필요한 성적서를 보관합니다.

5단계20 분종합건설사PM/CM 업체전문건설사시행사 / 발주처

작동 방식, 단계별로

플랫폼 전반에 걸친 5단계 - 각 단계에서 무엇을 하는지, 그리고 왜 중요한지.

1

Write the test plan before the first pour, not after

품질 관리

Set out, per grade and per element type, what is checked and when: mix approval, workability at the point of placing, the sampling frequency the code sets by volume placed, the ages at which cubes are tested, curing, and formwork striking. Mark the pre-pour check as a hold point rather than as a notification.

이유: A hold point is the only instrument that survives a busy site. A check written as a notification is done when there is time, which on a pour day there is not, and the pour goes ahead because stopping it costs a truck of concrete.

입력Specification and gradesThe code requirements that apply결과An inspection and test plan for concreteHold points nobody may pass
2

Clear the pour on the things that disappear

검사

Inspect against the plan before concrete is called: bar size, spacing and laps against the schedule, cover blocks in place and of the right thickness, the detailing at joints and confinement zones, formwork line and support, and the element clean. Photograph the reinforcement, and record who cleared it.

이유: Everything in that list is invisible an hour later and expensive to verify afterwards. Cover in particular decides how long the structure lasts and cannot be inspected once poured, so the record made at this moment is the only evidence that will ever exist.

입력The element about to be pouredReinforcement drawings and schedules결과A cleared pour, with evidenceWhat the reinforcement looked like
3

Cast the cubes and tie them to the element, not to the day

양식 및 체크리스트

Fill the pour card as the concrete is placed: grade, volume, time, workability reading, weather, and the identification of every cube cast from it, against the element being poured. Record the test ages that fall due from those dates.

이유: Cubes identified only by date are useless on a site pouring three elements a day. When a result comes back low, the question is which element it belongs to, and a card that answers that turns a structural investigation into a check of one beam.

입력The pour, its grade and its volume결과Cubes tied to the element they came fromTest dates falling due
4

Treat a low result as a bounded non-conformance

부적합

Read the results against the acceptance criteria the code sets, and where they fall short, raise a non-conformance naming the element, the pour and the volume affected. Record the further testing or structural assessment agreed, and who signs off the outcome.

이유: A low seven day result is information, not a verdict, and a low twenty-eight day result has a defined route through it. What decides the cost is whether the extent is known. A non-conformance that names one element is a repair; one that cannot say which pour it belongs to becomes a survey of a floor.

입력Cube results at each age결과A non-conformance with a known extentThe route to acceptance or rejection
5

File the certificates against the structure they prove

문서

Keep the pour cards, the laboratory certificates, the pre-pour clearances and any non-conformance and its closure together, organised by element rather than by month.

이유: At handover, and at any later query about the structure, the question is always about a part of the building rather than about a period of time. A file arranged by element answers it in minutes; one arranged by month is searched by somebody who was not there.

입력Test certificates and pour cards결과A concrete file arranged by element
모듈

이 플레이북의 모듈

플랫폼 190개 모듈 중 5

The market this case is written for

인도

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CPWD DSR
  • IS 456
  • RERA

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

품질 및 안전 카테고리의 더 보기

품질 및 안전

Toolbox talk and safety check

Brief the crew on the hazards this shift actually carries, capture who was there, then prov…

2단계8 분열기