Casos / Comercial e contratos
Comercial e contratos

Pague os salários Davis-Bacon e entregue o certified payroll

Traga a wage determination para a obra antes de a orçamentar, mapeie cada classificação para o trabalho que alguém vai realmente fazer, capture as horas por classificação em obra, pague a taxa base e o fringe que a determination fixa, e entregue semanalmente o certified payroll com a sua declaração de conformidade assinada.

7 etapas15 minEmpreiteiro geralSubempreiteiro especializadoConsultoria de custos / QS

Como funciona, passo a passo

7 passos ao longo da plataforma - o que fazer em cada um e por que importa.

1

Pull the wage determination in before you price anything

Custos de mão de obra

Load the wage determination that came with the solicitation as a rate table: every classification, its basic hourly rate and its fringe rate, with the determination number and its date recorded beside them. Mark the classifications your crews will work that the determination does not list, because those need a conformance request to the contracting officer rather than a rate you picked yourself.

Captura de tela, etapa 1: Pull the wage determination in before you price anything (Custos de mão de obra, Pague os salários Davis-Bacon e entregue o certified payroll)
Custos de mão de obra: Pull the wage determination in before you price anything

Por quê: The determination is the floor, it is county specific and trade specific, and it is not negotiable at any point after award. Reading it after the bid is submitted is how a job is won at a labour rate that does not exist, and a classification handled by inventing a rate is the one the audit finds, because a rate nobody conformed has no paper behind it.

EntradaSolicitation documentsWage determinationResultadoRate table loadedClassifications not listed
2

Price the work at the determination, not at your shop rate

Planilha Orçamentária

Build the crew rate behind each item from the determination's basic rate plus its fringe, then add the burdens the fringe does not cover, and price overtime at time and a half beyond forty hours in the week. Keep the difference between this and your ordinary shop rate visible as its own figure.

Captura de tela, etapa 2: Price the work at the determination, not at your shop rate (Planilha Orçamentária, Pague os salários Davis-Bacon e entregue o certified payroll)
Planilha Orçamentária: Price the work at the determination, not at your shop rate

Por quê: The fringe is part of the obligation and not an allowance, so a bill priced on base rates alone is short by the fringe on every hour. Keeping the difference from your ordinary rates visible is what lets the company decide whether it wants this kind of work at all, rather than finding out at the post mortem that federally funded jobs quietly lose money.

EntradaRate table loadedScope and quantitiesResultadoPriced billCost above shop rates
3

Capture hours by classification, not by name alone

Tempo em obra

Book every hour worked on site against the classification the work belongs to and the day it happened. Where somebody worked two classifications in one day, record both with the hours split between them rather than putting the whole day under the higher one or the lower one.

Por quê: The certified payroll is a statement about hours by classification, so a timesheet that records only hours by person cannot produce it and has to be reconstructed from memory every Friday. Split days are where reconstruction goes wrong, and an underpayment found months later is repaid with interest plus whatever the agency withholds while it looks at the rest of the file.

EntradaCrew on siteClassification listResultadoHours by classificationSplit-classification days
4

Pay weekly, with the fringe in cash or into a real plan

Processamento de Salários

Run the payroll once a week, pay each worker the basic rate for the classification they worked, and settle the fringe either as cash on the paycheck or as a contribution to a bona fide plan, recorded either way. Pay apprentices at their program rate only where they are registered in an approved program and only within the ratio it allows, and list every deduction taken.

Por quê: Weekly payment is part of the obligation, not a company habit, and an unregistered apprentice is simply a journeyman being underpaid. Deductions are the other common finding: anything beyond the ones permitted turns a correct gross wage into an incorrect net one, and it is the net figure the investigator reads first.

EntradaHours by classificationFringe benefit plansResultadoWeekly payroll runDeductions recorded
5

File the weekly certified payroll and sign the statement

Documentos

Produce the payroll for each week the crew worked on the site, showing every worker with their classification, hours by day, rate, gross, deductions and net, and file it with the contracting agency within the days the contract allows after the pay date. Attach the signed statement of compliance and keep the filed copy with the week it covers. The published form is optional; the information on it is not.

Captura de tela, etapa 5: File the weekly certified payroll and sign the statement (Documentos, Pague os salários Davis-Bacon e entregue o certified payroll)
Documentos: File the weekly certified payroll and sign the statement

Por quê: This is the document that turns paying correctly into having proved it, and it is signed personally under penalty, which is why it should never be assembled by somebody who did not see the hours. A week filed late is a compliance finding on its own, before anybody has looked at whether the wages themselves were right, and the usual remedy is the agency holding the next payment.

EntradaWeekly payroll runWage determinationResultadoCertified payroll filedStatement of compliance
6

Hold every subcontractor to the same obligation

Diretório de subempreiteiros

Write the wage clauses and the determination into every subcontract at every tier, then make the week's certified payroll a condition of that subcontractor being paid rather than something chased afterwards. Read what they send: a payroll with a classification that is not on the determination, or a rate below it, is a finding you can still fix.

Captura de tela, etapa 6: Hold every subcontractor to the same obligation (Diretório de subempreiteiros, Pague os salários Davis-Bacon e entregue o certified payroll)
Diretório de subempreiteiros: Hold every subcontractor to the same obligation

Por quê: The prime contractor answers for the compliance of the whole chain, so a second tier subcontractor underpaying its crew is the prime's restitution to pay and the prime's payments the agency withholds. Gating the money on the paperwork is the only mechanism that reliably produces the paperwork, and it costs nothing while the money is still yours.

EntradaSubcontract listSubcontractor payrollsResultadoPayment gated on the payrollCompliance record per sub
7

Put the weekly clock and the retention date under watch

Prazos

Set the weekly filing date as a recurring deadline for as long as anyone works on the site, add the posting of the determination and the worker notice at the site entrance, and record the date the payroll records may finally be destroyed, counted from completion rather than from the last pay date.

Captura de tela, etapa 7: Put the weekly clock and the retention date under watch (Prazos, Pague os salários Davis-Bacon e entregue o certified payroll)
Prazos: Put the weekly clock and the retention date under watch

Por quê: An investigation usually arrives long after the crews have gone, and it asks for the weeks nobody remembers. Records destroyed before the retention period ends leave the contractor unable to prove a payment it actually made, which in practice is the same position as not having made it.

EntradaWeekly filing scheduleRecord retention ruleResultadoFiling dates under watchRecords kept to the end date
Módulos

Módulos deste playbook

7 / 190 módulos da plataforma

O mercado para o qual este caso foi escrito

Estados Unidos

Tudo neste caso segue a forma como a obra é medida, orçada e paga neste mercado. Os documentos, a decomposição de custos e as regras de pagamento são os que se usam lá, não uma versão genérica.

Normas que ele segue

  • CSI MasterFormat
  • UniFormat II
  • AIA A201

Você não precisa configurar nada disso na mão. Na primeira vez que abre a plataforma, ela pergunta em que mercado você trabalha. Escolha este e ela ajusta o idioma da interface, carrega a base de custos correspondente, registra a classificação de custos e adiciona um projeto de exemplo que você pode abrir na hora.

As verificações deste mercado também vêm com a plataforma. Ative uma vez e um orçamento ao qual falte algo que o mercado espera é sinalizado enquanto você trabalha nele, e não depois que a proposta já saiu.

Mais em Comercial e contratos

Comercial e contratos

Gerir um pacote de subempreitada

Adjudique um pacote de trabalhos a um subempreiteiro, coloque-o num subcontrato com um mapa…

3 etapas11 minAbrir
Comercial e contratos

Fatura de pagamento e conciliação

Valorize o trabalho executado neste período face ao contrato, apresente a fatura com a evidê…

3 etapas12 minAbrir