Scenariusze / Budowa i teren
Budowa i teren

Otwórz budowę zgodnie z Construction Regulations

Ustal, czy robota wymaga construction work permit, czy tylko zgłoszenia, ustaw specyfikację i plan we właściwej kolejności, dokonaj wszystkich wyznaczeń na piśmie i załóż health and safety file pierwszego dnia, zamiast odtwarzać go przy odbiorze.

7 kroków14 minGeneralny wykonawcaDeweloper / klientBiuro zarządzania projektem / budową

Jak to działa, krok po kroku

7 kroków w całej platformie - co robisz na każdym z nich i dlaczego to ważne.

1

Decide between a permit and a notification, then apply

Zgłoszenia do urzędu

Measure the job against regulation 3(1): more than 180 days, more than 1800 person days, or a works contract value equal to or exceeding thirteen million rand or CIDB grading level 6. Any one of those means the client applies for a construction work permit at least 30 days before work starts. Below that, regulation 4(1) still requires notification at least 7 days before where the work includes excavation, work at height with a risk of falling, demolition or the use of explosives.

Dlaczego: Regulation 3(7) forbids construction work before the permit and its number have been issued, and regulation 3(4) requires the number to be displayed conspicuously at the main entrance to the site. A programme that puts the first activity 30 days after award on a permit job is a programme that starts with an unlawful month, and an inspector reads the entrance board before anything else.

WejścieScope and durationWorks contract valueWynikPermit or notificationPermit number
2

Get the client's specification written before tender

Zarządzanie HSE

The client prepares a baseline risk assessment for the intended work under regulation 5(1)(a) and, on it, a site specific health and safety specification under regulation 5(1)(b), and gives that specification to the designer and to every tenderer. Where a permit is required, regulation 5(5) also has the client appoint a competent person in writing as agent, and regulation 5(7)(b) requires that agent to be registered with a statutory body approved by the Chief Inspector.

Zrzut ekranu, krok 2: Get the client's specification written before tender (Zarządzanie HSE, Otwórz budowę zgodnie z Construction Regulations)
Zarządzanie HSE: Get the client's specification written before tender

Dlaczego: The specification is the client's document and it comes first, because the contractor's plan is written against it. A tender issued without one produces bids that have priced nothing for health and safety, and a contractor asked afterwards to write both documents has been asked to set its own standard and then to be measured against it.

WejścieDesign informationSite hazardsWynikBaseline risk assessmentHealth and safety specification
3

Write the plan against the specification and get it approved

Bezpieczeństwo

The principal contractor prepares the health and safety plan required by regulation 7(1)(a) against the client's specification, with the risk assessments required by regulation 9 done by a competent person appointed in writing and forming part of the plan. The client then discusses and negotiates the contents of that plan with the principal contractor and finally approves it for implementation under regulation 5(1)(l).

Zrzut ekranu, krok 3: Write the plan against the specification and get it approved (Bezpieczeństwo, Otwórz budowę zgodnie z Construction Regulations)
Bezpieczeństwo: Write the plan against the specification and get it approved

Dlaczego: An approved plan is what turns a generic safety policy into something enforceable on this site, activity by activity. It is also the document a client is entitled to stop work over: where the plan is not being followed the client may stop the work, and an approval that was never obtained leaves both sides arguing about what the standard was after somebody has been hurt.

WejścieClient specificationMethod statementsWynikHealth and safety planRisk assessments
4

Make every appointment in writing, and only for this site

Nadzór na budowie

Appoint in writing, with the competence evidence attached: a full time construction manager for this single site under regulation 8(1), a construction health and safety officer under regulation 8(5) after consultation with the client and registered with an approved statutory body under regulation 8(6), and the construction supervisors that the construction manager itself must appoint in writing under regulation 8(7).

Zrzut ekranu, krok 4: Make every appointment in writing, and only for this site (Nadzór na budowie, Otwórz budowę zgodnie z Construction Regulations)
Nadzór na budowie: Make every appointment in writing, and only for this site

Dlaczego: Regulation 8(4) says a construction manager may not manage more than one site, and regulation 8(10) limits a construction supervisor in the same way unless enough competent employees are designated on every site involved. The habit of one manager covering three sites in a province is exactly what those subregulations forbid, and an appointment letter naming two sites is evidence of the breach rather than cover for it.

WejścieNominated peopleCompetence evidenceWynikWritten appointmentsSite responsibility chart
5

Induct everyone who comes through the gate

Mobilizacja placu budowy

Run health and safety induction training for employees and for visitors, keep the record of it on site as regulation 7(7) requires, and hold a valid medical certificate of fitness in the form of Annexure 3 for every worker before they start.

Zrzut ekranu, krok 5: Induct everyone who comes through the gate (Mobilizacja placu budowy, Otwórz budowę zgodnie z Construction Regulations)
Mobilizacja placu budowy: Induct everyone who comes through the gate

Dlaczego: Induction records and certificates of fitness are the two things checked first in an inspection and the two things hardest to reconstruct afterwards, because they are about individual people on individual days. A gate register that matches the induction list is the cheapest proof a site can hold, and it only exists if it is kept as people arrive.

WejścieWorkers and visitorsApproved planWynikInduction recordsCertificates of fitness
6

Keep the audit cycle running every thirty days

Kontrole

Regulation 5(1)(o) has the client ensure that health and safety audits and document verification are carried out at intervals agreed with the contractors but at least once every 30 days, and regulation 5(1)(p) puts the report in the principal contractor's hands within seven days. Log each finding as a corrective action with an owner and a date, and close it against evidence rather than against a promise.

Zrzut ekranu, krok 6: Keep the audit cycle running every thirty days (Kontrole, Otwórz budowę zgodnie z Construction Regulations)
Kontrole: Keep the audit cycle running every thirty days

Dlaczego: A thirty day audit that nobody diarised becomes a ninety day audit, and a finding that was closed by conversation is a finding that comes back. The audit trail is also the client's own protection: the duty in regulation 5 is the client's, and a client that never audited cannot show it discharged it.

WejścieApproved planSite walksWynikAudit reportsCorrective actions
7

Keep the health and safety file, then hand it over

Dokumenty

Keep and maintain the health and safety file required by regulation 7(1)(b) from the first day of the job, and on completion hand a consolidated file to the client under regulation 7(1)(e), including a record of all drawings, designs and materials used and any other information about the structure.

Zrzut ekranu, krok 7: Keep the health and safety file, then hand it over (Dokumenty, Otwórz budowę zgodnie z Construction Regulations)
Dokumenty: Keep the health and safety file, then hand it over

Dlaczego: The file is not a closing document, it is the running record that happens to be handed over at the end. A file assembled in the last fortnight of a two year contract is missing the appointment letters of people who left, the certificates of materials nobody kept the delivery notes for, and the audit reports from the first winter. The client also needs it to run the building: the next contractor to open a ceiling is relying on what is in it.

WejścieSite recordsDrawings and materialsWynikHealth and safety fileHandover to client
Moduły

Moduły w tym playbooku

7 / 190 modułów platformy

The market this case is written for

Republika Południowej Afryki

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • JBCC 6.2
  • SANS 1921

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Więcej w kategorii Budowa i teren

Budowa i teren

Zamknij dzień budowy

Zamknij dzień budowy prawidłowo: wpisz dziennik, zaksięguj godziny roboczej i sprzętu, wgraj…

4 kroków9 minOtwórz
Budowa i teren

Odpowiedz na zapytanie RFI

Zamień pytanie z frontu robót w śledzone zapytanie, przekaż je stronie odpowiedzialnej za od…

3 kroków9 minOtwórz