Transformer une modification en avenant payé
Consignez une modification de périmètre pendant qu'elle est fraîche, chiffrez-la comme avena…
Intégrez la wage determination au chantier avant qu'il ne soit chiffré, faites correspondre chaque classification à un travail réellement effectué, saisissez les heures par classification sur site, payez le taux de base et le fringe que fixe la determination, et déposez chaque semaine le certified payroll avec sa statement of compliance signée.
7 étapes à travers la plateforme - ce que vous faites à chacune et pourquoi c’est important.
Load the wage determination that came with the solicitation as a rate table: every classification, its basic hourly rate and its fringe rate, with the determination number and its date recorded beside them. Mark the classifications your crews will work that the determination does not list, because those need a conformance request to the contracting officer rather than a rate you picked yourself.

Pourquoi: The determination is the floor, it is county specific and trade specific, and it is not negotiable at any point after award. Reading it after the bid is submitted is how a job is won at a labour rate that does not exist, and a classification handled by inventing a rate is the one the audit finds, because a rate nobody conformed has no paper behind it.
Build the crew rate behind each item from the determination's basic rate plus its fringe, then add the burdens the fringe does not cover, and price overtime at time and a half beyond forty hours in the week. Keep the difference between this and your ordinary shop rate visible as its own figure.

Pourquoi: The fringe is part of the obligation and not an allowance, so a bill priced on base rates alone is short by the fringe on every hour. Keeping the difference from your ordinary rates visible is what lets the company decide whether it wants this kind of work at all, rather than finding out at the post mortem that federally funded jobs quietly lose money.
Book every hour worked on site against the classification the work belongs to and the day it happened. Where somebody worked two classifications in one day, record both with the hours split between them rather than putting the whole day under the higher one or the lower one.
Pourquoi: The certified payroll is a statement about hours by classification, so a timesheet that records only hours by person cannot produce it and has to be reconstructed from memory every Friday. Split days are where reconstruction goes wrong, and an underpayment found months later is repaid with interest plus whatever the agency withholds while it looks at the rest of the file.
Run the payroll once a week, pay each worker the basic rate for the classification they worked, and settle the fringe either as cash on the paycheck or as a contribution to a bona fide plan, recorded either way. Pay apprentices at their program rate only where they are registered in an approved program and only within the ratio it allows, and list every deduction taken.
Pourquoi: Weekly payment is part of the obligation, not a company habit, and an unregistered apprentice is simply a journeyman being underpaid. Deductions are the other common finding: anything beyond the ones permitted turns a correct gross wage into an incorrect net one, and it is the net figure the investigator reads first.
Produce the payroll for each week the crew worked on the site, showing every worker with their classification, hours by day, rate, gross, deductions and net, and file it with the contracting agency within the days the contract allows after the pay date. Attach the signed statement of compliance and keep the filed copy with the week it covers. The published form is optional; the information on it is not.

Pourquoi: This is the document that turns paying correctly into having proved it, and it is signed personally under penalty, which is why it should never be assembled by somebody who did not see the hours. A week filed late is a compliance finding on its own, before anybody has looked at whether the wages themselves were right, and the usual remedy is the agency holding the next payment.
Write the wage clauses and the determination into every subcontract at every tier, then make the week's certified payroll a condition of that subcontractor being paid rather than something chased afterwards. Read what they send: a payroll with a classification that is not on the determination, or a rate below it, is a finding you can still fix.

Pourquoi: The prime contractor answers for the compliance of the whole chain, so a second tier subcontractor underpaying its crew is the prime's restitution to pay and the prime's payments the agency withholds. Gating the money on the paperwork is the only mechanism that reliably produces the paperwork, and it costs nothing while the money is still yours.
Set the weekly filing date as a recurring deadline for as long as anyone works on the site, add the posting of the determination and the worker notice at the site entrance, and record the date the payroll records may finally be destroyed, counted from completion rather than from the last pay date.

Pourquoi: An investigation usually arrives long after the crews have gone, and it asks for the weeks nobody remembers. Records destroyed before the retention period ends leave the contractor unable to prove a payment it actually made, which in practice is the same position as not having made it.
7 / 190 modules de la plateforme
Tout dans ce cas suit la façon dont les travaux sont métrés, chiffrés et payés sur ce marché. Les formulaires, la décomposition des coûts et les règles de paiement sont ceux qui y sont utilisés, pas une version générique.
Normes qu’il suit
Vous n’avez rien de tout cela à paramétrer à la main. Au premier démarrage, la plateforme demande sur quel marché vous travaillez. Choisissez celui-ci et elle règle la langue de l’interface, charge la base de coûts correspondante, enregistre la classification des coûts et ajoute un projet d’exemple que vous pouvez ouvrir tout de suite.
Les contrôles propres à ce marché sont eux aussi fournis avec la plateforme. Une fois activés, un devis auquel il manque quelque chose que le marché attend est signalé pendant que vous y travaillez, et non après l’envoi de l’offre.
Consignez une modification de périmètre pendant qu'elle est fraîche, chiffrez-la comme avena…
Attribuez un lot de travaux à un sous-traitant, mettez-le sous contrat avec un échéancier de…
Valorisez les travaux réalisés cette période par rapport au contrat, établissez la demande a…