Llevar una building consent hasta la code compliance

Resuelva si el trabajo necesita una consent y si alguna parte es restricted building work, presente la solicitud, responda la request for further information sin perder el plazo de decisión, pase las inspecciones que nombra la consent, reúna los records of work, y solicite el code compliance certificate.

7 pasos18 minContratista generalPromotor / clienteEstudio de proyectos / ingenieríaGestora de proyectos / construcción

Cómo funciona, paso a paso

7 pasos a lo largo de la plataforma - qué hacer en cada uno y por qué importa.

1

Settle the route before anybody draws anything

Clasificador de Ruta

Classify the work: does it need a building consent, does any part of it fall inside the exempt work Schedule 1 describes, and is any of it restricted building work, which is the design and construction of the primary structure and the external moisture management systems of a house or small to medium apartment building. Record the answer and what it rests on.

Por que: Exempt work still has to comply with the Building Code, so exemption removes the paperwork and not the standard, and work exempted wrongly is unconsented building work that the territorial authority can require to be fixed years later. Restricted building work found at the end means finding a licensed practitioner willing to certify somebody else's finished work, which is the most expensive discovery in this whole case.

EntradaScope of the building workExempt work in Schedule 1ResultadoConsent needed or notRestricted building work identified
2

Lodge a complete application, not an early one

Presentaciones a Autoridad

Lodge the application with the building consent authority as one pack: the drawings and specification at the level of detail the Code compliance path needs, the structural and other calculations, the product information, and the memorandum from the licensed design practitioner where the work is restricted building work. Record the lodgement date, because the decision period runs from it.

Por que: The authority has 20 working days to grant or refuse, and an incomplete application does not shorten that period, it just spends it on a request for further information. Lodging two weeks early with half the structural documentation reliably costs more calendar time than lodging two weeks later with all of it.

EntradaDrawings, specification and calculationsDesigner's memorandum where requiredResultadoApplication lodged and datedDecision period running
3

Answer the request before the file goes cold

Correspondencia

Log every request for further information against the application with the date it arrived, route each question to the person who can answer it, and send one consolidated response rather than a trickle. Keep the sent copy and the date, and record which drawings were superseded by the answer.

Por que: The decision period is suspended while a request is outstanding, so every day the answer sits with the design team is a day added to the consent and not a day of the authority's twenty. That is also why a request answered piecemeal is the slowest of all: the clock restarts and stops again with each round.

EntradaRequest for further informationDesign team's answerResultadoResponse sent and loggedDecision period resumed
4

Book the inspections the consent names, in order

Inspecciones

Put the inspections the consent lists onto the programme as the activities they actually are, book each one before the work it covers is closed up, and record the result with the date and the inspector's findings. Where an inspection fails, record what has to be fixed and re-book it rather than carrying on.

Por que: The building consent authority can only issue a code compliance certificate if it is satisfied on reasonable grounds that the work complies, and the inspection record is most of those grounds. Work closed up before its inspection is work that may have to be opened again, and the cost of that is carried by whoever built it, not by whoever forgot to book.

EntradaGranted consent and its conditionsConstruction programmeResultadoInspections passed and datedItems to fix before the next one
5

Collect the records while the trades are still on site

Gestión de calidad

Collect the record of work from every licensed building practitioner who carried out or supervised restricted building work, together with the producer statements, test results and product certificates the consent conditions call for. Track them as a list with the gaps named, not as a folder somebody will audit later.

Por que: A licensed practitioner owes a record of work on completion of their restricted building work, and chasing one from a subcontractor who left the job eight months ago is a different task from asking for it in the week they finished. Every missing document becomes a hold on the code compliance certificate, and the certificate is usually holding up settlement.

EntradaRestricted building work carried outProducer statements and test resultsResultadoRecords of work collectedMissing certificates named
6

Apply for the code compliance certificate

Cierre

Apply once the file is complete and the work is finished, with the inspection record, the records of work, the producer statements and the as-built information. The authority has 20 working days to decide, and it decides against the consent as granted, so any change made on site has to have been consented as an amendment before this point.

Por que: The certificate is what says the work complies with the consent, and its absence follows the building rather than the builder. A house without one is harder to sell, harder to insure and harder to finance, and the owner who inherits that problem is usually the one paying to solve it years after everyone who could have solved it cheaply has moved on.

EntradaRecords of work collectedInspections passed and datedResultadoCertificate applied forCode compliance certificate issued
7

Hand the owner the file the property will need

Documentos

File the whole consent history where the owner and the next owner can find it: the consented drawings, the amendments, the inspection record, the certificates and the code compliance certificate itself. Where the building has specified systems, record the compliance schedule and the annual building warrant of fitness that now runs against it.

Por que: The consent file is read by people who were not there: a purchaser's solicitor, an insurer, the designer of the next alteration. A complete file answers their questions without anybody being called; an incomplete one turns every future project on the building into an archaeology exercise, and the council's own property file is rarely as complete as the builder's was.

EntradaCode compliance certificate issuedSpecified systems in the buildingResultadoConsent pack filed for the ownerCompliance schedule obligations noted
Módulos

Módulos de este playbook

7 / 190 módulos de la plataforma

El mercado para el que está escrito este caso

Nueva Zelanda

Todo en este caso sigue la forma en que la obra se mide, se valora y se paga en este mercado. Los documentos, el desglose de costes y las reglas de pago son los que se usan allí, no una versión genérica.

Normas que sigue

  • NZS 3910
  • Construction Contracts Act

No tienes que configurar nada de eso a mano. La primera vez que abres la plataforma te pregunta en qué mercado trabajas. Elige este y ajusta el idioma de la interfaz, carga la base de costes correspondiente, registra la clasificación de costes y añade un proyecto de ejemplo que puedes abrir enseguida.

Las comprobaciones de este mercado también vienen con la plataforma. Actívalas una vez y un presupuesto al que le falte algo que el mercado espera queda señalado mientras trabajas en él, no después de presentar la oferta.

Más en Calidad y seguridad