Skriv kontroll- och provplanen för betongen, frige varje gjutning innan den startar, gjut och spåra kuberna mot den gjutning de kom från, agera korrekt på ett underkänt resultat, och förvara intygen där slutbesiktningen kommer att behöva dem.

5 steg20 minGeneralentreprenörProjekt- / byggledningsföretagSpecialunderentreprenörByggherre / beställare

Så fungerar det, steg för steg

5 steg genom plattformen - vad du gör i varje och varför det spelar roll.

1

Write the test plan before the first pour, not after

Kvalitetsstyrning

Set out, per grade and per element type, what is checked and when: mix approval, workability at the point of placing, the sampling frequency the code sets by volume placed, the ages at which cubes are tested, curing, and formwork striking. Mark the pre-pour check as a hold point rather than as a notification.

Skärmbild, steg 1: Write the test plan before the first pour, not after (Kvalitetsstyrning, Håll betongen till IS 456, från gjutkort till kubresultat)
Kvalitetsstyrning: Write the test plan before the first pour, not after

Varför: A hold point is the only instrument that survives a busy site. A check written as a notification is done when there is time, which on a pour day there is not, and the pour goes ahead because stopping it costs a truck of concrete.

IndataSpecification and gradesThe code requirements that applyResultatAn inspection and test plan for concreteHold points nobody may pass
2

Clear the pour on the things that disappear

Besiktningar

Inspect against the plan before concrete is called: bar size, spacing and laps against the schedule, cover blocks in place and of the right thickness, the detailing at joints and confinement zones, formwork line and support, and the element clean. Photograph the reinforcement, and record who cleared it.

Skärmbild, steg 2: Clear the pour on the things that disappear (Besiktningar, Håll betongen till IS 456, från gjutkort till kubresultat)
Besiktningar: Clear the pour on the things that disappear

Varför: Everything in that list is invisible an hour later and expensive to verify afterwards. Cover in particular decides how long the structure lasts and cannot be inspected once poured, so the record made at this moment is the only evidence that will ever exist.

IndataThe element about to be pouredReinforcement drawings and schedulesResultatA cleared pour, with evidenceWhat the reinforcement looked like
3

Cast the cubes and tie them to the element, not to the day

Formulär och checklistor

Fill the pour card as the concrete is placed: grade, volume, time, workability reading, weather, and the identification of every cube cast from it, against the element being poured. Record the test ages that fall due from those dates.

Varför: Cubes identified only by date are useless on a site pouring three elements a day. When a result comes back low, the question is which element it belongs to, and a card that answers that turns a structural investigation into a check of one beam.

IndataThe pour, its grade and its volumeResultatCubes tied to the element they came fromTest dates falling due
4

Treat a low result as a bounded non-conformance

Avvikelser

Read the results against the acceptance criteria the code sets, and where they fall short, raise a non-conformance naming the element, the pour and the volume affected. Record the further testing or structural assessment agreed, and who signs off the outcome.

Varför: A low seven day result is information, not a verdict, and a low twenty-eight day result has a defined route through it. What decides the cost is whether the extent is known. A non-conformance that names one element is a repair; one that cannot say which pour it belongs to becomes a survey of a floor.

IndataCube results at each ageResultatA non-conformance with a known extentThe route to acceptance or rejection
5

File the certificates against the structure they prove

Dokument

Keep the pour cards, the laboratory certificates, the pre-pour clearances and any non-conformance and its closure together, organised by element rather than by month.

Skärmbild, steg 5: File the certificates against the structure they prove (Dokument, Håll betongen till IS 456, från gjutkort till kubresultat)
Dokument: File the certificates against the structure they prove

Varför: At handover, and at any later query about the structure, the question is always about a part of the building rather than about a period of time. A file arranged by element answers it in minutes; one arranged by month is searched by somebody who was not there.

IndataTest certificates and pour cardsResultatA concrete file arranged by element
Moduler

Moduler i denna playbook

5 / 190 plattformsmoduler

The market this case is written for

Indien

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CPWD DSR
  • IS 456
  • RERA

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Mer inom Kvalitet och säkerhet

Kvalitet och säkerhet

Toolbox talk and safety check

Brief the crew on the hazards this shift actually carries, capture who was there, then prov…

2 steg8 minÖppna
Kvalitet och säkerhet

Get a material submittal approved

Put the product you plan to buy in front of the designer with its data behind it, get it ch…

3 steg9 minÖppna