Stil de tre fianzas og frigiv dem i rækkefølge

Stil fianza de cumplimiento inden for de dage, tildelingen giver, sikr anticipo, før pengene bevæger sig, hold alle tre kautioner i et register med deres datoer, påtegn dem, når en convenio modificatorio ændrer kontrakten, og annullér hver enkelt på den begivenhed, der faktisk afslutter dens risiko.

6 trin16 minHovedentreprenørFagentreprenørUdvikler / bygherre

Sådan fungerer det, trin for trin

6 trin gennem platformen - hvad du gør i hvert, og hvorfor det betyder noget.

1

Deliver the fianza de cumplimiento inside the days you have

Kontrakter

As soon as the fallo is notified, have the afianzadora issue the fianza de cumplimiento on the terms the convocatoria set, in favour of the dependencia, and deliver it. The period is fifteen days following the notification of the award where the convocatoria does not name another one. Record the delivery date on the contract, not only the date on the bond.

Skærmbillede, trin 1: Deliver the fianza de cumplimiento inside the days you have (Kontrakter, Stil de tre fianzas og frigiv dem i rækkefølge)
Kontrakter: Deliver the fianza de cumplimiento inside the days you have

Hvorfor: This is one of the few deadlines on a Mexican public contract that can cost you the contract itself rather than money, and it lands in the week everyone is celebrating. It is short by design and it starts on a notification rather than on a signature, so a firm that waits for the contract to be drafted before calling the afianzadora has already spent most of it.

InputNotification of the awardBond terms the convocatoria setsResultatFianza de cumplimiento deliveredDelivery date against the deadline
2

Secure the anticipo before the money moves

Finans

Put the fianza de anticipo in place for the whole of the advance before any part of it is paid over, and record it against the anticipo rather than against the contract in general. Where the anticipo is granted in parts, make sure the security covers the part being released.

Skærmbillede, trin 2: Secure the anticipo before the money moves (Finans, Stil de tre fianzas og frigiv dem i rækkefølge)
Finans: Secure the anticipo before the money moves

Hvorfor: It secures a different thing from the fianza de cumplimiento, which is why it exists separately: money handed over before there is any work to look at. That also decides when it ends. It follows the amortizacion, not the completion of the works, so on a job that finishes with the advance not fully repaid this bond outlives the project and nobody expects it to.

InputAnticipo the contract grantsWhen each part is to be paidResultatFianza de anticipo in placePayment released against the security
3

Keep the three in one register with their dates

Frister

Enter each bond once with the four things anybody will ever ask: what it secures, its amount, the afianzadora and policy number, and the event that ends it. Then set the dates that follow from those events, so the register is what gets read rather than the folder of PDFs.

Hvorfor: Bonds fail quietly in both directions. One that expires while the risk is still live leaves the works unsecured and the dependencia entitled to say so; one that outlives its risk goes on charging a premium every year until somebody notices, which on a portfolio of finished jobs is a real number nobody has ever added up.

InputBonds issued so farEvents that end each riskResultatOne register, three bonds, datedAn owner against each date
4

Endorse the bonds when a convenio moves the contract

Ændringsordrer

Every convenio modificatorio that raises the contract amount or extends the term is a change to the security as well as to the works. Have the fianza de cumplimiento endorsed for the new amount and the new period, and update the register from the endorsement rather than from the convenio.

Skærmbillede, trin 4: Endorse the bonds when a convenio moves the contract (Ændringsordrer, Stil de tre fianzas og frigiv dem i rækkefølge)
Ændringsordrer: Endorse the bonds when a convenio moves the contract

Hvorfor: An increase agreed but not endorsed leaves the extra work unsecured, which is a finding the moment anybody audits the file and an argument the dependencia can use to hold an estimacion. It is invisible while it lasts, because the convenio is signed, the works are proceeding and the original bond is still perfectly valid for the amount it was written for.

InputConvenio modificatorioBonds as currently issuedResultatEndorsement matching the new amountNo unsecured increase left open
5

Put up the vicios ocultos security before the acta

Afslutning

Before the acta de entrega-recepcion is signed, provide the guarantee article 66 LOPSRM requires against defects and hidden vices for the twelve months that follow. The article lets you choose the form: a fianza, an irrevocable letter of credit, or an amount placed in trust. Choose it on cash rather than habit, and diarise the day the twelve months end.

Skærmbillede, trin 5: Put up the vicios ocultos security before the acta (Afslutning, Stil de tre fianzas og frigiv dem i rækkefølge)
Afslutning: Put up the vicios ocultos security before the acta

Hvorfor: It has to exist before the works are received, so it is prepared during the busiest fortnight of the job or it delays the acta, and a delayed acta delays the finiquito and everything behind it. The choice of form is worth an hour: a trust deposit ties up cash for a year while a fianza costs a premium, and the right answer depends on which of those the firm has less of.

InputDate set for the recepcion fisicaMonto total ejercidoResultatVicios ocultos security in placeTwelve month period diarised
6

Cancel each bond on the event that ends its risk

Dokumenter

Release the fianza de anticipo when the advance reaches zero, the fianza de cumplimiento against the finiquito and the acta administrativa that extinguishes the rights and obligations, and the vicios ocultos security when the twelve months are up with no claim outstanding. File the paper the afianzadora needs against each one, because a cancellation is granted on evidence rather than on a request.

Skærmbillede, trin 6: Cancel each bond on the event that ends its risk (Dokumenter, Stil de tre fianzas og frigiv dem i rækkefølge)
Dokumenter: Cancel each bond on the event that ends its risk

Hvorfor: Nobody is chasing you to stop paying, so this is the step that gets skipped on every job that ends well. The cost is not only the premium: an open bond consumes the line the afianzadora will extend you, and a firm bidding its next contract discovers its capacity is committed to three jobs it finished years ago.

InputFiniquito and acta administrativaAnticipo balance at zeroResultatEach bond cancelled on its own eventPremiums stopped
Moduler

Moduler i denne playbook

6 / 190 platformmoduler

The market this case is written for

Mexico

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CFDI 4.0
  • Ley de Obras Publicas

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Mere inden for Kommercielt og kontrakter

Kommercielt og kontrakter

Kør en underentreprenørpakke

Tildel en fagpakke til en underentreprenør, læg den på en underentreprise med en betalingspl…

3 trin11 minÅbn
Kommercielt og kontrakter

Betalingsanmodning og afstemning

Værdisæt det arbejde, der er udført i denne periode, op mod kontrakten, opret betalingsanmod…

3 trin12 minÅbn