صدور interim payment certificate و دریافت پرداخت بر اساس آن

دوره را در برابر صورت‌وضعیت اندازه‌گیری کنید، آن را به نرخ‌های قرارداد ارزش‌گذاری کنید، اقلام حسن انجام کار را نگه دارید، از نماینده اصلی بخواهید interim payment certificate صادر کند و ساعت را از تاریخ گواهی آغاز کنید، چون بازه‌ای که پس از آن می‌آید به روز اندازه‌گیری می‌شود نه هفته.

9 مرحله12 دقیقهپیمانکار عمومیپیمانکار جزء تخصصیمشاوره هزینه / QS

چگونه کار می‌کند، گام به گام

9 گام در سراسر پلتفرم - کاری که در هر گام انجام می‌دهید و چرا اهمیت دارد.

1

Measure the period bill item by bill item

پیشرفت

Record what was executed against each bill item for the period as a percentage of its contract quantity. The earned quantity follows from that percentage and the design quantity, and the earned amount from the same percentage and the position total, so one honest number per line produces the whole valuation.

چرا: A payment valuation built from a single project percentage cannot be checked and therefore cannot be approved without a conversation. Measured line by line, the disagreement is about one bill item rather than about the whole month, and the rest of the money moves while that one is settled.

ورودیContract bill of quantitiesWork executed this periodخروجیPercent complete per bill itemEarned quantities for the period
2

Value it at the contract rates

صورت مقادیر (BOQ)

Read the valuation back against the bill and check the rates it used are the contract rates. Where a bill item has been measured past the quantity the contract carries, deal with it as a change to the position with an order behind it rather than as a larger figure on the same line.

چرا: A contract instruction certified quietly is one the client can refuse at the final account, months after the work was built and paid for down the chain. Raising it as a change while it is small is the only version of that conversation where you are not asking to be paid for work already done.

ورودیEarned quantities for the periodContract ratesخروجیValuation for the periodContract instructions flagged
3

Apply retention and previous payments

مالی

Take the cumulative valuation, subtract what has already been certified, and apply retention at the contract percentage. The figure that leaves this step is the one the tax invoice is raised for, and the backup behind it is the measure that produced it. Under JBCC 6.2 the money withheld is the payment reduction that comes with the fixed construction guarantee, 5 percent of the value certified up to practical completion and 2.5 percent up to final completion, and under GCC 2015 it is retention in the ordinary sense; either way it is a figure with a release date attached.

چرا: Interim payments are cumulative, so the month's money is a difference between two totals rather than a total of its own. Computing it from the cumulative figure is what stops a line being paid twice or dropped entirely when a period is re-measured.

ورودیCumulative valuationPrevious payments and retentionخروجیRetention held to dateNet due for the period
4

Get it approved by the people who have to approve it

مسیرهای تأیید

Route the payment valuation to the principal agent, and to whoever the contract adds after them. Keep the approval date, because the tax invoice follows the approval and the payment clock runs from there, so an approval that slips moves everything behind it. The principal agent's approval is the interim payment certificate itself, issued by the date for issue the contract data fixes each month. Record that date beside the day the certificate actually arrived, because the payment count runs from the first and a certificate issued late does not move it.

چرا: Approval sitting in an inbox is the most common reason a payment is late, and it is invisible while it is happening because nobody has refused anything. A route with a date on each hop turns that into a question with an owner instead of a monthly complaint.

ورودیValuation for the periodPrincipal agent named for certificationخروجیInterim payment certificate issuedDate for issue and date issued on record
5

Issue the tax invoice against the approved figure

مالی

Raise the tax invoice against the approved payment valuation, carrying retention and any deduction the contract provides for, and reference the payment valuation on it. Quote the certificate number and the certified amount on the invoice, since the employer's accounts pay against the certificate and not against the valuation.

چرا: A demand for a figure nobody approved is one that will be returned, and the clock does not start on a returned document. Matching it to the payment valuation also means the accounts and the valuation tell the same story at year end without anybody reconciling them by hand.

ورودیInterim payment certificate issuedRetention and deductionsخروجیTax invoice issuedAmount carried into the accounts
6

Open the payment clock on the right day

ساعت پرداخت

Open a clock over the tax invoice starting from the date for issue of the payment certificate fixed in the contract data, under the JBCC payment clause. Payment falls due 14 calendar days later, and the clock records that date rather than leaving it to be worked out when somebody asks.

چرا: The single most expensive mistake in interim payment is starting the count on the wrong event, because every deadline behind it inherits the error and none of them look wrong. Anchoring on the date for issue of the payment certificate fixed in the contract data once makes the whole chain checkable. Opening it on the day the certificate arrived, or on your own invoice date, moves every deadline later and does it silently, which is the version of this mistake that never gets caught, because nothing looks overdue until the remedy has already expired. The agreement counts from the date the certificate was due, so a principal agent who issues late has not bought the employer a day.

ورودیCertificate and its date for issueCertified amountخروجیOpen payment clockDue date computed
7

Read the dates the regime computes

ساعت پرداخت

Read back the dates the JBCC payment clause produces from the date for issue of the payment certificate fixed in the contract data. The sum payable leads, the due date and the final date for payment sit under it, and the derivation spells out each date against the provision it came from, so every one of them can be quoted rather than asserted. There is no statute behind these dates, so the only authority is the agreement: fourteen calendar days from the date for issue under JBCC 6.2, seven more for the money to reach each subcontractor, and GCC 2015 running its own longer count from the engineer's certificate. The row the clock is opened on has to carry the count the agreement gives, and its derivation is what you quote.

چرا: Deadlines that are typed in are deadlines that are typed in wrong, and a payment regime has more of them than anyone holds in their head. A derivation you can read out loud is what turns a phone call about a late payment into a quotable line.

ورودیOpen payment clockChosen regimeخروجیDue dateDerivation you can quote
8

Watch the clock count each deadline down

ساعت پرداخت

Come back to the list as the month runs. It says how many clocks the project carries and how many are past their final date, badges the overdue ones and fills the breach register underneath. Open an overdue one and the findings name the sum outstanding, the days it has run past the final date and the rate interest runs at.

چرا: Reading a clock is what writes its register, so a quiet register on a project nobody opens is telling you about the reading and not about the payments. Nobody misses a deadline on purpose; they miss it because the day it mattered looked like every other day.

ورودیOpen clocks on the projectFinal dates for paymentخروجیOverdue certificates flaggedBreach register rows
9

Escalate with the record already assembled

مکاتبات

When the clock has run out, give the employer the five working days notice to comply that the JBCC agreement requires, and if it passes unpaid suspend the works, exercise the lien or call up the payment guarantee. The record the steps above produced, dates, approvals and the documents themselves, is the case, and it is assembled already rather than reconstructed under time pressure.

چرا: The difference between a claim that is paid and one that is argued about is almost never the merits. It is whether the dates and the documents were kept as the work happened, because reconstructing them afterwards is expensive and looks exactly like inventing them.

ورودیDue date passed unpaidCertificate, invoice and datesخروجیFive working days notice to complyRight to suspend or call the guarantee preserved
ماژول‌ها

ماژول‌های این سناریو

6 / 190 ماژول پلتفرم

The market this case is written for

افریقای جنوبی

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • JBCC 6.2
  • SANS 1921

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

بیشتر در بازرگانی و قراردادها

بازرگانی و قراردادها

اجرای یک بسته پیمانکار جزء

یک بسته کاری را به یک پیمانکار جزء واگذار کنید، آن را در یک پیمان فرعی همراه با جدول ارزش‌ها…

3 مرحله11 دقیقهباز کردن
بازرگانی و قراردادها

درخواست پرداخت و تطبیق

کار انجام‌شده این دوره را در برابر قرارداد ارزش‌گذاری کنید، درخواست پرداخت را همراه با مدارک…

3 مرحله12 دقیقهباز کردن