سناریوها / بازرگانی و قراردادها
بازرگانی و قراردادها

صدور tax invoice و انتساب GST روی یک progress payment

GST را روی ده درصد تعیین کنید و آنچه بیرون از آن است شناسایی کنید، tax invoice‌ای صادر کنید که جزئیاتی را که قانون می‌خواهد حمل کند، هر مؤلفه progress را طبق Division 156 به دوره درست منتسب کنید، هم retention کسرشده و هم آزادشده را مدیریت کنید، ABN هر پیمانکار فرعی را پیش از پرداخت تأیید کنید، و دوره‌ها را با activity statement تطبیق دهید.

6 مرحله14 دقیقهپیمانکار عمومیپیمانکار جزء تخصصیمشاوره هزینه / QS

چگونه کار می‌کند، گام به گام

6 گام در سراسر پلتفرم - کاری که در هر گام انجام می‌دهید و چرا اهمیت دارد.

1

Set the rate and mark what sits outside it

نرخ‌های مالیاتی

Set GST at ten per cent on the project and mark the amounts that are not consideration for a taxable supply, so they never pick the rate up by default. Liquidated damages deducted, a payment of damages and a security deposit that has not been forfeited are the ones that come up on a building job.

چرا: The rate is the easy half. The expensive half is a deduction that was never a supply being run through the same tax treatment as the work, because the error is invisible on the face of the invoice and repeats every month until somebody reconciles a year of it at once.

ورودیGST registration and ABNWhat the contract suppliesخروجیGST rate set on the projectAmounts outside the tax
2

Issue a document that is actually a tax invoice

مالی

Raise the invoice with everything the law asks a tax invoice to show: that it is intended as a tax invoice, your identity and your ABN, the date, what was supplied, the GST amount or a statement that the total includes GST, and the recipient's identity or ABN once the sale reaches the threshold at which that is required. Where the principal issues a recipient created tax invoice instead, record the written agreement that allows it.

چرا: A recipient cannot claim the input tax credit without a valid tax invoice, so a document short of one particular is not a small formatting problem, it is a payment your client's accounts team will hold until it is reissued. On a monthly claim cycle that is a month of cash for a missing line of text.

ورودیCertified progress claimSupplier and recipient detailsخروجیTax invoice issuedRequired particulars present
3

Attribute each component to the period it belongs in

پرداخت‌ها

Record the date the invoice was issued and the date payment came in against each progress component, and let the period follow the basis you account on. Division 156 treats each progressive or periodic component of a supply as a separate supply for this purpose, so the building being unfinished does not defer anything.

چرا: A builder who waits for practical completion to account for the GST on two years of progress claims has been reporting a series of periods wrong, and the correction arrives with interest attached. The dates that settle it are the invoice date and the payment date, both of which are on the record already if anybody thought to keep them.

ورودیTax invoice issuedCash or accruals basisخروجیComponent in the right periodInvoice and payment dates recorded
4

Handle retention once, not twice

وجه‌التزام

Track retention as an amount withheld from a claim that has already been made rather than as a separate later sale, with the balance held, the reduction at practical completion and the release at the end of the defects liability period each carrying its own date.

چرا: Retention is the place the two common errors meet. Treated as a new supply on release, the GST is reported twice; forgotten entirely, the last five per cent of a job is never chased at all. Held as a running balance with dates on it, both problems disappear and the release becomes something somebody is watching for.

ورودیRetention withheld this periodRetention due for releaseخروجیRetention treated onceBalance held by release date
5

Check the ABN before you pay the subcontractor

مالیات تکلیفی

Check that each supplier has quoted an ABN and whether it is registered for GST, and set the withholding on the ones that have not. An invoice from a supplier who is not registered for GST should not be carrying a GST line at all, and paying one that does is money you cannot claim back.

چرا: Where no ABN is quoted for a taxable supply the payer is required to withhold at the top rate and remit it, and the liability for not doing so sits with the payer rather than with the supplier who left it off. Checking at the first invoice costs a minute and settles the whole job.

ورودیSubcontractor invoicesABN quoted or missingخروجیABN and GST status checkedWithholding applied where required
6

Reconcile the period before the activity statement

گزارش‌ها

Report the period: what was invoiced, what was received, the GST collected and the credits claimed, with the differences named rather than left as a rounding. Keep the report so the same question about the same month can be answered a year later without rebuilding it.

چرا: The activity statement is a return, so an error in it is a correction rather than an adjustment, and corrections come with interest. A reconciliation that names its differences each month is also the only version of this work that takes an hour instead of a fortnight when a review asks for it.

ورودیComponents in the periodInput tax credits claimedخروجیPeriod totals reconciledDifferences explained
ماژول‌ها

ماژول‌های این سناریو

4 / 190 ماژول پلتفرم

The market this case is written for

استرالیا

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • AS 4000
  • Security of Payment Act

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

بیشتر در بازرگانی و قراردادها

بازرگانی و قراردادها

اجرای یک بسته پیمانکار جزء

یک بسته کاری را به یک پیمانکار جزء واگذار کنید، آن را در یک پیمان فرعی همراه با جدول ارزش‌ها…

3 مرحله11 دقیقهباز کردن
بازرگانی و قراردادها

درخواست پرداخت و تطبیق

کار انجام‌شده این دوره را در برابر قرارداد ارزش‌گذاری کنید، درخواست پرداخت را همراه با مدارک…

3 مرحله12 دقیقهباز کردن