Issue a tax invoice and attribute GST on a progress payment

Set GST at ten per cent and mark what falls outside it, issue a tax invoice carrying the particulars the law requires, attribute each progress component to the right period under Division 156, deal with retention when it is withheld and when it is released, check every subcontractor's ABN before you pay, and reconcile the period for the activity statement.

6 алхам14 минЕрөнхий гүйцэтгэгчМэргэшсэн дэд гүйцэтгэгчӨртгийн зөвлөгөө / QS

Хэрхэн ажилладаг, алхам алхмаар

Платформ даяар 6 алхам - алхам бүрт юу хийх, яагаад чухал болохыг.

1

Set the rate and mark what sits outside it

Татварын хувь хэмжээ

Set GST at ten per cent on the project and mark the amounts that are not consideration for a taxable supply, so they never pick the rate up by default. Liquidated damages deducted, a payment of damages and a security deposit that has not been forfeited are the ones that come up on a building job.

Дэлгэцийн зураг, 1-р алхам: Set the rate and mark what sits outside it (Татварын хувь хэмжээ, Issue a tax invoice and attribute GST on a progress payment)
Татварын хувь хэмжээ: Set the rate and mark what sits outside it

Яагаад: The rate is the easy half. The expensive half is a deduction that was never a supply being run through the same tax treatment as the work, because the error is invisible on the face of the invoice and repeats every month until somebody reconciles a year of it at once.

ОролтGST registration and ABNWhat the contract suppliesҮр дүнGST rate set on the projectAmounts outside the tax
2

Issue a document that is actually a tax invoice

Санхүү

Raise the invoice with everything the law asks a tax invoice to show: that it is intended as a tax invoice, your identity and your ABN, the date, what was supplied, the GST amount or a statement that the total includes GST, and the recipient's identity or ABN once the sale reaches the threshold at which that is required. Where the principal issues a recipient created tax invoice instead, record the written agreement that allows it.

Дэлгэцийн зураг, 2-р алхам: Issue a document that is actually a tax invoice (Санхүү, Issue a tax invoice and attribute GST on a progress payment)
Санхүү: Issue a document that is actually a tax invoice

Яагаад: A recipient cannot claim the input tax credit without a valid tax invoice, so a document short of one particular is not a small formatting problem, it is a payment your client's accounts team will hold until it is reissued. On a monthly claim cycle that is a month of cash for a missing line of text.

ОролтCertified progress claimSupplier and recipient detailsҮр дүнTax invoice issuedRequired particulars present
3

Attribute each component to the period it belongs in

Төлбөр

Record the date the invoice was issued and the date payment came in against each progress component, and let the period follow the basis you account on. Division 156 treats each progressive or periodic component of a supply as a separate supply for this purpose, so the building being unfinished does not defer anything.

Дэлгэцийн зураг, 3-р алхам: Attribute each component to the period it belongs in (Төлбөр, Issue a tax invoice and attribute GST on a progress payment)
Төлбөр: Attribute each component to the period it belongs in

Яагаад: A builder who waits for practical completion to account for the GST on two years of progress claims has been reporting a series of periods wrong, and the correction arrives with interest attached. The dates that settle it are the invoice date and the payment date, both of which are on the record already if anybody thought to keep them.

ОролтTax invoice issuedCash or accruals basisҮр дүнComponent in the right periodInvoice and payment dates recorded
4

Handle retention once, not twice

Суутгал

Track retention as an amount withheld from a claim that has already been made rather than as a separate later sale, with the balance held, the reduction at practical completion and the release at the end of the defects liability period each carrying its own date.

Дэлгэцийн зураг, 4-р алхам: Handle retention once, not twice (Суутгал, Issue a tax invoice and attribute GST on a progress payment)
Суутгал: Handle retention once, not twice

Яагаад: Retention is the place the two common errors meet. Treated as a new supply on release, the GST is reported twice; forgotten entirely, the last five per cent of a job is never chased at all. Held as a running balance with dates on it, both problems disappear and the release becomes something somebody is watching for.

ОролтRetention withheld this periodRetention due for releaseҮр дүнRetention treated onceBalance held by release date
5

Check the ABN before you pay the subcontractor

Татвар суутгал

Check that each supplier has quoted an ABN and whether it is registered for GST, and set the withholding on the ones that have not. An invoice from a supplier who is not registered for GST should not be carrying a GST line at all, and paying one that does is money you cannot claim back.

Яагаад: Where no ABN is quoted for a taxable supply the payer is required to withhold at the top rate and remit it, and the liability for not doing so sits with the payer rather than with the supplier who left it off. Checking at the first invoice costs a minute and settles the whole job.

ОролтSubcontractor invoicesABN quoted or missingҮр дүнABN and GST status checkedWithholding applied where required
6

Reconcile the period before the activity statement

Тайлан

Report the period: what was invoiced, what was received, the GST collected and the credits claimed, with the differences named rather than left as a rounding. Keep the report so the same question about the same month can be answered a year later without rebuilding it.

Дэлгэцийн зураг, 6-р алхам: Reconcile the period before the activity statement (Тайлан, Issue a tax invoice and attribute GST on a progress payment)
Тайлан: Reconcile the period before the activity statement

Яагаад: The activity statement is a return, so an error in it is a correction rather than an adjustment, and corrections come with interest. A reconciliation that names its differences each month is also the only version of this work that takes an hour instead of a fortnight when a review asks for it.

ОролтComponents in the periodInput tax credits claimedҮр дүнPeriod totals reconciledDifferences explained
Модулиуд

Энэ тоглолтын модулиуд

Платформын 190 модулиас 4

The market this case is written for

Австрали

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • AS 4000
  • Security of Payment Act

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.