Correr o relógio de segurança de pagamento sobre um auto de progresso

Meça o período face ao calendário do contrato, submeta o auto de progresso ao Superintendent, notifique-o como reclamação de pagamento ao abrigo do Security of Payment Act e deixe o módulo contar os dias úteis de que o destinatário dispõe, para que um pagamento atrasado seja um registo datado em vez de um telefonema.

7 etapas12 minEmpreiteiro geralSubempreiteiro especializadoConsultoria de custos / QS

Como funciona, passo a passo

7 passos ao longo da plataforma - o que fazer em cada um e por que importa.

1

Measure the period claim item by claim item

Avanço

Record what was executed against each claim item for the period as a percentage of its contract quantity. The earned quantity follows from that percentage and the design quantity, and the earned amount from the same percentage and the position total, so one honest number per line produces the whole valuation.

Captura de tela, etapa 1: Measure the period claim item by claim item (Avanço, Correr o relógio de segurança de pagamento sobre um auto de progresso)
Avanço: Measure the period claim item by claim item

Por quê: A progress claim built from a single project percentage cannot be checked and therefore cannot be approved without a conversation. Measured line by line, the disagreement is about one claim item rather than about the whole month, and the rest of the money moves while that one is settled.

EntradaContract schedule of ratesWork executed this periodResultadoPercent complete per claim itemEarned quantities for the period
2

Value it at the contract rates

Planilha Orçamentária

Read the valuation back against the bill and check the rates it used are the contract rates. Where a claim item has been measured past the quantity the contract carries, deal with it as a change to the position with an order behind it rather than as a larger figure on the same line.

Captura de tela, etapa 2: Value it at the contract rates (Planilha Orçamentária, Correr o relógio de segurança de pagamento sobre um auto de progresso)
Planilha Orçamentária: Value it at the contract rates

Por quê: A variation certified quietly is one the client can refuse at the final account, months after the work was built and paid for down the chain. Raising it as a change while it is small is the only version of that conversation where you are not asking to be paid for work already done.

EntradaEarned quantities for the periodContract ratesResultadoValuation for the periodVariations flagged
3

Serve the payment claim on the respondent

Finanças

Raise the payment claim from the valuation, carrying retention and any deduction the contract provides for, and serve it the way the contract directs, which under the standard forms is by giving it to the Superintendent. Record the day and the manner of service, because every deadline in the regime counts from that day. In New South Wales the claim must say on its face that it is made under the Act, on every contract signed since 21 October 2019, and a head contractor's claim on the principal must carry the supporting statement that its subcontractors have been paid. Queensland went the other way: any invoice that identifies the work and states the amount is a payment claim there, endorsed or not, so an invoice you did not mean as a claim still starts a clock.

Captura de tela, etapa 3: Serve the payment claim on the respondent (Finanças, Correr o relógio de segurança de pagamento sobre um auto de progresso)
Finanças: Serve the payment claim on the respondent

Por quê: Nothing in the regime waits for the Superintendent. The Act counts from service, the respondent has a fixed number of business days to answer with a payment schedule, and a claim served late, served on the wrong party or missing the words the Act requires is a month of cash flow lost with nobody to blame but the claimant.

EntradaValuation for the periodRetention and deductionsResultadoPayment claim servedReference to the Act on the claim
4

Open the payment clock on the right day

Relógio de pagamento

Open a clock over the payment claim starting from the day it is served, under the Act of the state the work is in. In New South Wales payment falls due 15 business days after service on a head contract and 20 on a subcontract, and the respondent has 10 business days to answer with a payment schedule; Queensland runs its own count under the Building Industry Fairness Act. A contract may shorten either period and never lengthen it. The clock records the dates rather than leaving them to be worked out when somebody asks.

Por quê: The single most expensive mistake in interim payment is starting the count on the wrong event, because every deadline behind it inherits the error and none of them look wrong. Anchoring on the day the payment claim is served once makes the whole chain checkable. Business days are not calendar days, the state's public holidays move the answer, and New South Wales strikes 27 to 31 December out of the count as well. Counting them by hand is how a claimant arrives at adjudication one day out of time with a case that was otherwise good.

EntradaPayment claim servedDate of serviceResultadoOpen payment clockDue date computed
5

Read the dates the regime computes

Relógio de pagamento

Read back the dates the Security of Payment Act produces from the day the payment claim is served. The sum payable leads, the due date and the final date for payment sit under it, and the derivation spells out each date against the provision it came from, so every one of them can be quoted rather than asserted. Two dates matter here and only one of them is about money: the date a payment schedule is due, and the date payment is due. A respondent who lets the first pass without a schedule has agreed to the claimed amount.

Por quê: Deadlines that are typed in are deadlines that are typed in wrong, and a payment regime has more of them than anyone holds in their head. A derivation you can read out loud is what turns a phone call about a late payment into a quotable line.

EntradaOpen payment clockStatutory regime on recordResultadoDate a payment schedule is dueFinal date for payment
6

Log the Superintendent's certificate as the payment schedule

Relógio de pagamento

When the Superintendent's progress certificate comes back, record it against the claim as the payment schedule, with the day it arrived and the amount it schedules. If it schedules less than was claimed it has to say why, and if it arrives after the business days the Act allows it is no schedule at all and the claimed amount stands.

Por quê: The Superintendent certifies under the contract and the Act runs on its own timetable regardless, so a certificate that arrives late does not move the statutory dates, it only decides whether the respondent still has a schedule. Recording both is what lets you see the two regimes disagree while there is still time to act on it.

EntradaPayment claim servedSuperintendent's progress certificateResultadoPayment schedule on recordDate the schedule arrived
7

Escalate with the record already assembled

Documentos

When the clock has run out, lodge an adjudication application under the Security of Payment Act. The record the steps above produced, dates, approvals and the documents themselves, is the case, and it is assembled already rather than reconstructed under time pressure. Under the New South Wales Act an unanswered claim needs a notice of intention to apply, served inside the window the Act gives, before the application itself, and both windows are counted in business days.

Captura de tela, etapa 7: Escalate with the record already assembled (Documentos, Correr o relógio de segurança de pagamento sobre um auto de progresso)
Documentos: Escalate with the record already assembled

Por quê: The difference between a claim that is paid and one that is argued about is almost never the merits. It is whether the dates and the documents were kept as the work happened, because reconstructing them afterwards is expensive and looks exactly like inventing them.

EntradaPassed deadlinesClaim, schedule and service datesResultadoAdjudication applicationEntitlement preserved
Módulos

Módulos deste playbook

5 / 190 módulos da plataforma

O mercado para o qual este caso foi escrito

Austrália

Tudo neste caso segue a forma como a obra é medida, orçada e paga neste mercado. Os documentos, a decomposição de custos e as regras de pagamento são os que se usam lá, não uma versão genérica.

Normas que ele segue

  • AS 4000
  • Security of Payment Act

Você não precisa configurar nada disso na mão. Na primeira vez que abre a plataforma, ela pergunta em que mercado você trabalha. Escolha este e ela ajusta o idioma da interface, carrega a base de custos correspondente, registra a classificação de custos e adiciona um projeto de exemplo que você pode abrir na hora.

As verificações deste mercado também vêm com a plataforma. Ative uma vez e um orçamento ao qual falte algo que o mercado espera é sinalizado enquanto você trabalha nele, e não depois que a proposta já saiu.

Mais em Comercial e contratos

Comercial e contratos

Gerir um pacote de subempreitada

Adjudique um pacote de trabalhos a um subempreiteiro, coloque-o num subcontrato com um mapa…

3 etapas11 minAbrir
Comercial e contratos

Fatura de pagamento e conciliação

Valorize o trabalho executado neste período face ao contrato, apresente a fatura com a evidê…

3 etapas12 minAbrir