Mga Kaso / Commercial at kontrata
Commercial at kontrata

Ilagay ang tatlong fianzas at ilabas ang mga ito sa tamang pagkakasunod

Ihain ang fianza de cumplimiento sa loob ng mga araw na pinapayagan ng award, seguruhin ang anticipo bago gumalaw ang pera, itago ang tatlong bono sa isang rehistro kasama ang kanilang mga petsa, i-endorse ang mga ito kapag binago ng isang convenio modificatorio ang kontrata, at kanselahin ang bawat isa sa pangyayaring tunay na nagwawakas sa panganib nito.

6 hakbang16 minGeneral ContractorEspesyalistang SubcontractorDeveloper / Kliyente

Paano ito gumagana, hakbang-hakbang

6 hakbang sa buong platform - ano ang gagawin mo sa bawat isa at bakit mahalaga ito.

1

Deliver the fianza de cumplimiento inside the days you have

Mga Kontrata

As soon as the fallo is notified, have the afianzadora issue the fianza de cumplimiento on the terms the convocatoria set, in favour of the dependencia, and deliver it. The period is fifteen days following the notification of the award where the convocatoria does not name another one. Record the delivery date on the contract, not only the date on the bond.

Screenshot, hakbang 1: Deliver the fianza de cumplimiento inside the days you have (Mga Kontrata, Ilagay ang tatlong fianzas at ilabas ang mga ito sa tamang pagkakasunod)
Mga Kontrata: Deliver the fianza de cumplimiento inside the days you have

Bakit: This is one of the few deadlines on a Mexican public contract that can cost you the contract itself rather than money, and it lands in the week everyone is celebrating. It is short by design and it starts on a notification rather than on a signature, so a firm that waits for the contract to be drafted before calling the afianzadora has already spent most of it.

PapasokNotification of the awardBond terms the convocatoria setsLumalabasFianza de cumplimiento deliveredDelivery date against the deadline
2

Secure the anticipo before the money moves

Pananalapi

Put the fianza de anticipo in place for the whole of the advance before any part of it is paid over, and record it against the anticipo rather than against the contract in general. Where the anticipo is granted in parts, make sure the security covers the part being released.

Screenshot, hakbang 2: Secure the anticipo before the money moves (Pananalapi, Ilagay ang tatlong fianzas at ilabas ang mga ito sa tamang pagkakasunod)
Pananalapi: Secure the anticipo before the money moves

Bakit: It secures a different thing from the fianza de cumplimiento, which is why it exists separately: money handed over before there is any work to look at. That also decides when it ends. It follows the amortizacion, not the completion of the works, so on a job that finishes with the advance not fully repaid this bond outlives the project and nobody expects it to.

PapasokAnticipo the contract grantsWhen each part is to be paidLumalabasFianza de anticipo in placePayment released against the security
3

Keep the three in one register with their dates

Mga Deadline

Enter each bond once with the four things anybody will ever ask: what it secures, its amount, the afianzadora and policy number, and the event that ends it. Then set the dates that follow from those events, so the register is what gets read rather than the folder of PDFs.

Bakit: Bonds fail quietly in both directions. One that expires while the risk is still live leaves the works unsecured and the dependencia entitled to say so; one that outlives its risk goes on charging a premium every year until somebody notices, which on a portfolio of finished jobs is a real number nobody has ever added up.

PapasokBonds issued so farEvents that end each riskLumalabasOne register, three bonds, datedAn owner against each date
4

Endorse the bonds when a convenio moves the contract

Mga Change Order

Every convenio modificatorio that raises the contract amount or extends the term is a change to the security as well as to the works. Have the fianza de cumplimiento endorsed for the new amount and the new period, and update the register from the endorsement rather than from the convenio.

Screenshot, hakbang 4: Endorse the bonds when a convenio moves the contract (Mga Change Order, Ilagay ang tatlong fianzas at ilabas ang mga ito sa tamang pagkakasunod)
Mga Change Order: Endorse the bonds when a convenio moves the contract

Bakit: An increase agreed but not endorsed leaves the extra work unsecured, which is a finding the moment anybody audits the file and an argument the dependencia can use to hold an estimacion. It is invisible while it lasts, because the convenio is signed, the works are proceeding and the original bond is still perfectly valid for the amount it was written for.

PapasokConvenio modificatorioBonds as currently issuedLumalabasEndorsement matching the new amountNo unsecured increase left open
5

Put up the vicios ocultos security before the acta

Pagsasara

Before the acta de entrega-recepcion is signed, provide the guarantee article 66 LOPSRM requires against defects and hidden vices for the twelve months that follow. The article lets you choose the form: a fianza, an irrevocable letter of credit, or an amount placed in trust. Choose it on cash rather than habit, and diarise the day the twelve months end.

Screenshot, hakbang 5: Put up the vicios ocultos security before the acta (Pagsasara, Ilagay ang tatlong fianzas at ilabas ang mga ito sa tamang pagkakasunod)
Pagsasara: Put up the vicios ocultos security before the acta

Bakit: It has to exist before the works are received, so it is prepared during the busiest fortnight of the job or it delays the acta, and a delayed acta delays the finiquito and everything behind it. The choice of form is worth an hour: a trust deposit ties up cash for a year while a fianza costs a premium, and the right answer depends on which of those the firm has less of.

PapasokDate set for the recepcion fisicaMonto total ejercidoLumalabasVicios ocultos security in placeTwelve month period diarised
6

Cancel each bond on the event that ends its risk

Mga Dokumento

Release the fianza de anticipo when the advance reaches zero, the fianza de cumplimiento against the finiquito and the acta administrativa that extinguishes the rights and obligations, and the vicios ocultos security when the twelve months are up with no claim outstanding. File the paper the afianzadora needs against each one, because a cancellation is granted on evidence rather than on a request.

Screenshot, hakbang 6: Cancel each bond on the event that ends its risk (Mga Dokumento, Ilagay ang tatlong fianzas at ilabas ang mga ito sa tamang pagkakasunod)
Mga Dokumento: Cancel each bond on the event that ends its risk

Bakit: Nobody is chasing you to stop paying, so this is the step that gets skipped on every job that ends well. The cost is not only the premium: an open bond consumes the line the afianzadora will extend you, and a firm bidding its next contract discovers its capacity is committed to three jobs it finished years ago.

PapasokFiniquito and acta administrativaAnticipo balance at zeroLumalabasEach bond cancelled on its own eventPremiums stopped
Mga Module

Mga Module sa Playbook na Ito

6 / 190 na module ng platform

The market this case is written for

Mexico

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CFDI 4.0
  • Ley de Obras Publicas

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Higit pa sa Commercial at kontrata

Commercial at kontrata

Magsagawa ng Subcontractor Package

Igawad ang trade package sa isang subcontractor, ilagay ito sa subcontract na may schedule o…

3 hakbang11 minBukas