interim payment certificate جاری کریں اور اس پر payment حاصل کریں

مدت کو بل کے مقابلے میں ناپیں، اسے کنٹریکٹ ریٹس پر value کریں، retention روکیں، principal agent سے interim payment certificate جاری کروائیں اور certificate کی تاریخ سے clock کھولیں، کیونکہ اس کے بعد آنے والی window ہفتوں میں نہیں دنوں میں ناپی جاتی ہے۔

9 مراحل12 منٹجنرل کنٹریکٹرخصوصی سب کنٹریکٹرکاسٹ کنسلٹنسی / QS فرم

یہ کیسے کام کرتا ہے، قدم بہ قدم

9 قدم پوری پلیٹ فارم میں - ہر قدم پر کیا کرنا ہے اور یہ کیوں اہم ہے۔

1

Measure the period bill item by bill item

پیش رفت

Record what was executed against each bill item for the period as a percentage of its contract quantity. The earned quantity follows from that percentage and the design quantity, and the earned amount from the same percentage and the position total, so one honest number per line produces the whole valuation.

اسکرین شاٹ، قدم 1: Measure the period bill item by bill item (پیش رفت, interim payment certificate جاری کریں اور اس پر payment حاصل کریں)
پیش رفت: Measure the period bill item by bill item

کیوں: A payment valuation built from a single project percentage cannot be checked and therefore cannot be approved without a conversation. Measured line by line, the disagreement is about one bill item rather than about the whole month, and the rest of the money moves while that one is settled.

اندر جاتا ہےContract bill of quantitiesWork executed this periodباہر آتا ہےPercent complete per bill itemEarned quantities for the period
2

Value it at the contract rates

مقدار کا بل (BOQ)

Read the valuation back against the bill and check the rates it used are the contract rates. Where a bill item has been measured past the quantity the contract carries, deal with it as a change to the position with an order behind it rather than as a larger figure on the same line.

اسکرین شاٹ، قدم 2: Value it at the contract rates (مقدار کا بل (BOQ), interim payment certificate جاری کریں اور اس پر payment حاصل کریں)
مقدار کا بل (BOQ): Value it at the contract rates

کیوں: A contract instruction certified quietly is one the client can refuse at the final account, months after the work was built and paid for down the chain. Raising it as a change while it is small is the only version of that conversation where you are not asking to be paid for work already done.

اندر جاتا ہےEarned quantities for the periodContract ratesباہر آتا ہےValuation for the periodContract instructions flagged
3

Apply retention and previous payments

مالیات

Take the cumulative valuation, subtract what has already been certified, and apply retention at the contract percentage. The figure that leaves this step is the one the tax invoice is raised for, and the backup behind it is the measure that produced it. Under JBCC 6.2 the money withheld is the payment reduction that comes with the fixed construction guarantee, 5 percent of the value certified up to practical completion and 2.5 percent up to final completion, and under GCC 2015 it is retention in the ordinary sense; either way it is a figure with a release date attached.

اسکرین شاٹ، قدم 3: Apply retention and previous payments (مالیات, interim payment certificate جاری کریں اور اس پر payment حاصل کریں)
مالیات: Apply retention and previous payments

کیوں: Interim payments are cumulative, so the month's money is a difference between two totals rather than a total of its own. Computing it from the cumulative figure is what stops a line being paid twice or dropped entirely when a period is re-measured.

اندر جاتا ہےCumulative valuationPrevious payments and retentionباہر آتا ہےRetention held to dateNet due for the period
4

Get it approved by the people who have to approve it

منظوری روٹس

Route the payment valuation to the principal agent, and to whoever the contract adds after them. Keep the approval date, because the tax invoice follows the approval and the payment clock runs from there, so an approval that slips moves everything behind it. The principal agent's approval is the interim payment certificate itself, issued by the date for issue the contract data fixes each month. Record that date beside the day the certificate actually arrived, because the payment count runs from the first and a certificate issued late does not move it.

اسکرین شاٹ، قدم 4: Get it approved by the people who have to approve it (منظوری روٹس, interim payment certificate جاری کریں اور اس پر payment حاصل کریں)
منظوری روٹس: Get it approved by the people who have to approve it

کیوں: Approval sitting in an inbox is the most common reason a payment is late, and it is invisible while it is happening because nobody has refused anything. A route with a date on each hop turns that into a question with an owner instead of a monthly complaint.

اندر جاتا ہےValuation for the periodPrincipal agent named for certificationباہر آتا ہےInterim payment certificate issuedDate for issue and date issued on record
5

Issue the tax invoice against the approved figure

مالیات

Raise the tax invoice against the approved payment valuation, carrying retention and any deduction the contract provides for, and reference the payment valuation on it. Quote the certificate number and the certified amount on the invoice, since the employer's accounts pay against the certificate and not against the valuation.

اسکرین شاٹ، قدم 5: Issue the tax invoice against the approved figure (مالیات, interim payment certificate جاری کریں اور اس پر payment حاصل کریں)
مالیات: Issue the tax invoice against the approved figure

کیوں: A demand for a figure nobody approved is one that will be returned, and the clock does not start on a returned document. Matching it to the payment valuation also means the accounts and the valuation tell the same story at year end without anybody reconciling them by hand.

اندر جاتا ہےInterim payment certificate issuedRetention and deductionsباہر آتا ہےTax invoice issuedAmount carried into the accounts
6

Open the payment clock on the right day

ادائیگی کی گھڑی

Open a clock over the tax invoice starting from the date for issue of the payment certificate fixed in the contract data, under the JBCC payment clause. Payment falls due 14 calendar days later, and the clock records that date rather than leaving it to be worked out when somebody asks.

کیوں: The single most expensive mistake in interim payment is starting the count on the wrong event, because every deadline behind it inherits the error and none of them look wrong. Anchoring on the date for issue of the payment certificate fixed in the contract data once makes the whole chain checkable. Opening it on the day the certificate arrived, or on your own invoice date, moves every deadline later and does it silently, which is the version of this mistake that never gets caught, because nothing looks overdue until the remedy has already expired. The agreement counts from the date the certificate was due, so a principal agent who issues late has not bought the employer a day.

اندر جاتا ہےCertificate and its date for issueCertified amountباہر آتا ہےOpen payment clockDue date computed
7

Read the dates the regime computes

ادائیگی کی گھڑی

Read back the dates the JBCC payment clause produces from the date for issue of the payment certificate fixed in the contract data. The sum payable leads, the due date and the final date for payment sit under it, and the derivation spells out each date against the provision it came from, so every one of them can be quoted rather than asserted. There is no statute behind these dates, so the only authority is the agreement: fourteen calendar days from the date for issue under JBCC 6.2, seven more for the money to reach each subcontractor, and GCC 2015 running its own longer count from the engineer's certificate. The row the clock is opened on has to carry the count the agreement gives, and its derivation is what you quote.

کیوں: Deadlines that are typed in are deadlines that are typed in wrong, and a payment regime has more of them than anyone holds in their head. A derivation you can read out loud is what turns a phone call about a late payment into a quotable line.

اندر جاتا ہےOpen payment clockChosen regimeباہر آتا ہےDue dateDerivation you can quote
8

Watch the clock count each deadline down

ادائیگی کی گھڑی

Come back to the list as the month runs. It says how many clocks the project carries and how many are past their final date, badges the overdue ones and fills the breach register underneath. Open an overdue one and the findings name the sum outstanding, the days it has run past the final date and the rate interest runs at.

کیوں: Reading a clock is what writes its register, so a quiet register on a project nobody opens is telling you about the reading and not about the payments. Nobody misses a deadline on purpose; they miss it because the day it mattered looked like every other day.

اندر جاتا ہےOpen clocks on the projectFinal dates for paymentباہر آتا ہےOverdue certificates flaggedBreach register rows
9

Escalate with the record already assembled

خط و کتابت

When the clock has run out, give the employer the five working days notice to comply that the JBCC agreement requires, and if it passes unpaid suspend the works, exercise the lien or call up the payment guarantee. The record the steps above produced, dates, approvals and the documents themselves, is the case, and it is assembled already rather than reconstructed under time pressure.

اسکرین شاٹ، قدم 9: Escalate with the record already assembled (خط و کتابت, interim payment certificate جاری کریں اور اس پر payment حاصل کریں)
خط و کتابت: Escalate with the record already assembled

کیوں: The difference between a claim that is paid and one that is argued about is almost never the merits. It is whether the dates and the documents were kept as the work happened, because reconstructing them afterwards is expensive and looks exactly like inventing them.

اندر جاتا ہےDue date passed unpaidCertificate, invoice and datesباہر آتا ہےFive working days notice to complyRight to suspend or call the guarantee preserved
ماڈیولز

اس سیناریو کے ماڈیولز

6 / 190 پلیٹ فارم ماڈیولز

The market this case is written for

جنوبی افریقہ

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • JBCC 6.2
  • SANS 1921

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

کمرشل اور کنٹریکٹس میں مزید

کمرشل اور کنٹریکٹس

سب کنٹریکٹر پیکج چلائیں

ٹریڈ پیکج کسی سب کنٹریکٹر کو دیں، اسے شیڈول آف ویلیوز اور ریٹینشن کے ساتھ سب کنٹریکٹ پر رکھی…

3 مراحل11 منٹکھولیں
کمرشل اور کنٹریکٹس

ادائیگی کی درخواست اور مصالحت

اس مدت میں جگہ پر لگے کام کی قیمت کنٹریکٹ کے مقابلے میں لگائیں، پیچھے ثبوت کے ساتھ درخواست ا…

3 مراحل12 منٹکھولیں