케이스 / 품질 및 안전
품질 및 안전

building consent를 code compliance까지 진행하기

work에 consent가 필요한지, 그 일부가 restricted building work에 해당하는지 확인하고, 신청서를 제출하고, 결정 기간을 잃지 않으면서 request for further information에 답변하고, consent가 지정하는 검사를 통과하고, records of work를 모으고, code compliance certificate를 신청한다.

7단계18 분종합건설사시행사 / 발주처설계 / 엔지니어링 업체PM/CM 업체

작동 방식, 단계별로

플랫폼 전반에 걸친 7단계 - 각 단계에서 무엇을 하는지, 그리고 왜 중요한지.

1

Settle the route before anybody draws anything

경로 분류기

Classify the work: does it need a building consent, does any part of it fall inside the exempt work Schedule 1 describes, and is any of it restricted building work, which is the design and construction of the primary structure and the external moisture management systems of a house or small to medium apartment building. Record the answer and what it rests on.

이유: Exempt work still has to comply with the Building Code, so exemption removes the paperwork and not the standard, and work exempted wrongly is unconsented building work that the territorial authority can require to be fixed years later. Restricted building work found at the end means finding a licensed practitioner willing to certify somebody else's finished work, which is the most expensive discovery in this whole case.

입력Scope of the building workExempt work in Schedule 1결과Consent needed or notRestricted building work identified
2

Lodge a complete application, not an early one

권한 제출

Lodge the application with the building consent authority as one pack: the drawings and specification at the level of detail the Code compliance path needs, the structural and other calculations, the product information, and the memorandum from the licensed design practitioner where the work is restricted building work. Record the lodgement date, because the decision period runs from it.

이유: The authority has 20 working days to grant or refuse, and an incomplete application does not shorten that period, it just spends it on a request for further information. Lodging two weeks early with half the structural documentation reliably costs more calendar time than lodging two weeks later with all of it.

입력Drawings, specification and calculationsDesigner's memorandum where required결과Application lodged and datedDecision period running
3

Answer the request before the file goes cold

서신

Log every request for further information against the application with the date it arrived, route each question to the person who can answer it, and send one consolidated response rather than a trickle. Keep the sent copy and the date, and record which drawings were superseded by the answer.

이유: The decision period is suspended while a request is outstanding, so every day the answer sits with the design team is a day added to the consent and not a day of the authority's twenty. That is also why a request answered piecemeal is the slowest of all: the clock restarts and stops again with each round.

입력Request for further informationDesign team's answer결과Response sent and loggedDecision period resumed
4

Book the inspections the consent names, in order

검사

Put the inspections the consent lists onto the programme as the activities they actually are, book each one before the work it covers is closed up, and record the result with the date and the inspector's findings. Where an inspection fails, record what has to be fixed and re-book it rather than carrying on.

이유: The building consent authority can only issue a code compliance certificate if it is satisfied on reasonable grounds that the work complies, and the inspection record is most of those grounds. Work closed up before its inspection is work that may have to be opened again, and the cost of that is carried by whoever built it, not by whoever forgot to book.

입력Granted consent and its conditionsConstruction programme결과Inspections passed and datedItems to fix before the next one
5

Collect the records while the trades are still on site

품질 관리

Collect the record of work from every licensed building practitioner who carried out or supervised restricted building work, together with the producer statements, test results and product certificates the consent conditions call for. Track them as a list with the gaps named, not as a folder somebody will audit later.

이유: A licensed practitioner owes a record of work on completion of their restricted building work, and chasing one from a subcontractor who left the job eight months ago is a different task from asking for it in the week they finished. Every missing document becomes a hold on the code compliance certificate, and the certificate is usually holding up settlement.

입력Restricted building work carried outProducer statements and test results결과Records of work collectedMissing certificates named
6

Apply for the code compliance certificate

마감

Apply once the file is complete and the work is finished, with the inspection record, the records of work, the producer statements and the as-built information. The authority has 20 working days to decide, and it decides against the consent as granted, so any change made on site has to have been consented as an amendment before this point.

이유: The certificate is what says the work complies with the consent, and its absence follows the building rather than the builder. A house without one is harder to sell, harder to insure and harder to finance, and the owner who inherits that problem is usually the one paying to solve it years after everyone who could have solved it cheaply has moved on.

입력Records of work collectedInspections passed and dated결과Certificate applied forCode compliance certificate issued
7

Hand the owner the file the property will need

문서

File the whole consent history where the owner and the next owner can find it: the consented drawings, the amendments, the inspection record, the certificates and the code compliance certificate itself. Where the building has specified systems, record the compliance schedule and the annual building warrant of fitness that now runs against it.

이유: The consent file is read by people who were not there: a purchaser's solicitor, an insurer, the designer of the next alteration. A complete file answers their questions without anybody being called; an incomplete one turns every future project on the building into an archaeology exercise, and the council's own property file is rarely as complete as the builder's was.

입력Code compliance certificate issuedSpecified systems in the building결과Consent pack filed for the ownerCompliance schedule obligations noted
모듈

이 플레이북의 모듈

플랫폼 190개 모듈 중 7

The market this case is written for

뉴질랜드

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • NZS 3910
  • Construction Contracts Act

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

품질 및 안전 카테고리의 더 보기

품질 및 안전

공사 검사 및 부적합(NCR) 종결하기

인수 기준에 따라 공사를 검사하고, 불합격 즉시 부적합(NCR)을 제기한 뒤, 시정 조치를 진행하고 재검사하여 하자가 실제로 해결되었음을 기록으로 남깁니다.

3단계10 분열기
품질 및 안전

툴박스 토크 및 안전 점검

이번 근무조가 실제로 마주할 위험 요소를 브리핑하고, 참석자를 기록한 뒤, 순회 점검을 통해 합의한 통제 수단이 실제로 갖춰져 있는지 증명합니다.

2단계8 분열기
품질 및 안전

자재 제출물 승인 받기

구매하려는 제품 자료를 근거와 함께 설계자에게 제출하고, 사양서와 대조해 검토받은 후 승인된 경우에만 발주로 진행한다.

3단계9 분열기