إبقاء orçamento estimado sigiloso بموجب Lei 14.133

أعدّ الـ orçamento estimado، قرر وبرّر سريّته، انشر quantitativos دون أسعار، ضع النسخة المسعّرة خلف ضبط وصول، وانشرها في التاريخ الذي يشترطه القانون، مع توثيق التاريخ.

6 خطوة14 دقيقةمطوّر / عميلمكتب إدارة المشاريع / الإنشاءاستشارات التكاليف / قياس الكميات

كيف يعمل، خطوة بخطوة

6 خطوات عبر المنصة - ما تفعله في كل منها ولماذا يهم.

1

Build the orcamento estimado in one place

جدول الكميات

Price the whole scope in the bill, with quantities per item and a unit cost against each, so the priced and unpriced versions are two views of one document rather than two spreadsheets somebody keeps in step by hand.

لقطة شاشة، الخطوة 1: Build the orcamento estimado in one place (جدول الكميات, إبقاء orçamento estimado sigiloso بموجب Lei 14.133)
جدول الكميات: Build the orcamento estimado in one place

لماذا: The moment there are two files, one of them is out of date and nobody knows which. Bidders then price quantities that the confidential estimate no longer contains, and the difference surfaces at the first medicao as work that was never in anybody's proposal.

المدخلاتDesign and its quantitiesReference price baseالمخرجاتPriced orcamento estimadoQuantitativos per item
2

Decide sigilo, and write down why

المناقصات

Settle whether this procedure runs with a confidential estimate, write the justification into the tender record before the edital is published, and name the officers who may see the priced version. Note the moment at which it becomes public, because that is a term of the decision and not an afterthought.

لقطة شاشة، الخطوة 2: Decide sigilo, and write down why (المناقصات, إبقاء orçamento estimado sigiloso بموجب Lei 14.133)
المناقصات: Decide sigilo, and write down why

لماذا: Article 24 of Lei 14.133 of 2021 makes confidentiality conditional on a justification, so an estimate withheld without one is simply an estimate that was not published. Deciding before the edital also settles the question for everybody at once, instead of leaving each person to guess what may be sent to a bidder who asks.

المدخلاتProcurement route chosenPriced orcamento estimadoالمخرجاتConfidentiality decision recordedJustification on the record
3

Publish the quantitativos without the prices

التقارير

Export the bill with the items, the units and the quantities and without any cost column, then read the export itself before it goes out. Check the totals row, the group subtotals and any figure carried in a note, because those are where a price survives an unpriced export.

لقطة شاشة، الخطوة 3: Publish the quantitativos without the prices (التقارير, إبقاء orçamento estimado sigiloso بموجب Lei 14.133)
التقارير: Publish the quantitativos without the prices

لماذا: Confidentiality under Lei 14.133 of 2021 covers the prices, not the quantities, so an edital that publishes neither is not more careful, it is defective: bidders cannot price work whose extent they have not been told. And a single surviving subtotal defeats the whole decision, because the unit cost can be inferred from it.

المدخلاتQuantitativos per itemConfidentiality decision recordedالمخرجاتUnpriced bill for the editalReport checked for stray prices
4

Keep the priced version where only named people reach it

المستندات

File the priced estimate in the document register with access limited to the officers the decision names, and let the system record who opened it and when. Do not circulate it by email, because an attachment forwarded once is outside every control you have.

لقطة شاشة، الخطوة 4: Keep the priced version where only named people reach it (المستندات, إبقاء orçamento estimado sigiloso بموجب Lei 14.133)
المستندات: Keep the priced version where only named people reach it

لماذا: If the estimate does leak, the question that follows is not whether it leaked but who could have seen it, and the answer has to be a list rather than a guess. A folder with a named group and an access log answers it in a minute; a file that lived in six mailboxes cannot be answered at all, and the procedure is cancelled while nobody is proved to have done anything.

المدخلاتPriced orcamento estimadoOfficers named on the decisionالمخرجاتPriced version filed with access limitedAccess log kept
5

Compare the proposals against the estimate nobody saw

إدارة العطاءات

Load the proposals against the same item list and read them item by item rather than on the total alone. Look for the positions priced far below the estimate as well as far above, and ask what the bidder thinks the item contains.

لماذا: A confidential estimate makes the comparison worth doing, because the prices were formed without sight of it and a wide spread on one item means the item is ambiguous rather than that one bidder is careless. That is the reading that improves the next edital, and it is only available before the estimate is disclosed.

المدخلاتUnpriced bill for the editalProposals receivedالمخرجاتBid comparison against the estimateItems priced far from the estimate
6

Disclose it when the law says, and record the date

المراسلات

Release the priced estimate into the procurement record at the point the decision named, log the release in the correspondence file, and lift the access restriction so nobody has to ask. Say plainly which version was released, by reference rather than by description.

لقطة شاشة، الخطوة 6: Disclose it when the law says, and record the date (المراسلات, إبقاء orçamento estimado sigiloso بموجب Lei 14.133)
المراسلات: Disclose it when the law says, and record the date

لماذا: Confidentiality under Lei 14.133 of 2021 is temporary by design, and the failure is almost always inertia rather than intent: the procedure ends, the folder stays closed and nobody is watching a date that produces no event. Logging the release makes the end of the confidentiality as visible as its beginning, which is the part an audit asks about.

المدخلاتConfidentiality decision recordedPriced orcamento estimadoالمخرجاتEstimate published to the fileDisclosure date on the record
الوحدات

وحدات هذا الدليل

6 / 190 من وحدات المنصة

The market this case is written for

البرازيل

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • Lei 14.133
  • SINAPI
  • ABNT NBR 12721

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

المزيد في المناقصات والمشتريات

المناقصات والمشتريات

إجراء مناقصة من BOQ

اطرح جدول كميات مسعّراً في السوق: حزّمه، وادعُ مقاولي الباطن، وسوِّ عروضهم، وأرسِ على الفائز…

5 خطوة12 دقيقةفتح
المناقصات والمشتريات

توريد المواد من BOQ

اشترِ الكميات التي سعّرتها بالفعل: أنشئ طلب شراء من الجدول، وضع الأمر لدى مورّد، وسجّل استلا…

4 خطوة10 دقيقةفتح
المناقصات والمشتريات

مقارنة العطاءات والترسية

خذ مجلد عطاءات مُعادة لا تتطابق تماماً، وأرجعها إلى النطاق نفسه، وسلّم العميل قرار ترسية يصم…

3 خطوة12 دقيقةفتح