Caser / Kommersielt og kontrakter
Kommersielt og kontrakter

Betale Davis-Bacon-lønn og levere certified payroll

Ta wage determination inn i jobben før den prissettes, koble hver klassifisering til arbeid noen faktisk skal gjøre, registrer timer per klassifisering på byggeplassen, betal grunnsatsen og fringe determination fastsetter, og lever certified payroll ukentlig med signert statement of compliance.

7 trinn15 minHovedentreprenørSpesialisert underentreprenørKostnadsrådgivning / kalkulasjon

Slik fungerer det, steg for steg

7 trinn gjennom plattformen - hva du gjør i hvert og hvorfor det betyr noe.

1

Pull the wage determination in before you price anything

Timesatser

Load the wage determination that came with the solicitation as a rate table: every classification, its basic hourly rate and its fringe rate, with the determination number and its date recorded beside them. Mark the classifications your crews will work that the determination does not list, because those need a conformance request to the contracting officer rather than a rate you picked yourself.

Skjermbilde, trinn 1: Pull the wage determination in before you price anything (Timesatser, Betale Davis-Bacon-lønn og levere certified payroll)
Timesatser: Pull the wage determination in before you price anything

Hvorfor: The determination is the floor, it is county specific and trade specific, and it is not negotiable at any point after award. Reading it after the bid is submitted is how a job is won at a labour rate that does not exist, and a classification handled by inventing a rate is the one the audit finds, because a rate nobody conformed has no paper behind it.

InndataSolicitation documentsWage determinationResultatRate table loadedClassifications not listed
2

Price the work at the determination, not at your shop rate

Mengdefortegnelse

Build the crew rate behind each item from the determination's basic rate plus its fringe, then add the burdens the fringe does not cover, and price overtime at time and a half beyond forty hours in the week. Keep the difference between this and your ordinary shop rate visible as its own figure.

Skjermbilde, trinn 2: Price the work at the determination, not at your shop rate (Mengdefortegnelse, Betale Davis-Bacon-lønn og levere certified payroll)
Mengdefortegnelse: Price the work at the determination, not at your shop rate

Hvorfor: The fringe is part of the obligation and not an allowance, so a bill priced on base rates alone is short by the fringe on every hour. Keeping the difference from your ordinary rates visible is what lets the company decide whether it wants this kind of work at all, rather than finding out at the post mortem that federally funded jobs quietly lose money.

InndataRate table loadedScope and quantitiesResultatPriced billCost above shop rates
3

Capture hours by classification, not by name alone

Felttid

Book every hour worked on site against the classification the work belongs to and the day it happened. Where somebody worked two classifications in one day, record both with the hours split between them rather than putting the whole day under the higher one or the lower one.

Hvorfor: The certified payroll is a statement about hours by classification, so a timesheet that records only hours by person cannot produce it and has to be reconstructed from memory every Friday. Split days are where reconstruction goes wrong, and an underpayment found months later is repaid with interest plus whatever the agency withholds while it looks at the rest of the file.

InndataCrew on siteClassification listResultatHours by classificationSplit-classification days
4

Pay weekly, with the fringe in cash or into a real plan

Lønn

Run the payroll once a week, pay each worker the basic rate for the classification they worked, and settle the fringe either as cash on the paycheck or as a contribution to a bona fide plan, recorded either way. Pay apprentices at their program rate only where they are registered in an approved program and only within the ratio it allows, and list every deduction taken.

Hvorfor: Weekly payment is part of the obligation, not a company habit, and an unregistered apprentice is simply a journeyman being underpaid. Deductions are the other common finding: anything beyond the ones permitted turns a correct gross wage into an incorrect net one, and it is the net figure the investigator reads first.

InndataHours by classificationFringe benefit plansResultatWeekly payroll runDeductions recorded
5

File the weekly certified payroll and sign the statement

Dokumenter

Produce the payroll for each week the crew worked on the site, showing every worker with their classification, hours by day, rate, gross, deductions and net, and file it with the contracting agency within the days the contract allows after the pay date. Attach the signed statement of compliance and keep the filed copy with the week it covers. The published form is optional; the information on it is not.

Skjermbilde, trinn 5: File the weekly certified payroll and sign the statement (Dokumenter, Betale Davis-Bacon-lønn og levere certified payroll)
Dokumenter: File the weekly certified payroll and sign the statement

Hvorfor: This is the document that turns paying correctly into having proved it, and it is signed personally under penalty, which is why it should never be assembled by somebody who did not see the hours. A week filed late is a compliance finding on its own, before anybody has looked at whether the wages themselves were right, and the usual remedy is the agency holding the next payment.

InndataWeekly payroll runWage determinationResultatCertified payroll filedStatement of compliance
6

Hold every subcontractor to the same obligation

Underentreprenør-register

Write the wage clauses and the determination into every subcontract at every tier, then make the week's certified payroll a condition of that subcontractor being paid rather than something chased afterwards. Read what they send: a payroll with a classification that is not on the determination, or a rate below it, is a finding you can still fix.

Skjermbilde, trinn 6: Hold every subcontractor to the same obligation (Underentreprenør-register, Betale Davis-Bacon-lønn og levere certified payroll)
Underentreprenør-register: Hold every subcontractor to the same obligation

Hvorfor: The prime contractor answers for the compliance of the whole chain, so a second tier subcontractor underpaying its crew is the prime's restitution to pay and the prime's payments the agency withholds. Gating the money on the paperwork is the only mechanism that reliably produces the paperwork, and it costs nothing while the money is still yours.

InndataSubcontract listSubcontractor payrollsResultatPayment gated on the payrollCompliance record per sub
7

Put the weekly clock and the retention date under watch

Frister

Set the weekly filing date as a recurring deadline for as long as anyone works on the site, add the posting of the determination and the worker notice at the site entrance, and record the date the payroll records may finally be destroyed, counted from completion rather than from the last pay date.

Skjermbilde, trinn 7: Put the weekly clock and the retention date under watch (Frister, Betale Davis-Bacon-lønn og levere certified payroll)
Frister: Put the weekly clock and the retention date under watch

Hvorfor: An investigation usually arrives long after the crews have gone, and it asks for the weeks nobody remembers. Records destroyed before the retention period ends leave the contractor unable to prove a payment it actually made, which in practice is the same position as not having made it.

InndataWeekly filing scheduleRecord retention ruleResultatFiling dates under watchRecords kept to the end date
Moduler

Moduler i denne playbooken

7 / 190 plattformmoduler

The market this case is written for

USA

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CSI MasterFormat
  • UniFormat II
  • AIA A201

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Mer innen Kommersielt og kontrakter

Kommersielt og kontrakter

Kjør en underentreprenørpakke

Tildel en fagpakke til en underentreprenør, legg den på en underentreprise med betalingsplan…

3 trinn11 minÅpne
Kommersielt og kontrakter

Betalingskrav og avstemming

Verdisett arbeidet utført denne perioden mot kontrakten, send inn kravet med dokumentasjonen…

3 trinn12 minÅpne