Cases / Udbud og indkøb
Udbud og indkøb

Hold orçamento estimado sigiloso under Lei 14.133

Byg orçamento estimado, afgør og begrund om det er fortroligt, offentliggør quantitativos uden priserne, hold den prissatte version bag adgangskontrol, og offentliggør den på den dato loven kræver, med datoen i journalen.

6 trin14 minUdvikler / bygherreProjekt- / byggeledelsesfirmaOmkostnings- / mængderådgivning

Sådan fungerer det, trin for trin

6 trin gennem platformen - hvad du gør i hvert, og hvorfor det betyder noget.

1

Build the orcamento estimado in one place

Tilbudsliste

Price the whole scope in the bill, with quantities per item and a unit cost against each, so the priced and unpriced versions are two views of one document rather than two spreadsheets somebody keeps in step by hand.

Skærmbillede, trin 1: Build the orcamento estimado in one place (Tilbudsliste, Hold orçamento estimado sigiloso under Lei 14.133)
Tilbudsliste: Build the orcamento estimado in one place

Hvorfor: The moment there are two files, one of them is out of date and nobody knows which. Bidders then price quantities that the confidential estimate no longer contains, and the difference surfaces at the first medicao as work that was never in anybody's proposal.

InputDesign and its quantitiesReference price baseResultatPriced orcamento estimadoQuantitativos per item
2

Decide sigilo, and write down why

Udbud

Settle whether this procedure runs with a confidential estimate, write the justification into the tender record before the edital is published, and name the officers who may see the priced version. Note the moment at which it becomes public, because that is a term of the decision and not an afterthought.

Skærmbillede, trin 2: Decide sigilo, and write down why (Udbud, Hold orçamento estimado sigiloso under Lei 14.133)
Udbud: Decide sigilo, and write down why

Hvorfor: Article 24 of Lei 14.133 of 2021 makes confidentiality conditional on a justification, so an estimate withheld without one is simply an estimate that was not published. Deciding before the edital also settles the question for everybody at once, instead of leaving each person to guess what may be sent to a bidder who asks.

InputProcurement route chosenPriced orcamento estimadoResultatConfidentiality decision recordedJustification on the record
3

Publish the quantitativos without the prices

Rapporter

Export the bill with the items, the units and the quantities and without any cost column, then read the export itself before it goes out. Check the totals row, the group subtotals and any figure carried in a note, because those are where a price survives an unpriced export.

Skærmbillede, trin 3: Publish the quantitativos without the prices (Rapporter, Hold orçamento estimado sigiloso under Lei 14.133)
Rapporter: Publish the quantitativos without the prices

Hvorfor: Confidentiality under Lei 14.133 of 2021 covers the prices, not the quantities, so an edital that publishes neither is not more careful, it is defective: bidders cannot price work whose extent they have not been told. And a single surviving subtotal defeats the whole decision, because the unit cost can be inferred from it.

InputQuantitativos per itemConfidentiality decision recordedResultatUnpriced bill for the editalReport checked for stray prices
4

Keep the priced version where only named people reach it

Dokumenter

File the priced estimate in the document register with access limited to the officers the decision names, and let the system record who opened it and when. Do not circulate it by email, because an attachment forwarded once is outside every control you have.

Skærmbillede, trin 4: Keep the priced version where only named people reach it (Dokumenter, Hold orçamento estimado sigiloso under Lei 14.133)
Dokumenter: Keep the priced version where only named people reach it

Hvorfor: If the estimate does leak, the question that follows is not whether it leaked but who could have seen it, and the answer has to be a list rather than a guess. A folder with a named group and an access log answers it in a minute; a file that lived in six mailboxes cannot be answered at all, and the procedure is cancelled while nobody is proved to have done anything.

InputPriced orcamento estimadoOfficers named on the decisionResultatPriced version filed with access limitedAccess log kept
5

Compare the proposals against the estimate nobody saw

Tilbudsstyring

Load the proposals against the same item list and read them item by item rather than on the total alone. Look for the positions priced far below the estimate as well as far above, and ask what the bidder thinks the item contains.

Hvorfor: A confidential estimate makes the comparison worth doing, because the prices were formed without sight of it and a wide spread on one item means the item is ambiguous rather than that one bidder is careless. That is the reading that improves the next edital, and it is only available before the estimate is disclosed.

InputUnpriced bill for the editalProposals receivedResultatBid comparison against the estimateItems priced far from the estimate
6

Disclose it when the law says, and record the date

Korrespondance

Release the priced estimate into the procurement record at the point the decision named, log the release in the correspondence file, and lift the access restriction so nobody has to ask. Say plainly which version was released, by reference rather than by description.

Skærmbillede, trin 6: Disclose it when the law says, and record the date (Korrespondance, Hold orçamento estimado sigiloso under Lei 14.133)
Korrespondance: Disclose it when the law says, and record the date

Hvorfor: Confidentiality under Lei 14.133 of 2021 is temporary by design, and the failure is almost always inertia rather than intent: the procedure ends, the folder stays closed and nobody is watching a date that produces no event. Logging the release makes the end of the confidentiality as visible as its beginning, which is the part an audit asks about.

InputConfidentiality decision recordedPriced orcamento estimadoResultatEstimate published to the fileDisclosure date on the record
Moduler

Moduler i denne playbook

6 / 190 platformmoduler

The market this case is written for

Brasilien

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • Lei 14.133
  • SINAPI
  • ABNT NBR 12721

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Mere inden for Udbud og indkøb

Udbud og indkøb

Kør et udbud ud fra en BOQ

Tag en prissat tilbudsliste ud på markedet: pak den, invitér underentreprenørerne, nivellér…

5 trin12 minÅbn
Udbud og indkøb

Indkøb materialer ud fra BOQ'en

Køb de mængder, du allerede har prissat: opret en rekvisition ud fra tilbudslisten, afgiv or…

4 trin10 minÅbn
Udbud og indkøb

Sammenlign tilbud og tildel

Tag en mappe med indkomne tilbud, der aldrig helt matcher, skær dem tilbage til det samme om…

3 trin12 minÅbn