Convertir un cambio en una modificación pagada
Registra un cambio de alcance mientras está reciente, valóralo como una modificación contrac…
Mida el período frente al presupuesto, valórelo a los precios del contrato, aplique la retención, haga que el Principal Agent emita el certificado de pago provisional y abra el reloj de pago en la fecha del certificado, porque el plazo que le sigue se mide en días y no en semanas.
9 pasos a lo largo de la plataforma - qué hacer en cada uno y por qué importa.
Record what was executed against each bill item for the period as a percentage of its contract quantity. The earned quantity follows from that percentage and the design quantity, and the earned amount from the same percentage and the position total, so one honest number per line produces the whole valuation.

Por que: A payment valuation built from a single project percentage cannot be checked and therefore cannot be approved without a conversation. Measured line by line, the disagreement is about one bill item rather than about the whole month, and the rest of the money moves while that one is settled.
Read the valuation back against the bill and check the rates it used are the contract rates. Where a bill item has been measured past the quantity the contract carries, deal with it as a change to the position with an order behind it rather than as a larger figure on the same line.

Por que: A contract instruction certified quietly is one the client can refuse at the final account, months after the work was built and paid for down the chain. Raising it as a change while it is small is the only version of that conversation where you are not asking to be paid for work already done.
Take the cumulative valuation, subtract what has already been certified, and apply retention at the contract percentage. The figure that leaves this step is the one the tax invoice is raised for, and the backup behind it is the measure that produced it. Under JBCC 6.2 the money withheld is the payment reduction that comes with the fixed construction guarantee, 5 percent of the value certified up to practical completion and 2.5 percent up to final completion, and under GCC 2015 it is retention in the ordinary sense; either way it is a figure with a release date attached.

Por que: Interim payments are cumulative, so the month's money is a difference between two totals rather than a total of its own. Computing it from the cumulative figure is what stops a line being paid twice or dropped entirely when a period is re-measured.
Route the payment valuation to the principal agent, and to whoever the contract adds after them. Keep the approval date, because the tax invoice follows the approval and the payment clock runs from there, so an approval that slips moves everything behind it. The principal agent's approval is the interim payment certificate itself, issued by the date for issue the contract data fixes each month. Record that date beside the day the certificate actually arrived, because the payment count runs from the first and a certificate issued late does not move it.

Por que: Approval sitting in an inbox is the most common reason a payment is late, and it is invisible while it is happening because nobody has refused anything. A route with a date on each hop turns that into a question with an owner instead of a monthly complaint.
Raise the tax invoice against the approved payment valuation, carrying retention and any deduction the contract provides for, and reference the payment valuation on it. Quote the certificate number and the certified amount on the invoice, since the employer's accounts pay against the certificate and not against the valuation.

Por que: A demand for a figure nobody approved is one that will be returned, and the clock does not start on a returned document. Matching it to the payment valuation also means the accounts and the valuation tell the same story at year end without anybody reconciling them by hand.
Open a clock over the tax invoice starting from the date for issue of the payment certificate fixed in the contract data, under the JBCC payment clause. Payment falls due 14 calendar days later, and the clock records that date rather than leaving it to be worked out when somebody asks.
Por que: The single most expensive mistake in interim payment is starting the count on the wrong event, because every deadline behind it inherits the error and none of them look wrong. Anchoring on the date for issue of the payment certificate fixed in the contract data once makes the whole chain checkable. Opening it on the day the certificate arrived, or on your own invoice date, moves every deadline later and does it silently, which is the version of this mistake that never gets caught, because nothing looks overdue until the remedy has already expired. The agreement counts from the date the certificate was due, so a principal agent who issues late has not bought the employer a day.
Read back the dates the JBCC payment clause produces from the date for issue of the payment certificate fixed in the contract data. The sum payable leads, the due date and the final date for payment sit under it, and the derivation spells out each date against the provision it came from, so every one of them can be quoted rather than asserted. There is no statute behind these dates, so the only authority is the agreement: fourteen calendar days from the date for issue under JBCC 6.2, seven more for the money to reach each subcontractor, and GCC 2015 running its own longer count from the engineer's certificate. The row the clock is opened on has to carry the count the agreement gives, and its derivation is what you quote.
Por que: Deadlines that are typed in are deadlines that are typed in wrong, and a payment regime has more of them than anyone holds in their head. A derivation you can read out loud is what turns a phone call about a late payment into a quotable line.
Come back to the list as the month runs. It says how many clocks the project carries and how many are past their final date, badges the overdue ones and fills the breach register underneath. Open an overdue one and the findings name the sum outstanding, the days it has run past the final date and the rate interest runs at.
Por que: Reading a clock is what writes its register, so a quiet register on a project nobody opens is telling you about the reading and not about the payments. Nobody misses a deadline on purpose; they miss it because the day it mattered looked like every other day.
When the clock has run out, give the employer the five working days notice to comply that the JBCC agreement requires, and if it passes unpaid suspend the works, exercise the lien or call up the payment guarantee. The record the steps above produced, dates, approvals and the documents themselves, is the case, and it is assembled already rather than reconstructed under time pressure.

Por que: The difference between a claim that is paid and one that is argued about is almost never the merits. It is whether the dates and the documents were kept as the work happened, because reconstructing them afterwards is expensive and looks exactly like inventing them.
6 / 190 módulos de la plataforma
Todo en este caso sigue la forma en que la obra se mide, se valora y se paga en este mercado. Los documentos, el desglose de costes y las reglas de pago son los que se usan allí, no una versión genérica.
Normas que sigue
No tienes que configurar nada de eso a mano. La primera vez que abres la plataforma te pregunta en qué mercado trabajas. Elige este y ajusta el idioma de la interfaz, carga la base de costes correspondiente, registra la clasificación de costes y añade un proyecto de ejemplo que puedes abrir enseguida.
Las comprobaciones de este mercado también vienen con la plataforma. Actívalas una vez y un presupuesto al que le falte algo que el mercado espera queda señalado mientras trabajas en él, no después de presentar la oferta.
Registra un cambio de alcance mientras está reciente, valóralo como una modificación contrac…
Adjudica un paquete de trabajos a un subcontratista, formalízalo en un subcontrato con un cu…
Valora la obra ejecutada este periodo frente al contrato, presenta la solicitud con su docum…