حالات عملية / التجاري والعقود
التجاري والعقود

إصدار tax invoice ونسبة GST على progress payment

حدد GST بعشرة بالمئة وحدد ما يقع خارجها، أصدر tax invoice يحمل التفاصيل التي يشترطها القانون، انسب كل مكون تقدم بموجب Division 156 إلى فترته الصحيحة، تعامل مع الـ retention المقتطع والمُفرج عنه، تحقق من ABN كل مقاول فرعي قبل الدفع، وطابق الفترات مع بيان النشاط.

6 خطوة14 دقيقةمقاول عاممقاول باطن متخصصاستشارات التكاليف / قياس الكميات

كيف يعمل، خطوة بخطوة

6 خطوات عبر المنصة - ما تفعله في كل منها ولماذا يهم.

1

Set the rate and mark what sits outside it

معدلات الضريبة

Set GST at ten per cent on the project and mark the amounts that are not consideration for a taxable supply, so they never pick the rate up by default. Liquidated damages deducted, a payment of damages and a security deposit that has not been forfeited are the ones that come up on a building job.

لقطة شاشة، الخطوة 1: Set the rate and mark what sits outside it (معدلات الضريبة, إصدار tax invoice ونسبة GST على progress payment)
معدلات الضريبة: Set the rate and mark what sits outside it

لماذا: The rate is the easy half. The expensive half is a deduction that was never a supply being run through the same tax treatment as the work, because the error is invisible on the face of the invoice and repeats every month until somebody reconciles a year of it at once.

المدخلاتGST registration and ABNWhat the contract suppliesالمخرجاتGST rate set on the projectAmounts outside the tax
2

Issue a document that is actually a tax invoice

المالية

Raise the invoice with everything the law asks a tax invoice to show: that it is intended as a tax invoice, your identity and your ABN, the date, what was supplied, the GST amount or a statement that the total includes GST, and the recipient's identity or ABN once the sale reaches the threshold at which that is required. Where the principal issues a recipient created tax invoice instead, record the written agreement that allows it.

لقطة شاشة، الخطوة 2: Issue a document that is actually a tax invoice (المالية, إصدار tax invoice ونسبة GST على progress payment)
المالية: Issue a document that is actually a tax invoice

لماذا: A recipient cannot claim the input tax credit without a valid tax invoice, so a document short of one particular is not a small formatting problem, it is a payment your client's accounts team will hold until it is reissued. On a monthly claim cycle that is a month of cash for a missing line of text.

المدخلاتCertified progress claimSupplier and recipient detailsالمخرجاتTax invoice issuedRequired particulars present
3

Attribute each component to the period it belongs in

المدفوعات

Record the date the invoice was issued and the date payment came in against each progress component, and let the period follow the basis you account on. Division 156 treats each progressive or periodic component of a supply as a separate supply for this purpose, so the building being unfinished does not defer anything.

لقطة شاشة، الخطوة 3: Attribute each component to the period it belongs in (المدفوعات, إصدار tax invoice ونسبة GST على progress payment)
المدفوعات: Attribute each component to the period it belongs in

لماذا: A builder who waits for practical completion to account for the GST on two years of progress claims has been reporting a series of periods wrong, and the correction arrives with interest attached. The dates that settle it are the invoice date and the payment date, both of which are on the record already if anybody thought to keep them.

المدخلاتTax invoice issuedCash or accruals basisالمخرجاتComponent in the right periodInvoice and payment dates recorded
4

Handle retention once, not twice

المحتجزات

Track retention as an amount withheld from a claim that has already been made rather than as a separate later sale, with the balance held, the reduction at practical completion and the release at the end of the defects liability period each carrying its own date.

لقطة شاشة، الخطوة 4: Handle retention once, not twice (المحتجزات, إصدار tax invoice ونسبة GST على progress payment)
المحتجزات: Handle retention once, not twice

لماذا: Retention is the place the two common errors meet. Treated as a new supply on release, the GST is reported twice; forgotten entirely, the last five per cent of a job is never chased at all. Held as a running balance with dates on it, both problems disappear and the release becomes something somebody is watching for.

المدخلاتRetention withheld this periodRetention due for releaseالمخرجاتRetention treated onceBalance held by release date
5

Check the ABN before you pay the subcontractor

ضريبة الاستقطاع

Check that each supplier has quoted an ABN and whether it is registered for GST, and set the withholding on the ones that have not. An invoice from a supplier who is not registered for GST should not be carrying a GST line at all, and paying one that does is money you cannot claim back.

لماذا: Where no ABN is quoted for a taxable supply the payer is required to withhold at the top rate and remit it, and the liability for not doing so sits with the payer rather than with the supplier who left it off. Checking at the first invoice costs a minute and settles the whole job.

المدخلاتSubcontractor invoicesABN quoted or missingالمخرجاتABN and GST status checkedWithholding applied where required
6

Reconcile the period before the activity statement

التقارير

Report the period: what was invoiced, what was received, the GST collected and the credits claimed, with the differences named rather than left as a rounding. Keep the report so the same question about the same month can be answered a year later without rebuilding it.

لقطة شاشة، الخطوة 6: Reconcile the period before the activity statement (التقارير, إصدار tax invoice ونسبة GST على progress payment)
التقارير: Reconcile the period before the activity statement

لماذا: The activity statement is a return, so an error in it is a correction rather than an adjustment, and corrections come with interest. A reconciliation that names its differences each month is also the only version of this work that takes an hour instead of a fortnight when a review asks for it.

المدخلاتComponents in the periodInput tax credits claimedالمخرجاتPeriod totals reconciledDifferences explained
الوحدات

وحدات هذا الدليل

4 / 190 من وحدات المنصة

The market this case is written for

أستراليا

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • AS 4000
  • Security of Payment Act

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

المزيد في التجاري والعقود

التجاري والعقود

تحويل تغيير إلى أمر تغيير مدفوع

التقط تغيير النطاق وهو طازج، وسعّره كأمر تغيير تعاقدي على أسعارك المتفق عليها، وحاسب عليه في…

3 خطوة11 دقيقةفتح
التجاري والعقود

إدارة حزمة مقاول باطن

أرسِ حزمة تخصص على مقاول باطن، وضعها في عقد باطن بجدول قيم ومحتجزات، ثم اسددها مستخلصاً بعد…

3 خطوة11 دقيقةفتح
التجاري والعقود

مطالبة الدفع ومطابقتها

قيّم العمل المنفَّذ خلال هذه الفترة مقابل العقد، وقدّم المطالبة مدعومة بأدلّتها، وطابِق ما ا…

3 خطوة12 دقيقةفتح